Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (DCF Central)
|
EDS
|
User Agency (meerut@nhai.org)
|
10/08/2021
|
Kindly resubmit the proposal with following documents
1. Final tree list with tree marking and girt calculation, botanical and common name of tree species.
2. The map showing site of compensatory afforestation according to GSDL geo coordinates.
2. Topo sheet of survey of India showing site of compensatory afforestation.
4. KML fle of the land proposed for compensatory afforestation.
|
|
2
|
User Agency (meerut@nhai.org)
|
REPLY
|
DFO (DCF Central)
|
27/08/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (DCF Central)
|
EDS
|
User Agency (meerut@nhai.org)
|
09/09/2021
|
Please submit the required details as per attached letter for EDS
|
|
4
|
User Agency (meerut@nhai.org)
|
REPLY
|
DFO (DCF Central)
|
13/04/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (DCF Central)
|
EDS
|
User Agency (meerut@nhai.org)
|
18/04/2022
|
The list of required documents are attached herewith
|
|
6
|
User Agency (meerut@nhai.org)
|
REPLY
|
DFO (DCF Central)
|
21/04/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (DCF Central)
|
EDS
|
User Agency (meerut@nhai.org)
|
22/04/2022
|
Kindly submit the documents as mentioned in EDS letter
|
|
8
|
User Agency (meerut@nhai.org)
|
REPLY
|
DFO (DCF Central)
|
23/04/2022
|
The correction have been made as per the instruction received
|
|
9
|
CF (Delhi)
|
EDS
|
DFO (DCF Central)
|
25/04/2022
|
As discussed, may please upload the necessary documents.
|
|
10
|
DFO (DCF Central)
|
REPLY
|
CF (Delhi)
|
25/04/2022
|
Requisite documents uploaded
|
|