TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/CG/OFC/59432/2020              (ii). Name of Project for which Forest Land is required : BharatNet Project Phase-II Katghora Forest Division              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Forest Land required for Optical Fibre Cable Laying works under National Optical Fibre Network Project of Bharat Broadband Network Limited (BBNL) for providing Broadband Connectivity from Poundi Uproda Block Headquarter to Gram Panchayats within Katghora Forest Division Katghora, District - Korba, C              (iv). File no. : F 5-03/2022/10-2              (v). State : Chhattisgarh              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 21.431
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/CG/OFC/59432/202025/11/202027/11/2020   03/12/2020   07/12/2020   30/12/2020 Katghora :31/12/2020Bilaspur(CG):
  28/10/2021 (Katghora)

Chhattisgarh:
17/11/2021
Chhattisgarh:
10/02/2022
24/03/2022
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .