TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/BR/ROAD/46901/2020              (ii). Name of Project for which Forest Land is required : Improvement Two Laning with paved shoulder of stretch from Bikramganj – Dawath – Maliyabagh – Nawanagar – Dumraon of NH– 120 (Ch. 201.665 to Ch 245.665) in the State of Bihar. (Excluded Area Dawath (C              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The National Highway Division, Gaya Bihar has decided to Concentric Up-gradation Widening and strengthening work of existing Two Laning with paved shoulder of stretch from Bikramganj – Dawath – Maliyabagh – Nawanagar – Dumraon of NH– 120 (Ch. 201.665 to Ch 245.665) excluding Dawath (Ch. 210.830 to C              (iv). File no. : FP/BR/ROAD/46901/2020              (v). State : Bihar              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 41.01
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/BR/ROAD/46901/202029/06/202007/08/2020   09/09/2021   07/05/2022   11/10/2022

Rohtash :11/10/2022


Bhojpur :11/10/2022

Patna:
  18/10/2022 (Bhojpur)

WildLife:
  19/10/2022 (Rohtash)

Bihar:
19/10/2022
Bihar:
19/10/2022
Ranchi:
10/11/2022
28/04/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Ranchi) on:21/12/2022  
Replied by State Government(Bihar) on:23/02/2023  
Query raised by Regional Office (Ranchi) on:29/03/2023  
Replied by State Government(Bihar) on:19/04/2023  
Query raised by State Government (Bihar) on:24/01/2023  
Replied by Nodal Officer (Bihar) on:23/02/2023  
Query raised by State Government (Bihar) on:11/04/2023  
Replied by Nodal Officer (Bihar) on:19/04/2023  
Query raised by Nodal Officer (Bihar) on:24/01/2023  
Replied by Circle(Patna) on:16/02/2023  
Query raised by Nodal Officer (Bihar) on:24/01/2023  
Replied by Circle(WildLife) on:16/02/2023  
Query raised by Nodal Officer (Bihar) on:11/04/2023  
Replied by Circle(Patna) on:12/04/2023  
Query raised by Nodal Officer (Bihar) on:11/04/2023  
Replied by Circle(WildLife) on:13/04/2023  
Query raised by Circle (Patna) on:24/01/2023  
Replied by DFO (Rohtash) on:16/02/2023  
Query raised by Circle (WildLife) on:24/01/2023  
Replied by DFO (Bhojpur) on:16/02/2023  
Query raised by Circle (Patna) on:11/04/2023  
Replied by DFO (Bhojpur) on:12/04/2023  
Query raised by DFO (Rohtash) on:24/01/2023  
Replied by UA on :16/02/2023  
Query raised by DFO (Bhojpur) on:11/04/2023  
Replied by UA on :12/04/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .