TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/BR/ROAD/129045/2021              (ii). Name of Project for which Forest Land is required : Forest Clearance for Two Laning with paved shoulder of stretch from Junction of NH-22 near Hazipur to junction of NH-122 at Bachhwara via Mahanar and Mohiuddin Nagar of NH- 122 B (Ch. 0.000 to Ch 72.9              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The National Highway Division, Biharsharif, Bihar has decided to Concentric Up-gradation Widening and strengthening work of existing Two Laning with paved shoulder of stretch from Junction of NH-22 near Hazipur to junction of NH-122 at Bachhwara via Mahanar and Mohiuddin Nagar of NH- 122 B (Ch. 0.00              (iv). File no. : FP/BR/ROAD/129045/2021              (v). State : Bihar              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 97.3934
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/BR/ROAD/129045/202120/03/202116/04/2021  01/04/2021   20/04/2021  06/04/2021   22/04/2021   02/01/2023

Saran :02/01/2023


Bagusarai :02/01/2023

Siwan:
  02/01/2023 (Saran)

Muzaffarpur:
  02/01/2023 (Bagusarai)

Bihar:
02/01/2023
Bihar:
02/01/2023
Ranchi:
04/01/2023
28/04/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Ranchi) on:27/02/2023  
Replied by State Government(Bihar) on:18/04/2023  
Query raised by State Government (Bihar) on:04/03/2023  
Replied by Nodal Officer (Bihar) on:18/04/2023  
Query raised by Nodal Officer (Bihar) on:06/03/2023  
Replied by Circle(Siwan) on:18/04/2023  
Query raised by Nodal Officer (Bihar) on:06/03/2023  
Replied by Circle(Muzaffarpur) on:18/04/2023  
Query raised by Circle (Siwan) on:06/03/2023  
Replied by DFO (Saran) on:18/04/2023  
Query raised by DFO (Saran) on:06/03/2023  
Replied by UA on :17/04/2023  
Query raised by DFO (Saran) on:17/04/2023  
Replied by UA on :18/04/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .