PART-II
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
(To be filled by the concerned Deputy Conservator of Forest)
State Serial No. of proposal :
UK-0114/2022
1.
Location of the project/Scheme :
Uttarakhand
(i)
State / Union Territory :
Uttarakhand
(ii)
District :
Pauri Garhwal
(iii)
Forest Division :
Lansdowne
 (iv)
Area of forest land proposed for diversion (in ha.) :
1.1
 (v)
Category of the Proposal:
Road
2.
Legal status of forest land proposed for diversion
S. No.
Division
Forest Land(ha.)
Legal Status
1
Lansdowne
1.1
Reserved Forest
Total
1.1
Division 1. : Lansdowne
3.
District wise area to be diverted in the division
S. No.
District
Area(ha.)
1
Pauri Garhwal
1.1
Total
1.1
4.
Details of Vegetation available in the forest land proposed for diversion
(i)
Density of vegetation
S. No.
Area(in ha.)
Density
Eco-Class
1
1.1
0.5
Eco 3
Total.
1.1
(ii)
Species-wise local/scientific names and girth-wise enumeration of trees at FRL
S. No.
Scientific Name
Local Name
(0-30)cm.
(31-60)cm.
(61-90)cm.
(91-120)cm.
(121-150)cm.
(>150)cm.
1
Mangifera Indica
Aam
0
4
6
1
3
2
2
Cassia Fistula
amaltas
0
1
2
1
0
0
3
Eucalyptus
Eucalyptus
0
0
0
0
0
2
4
Adina cordifolia
haldu
0
1
0
0
0
9
5
Melia Azadirachta
bakain
0
0
2
0
1
0
6
Artocarpus Heterophyllus
kathal
0
1
2
0
0
0
7
Others
kikar
0
0
1
0
0
0
8
Schreberaswictinioibes
kusum
0
0
0
0
0
1
9
Others
nimboo
0
1
0
0
0
0
10
Sapindus mukorossi
rith
0
0
1
1
0
0
11
Tectona Grandis
sagaun
0
0
0
1
0
0
12
Alstonia Scholaris
saptparn
0
1
0
0
0
0
13
Grevillea robusta
silver oak
0
0
1
3
0
0
14
Albizzia lebbeck
siras
0
0
0
0
0
1
15
Others
taru
0
0
1
2
2
0
16
Others
myroxylon
0
2
0
0
1
0
17
Aegle Marmelos
bel
0
0
1
1
0
0
18
Ficus Religiosa
pepal
0
0
0
0
1
0
19
Holoptelia integrifolia
kanju
1
8
3
5
5
13
20
Melotus Philippensis
Rohini
2
0
0
0
0
0
Total
3
19
20
15
13
28
Sub Total (No of Trees.)
98
5.
Working plan prescription for the forest land proposed for diversion :
As per the Working plan ,The maintained area is under the protection and improvement minutes.
6.
Brief note on vulnerability of the forest area to erosion :
At present the proposed site dose't seen to be vulnerable to soil erosion.
7.
Approximate distance of the proposed site for diversion from boundary of forest(in km.) :
0
8.
Significance of the forest land proposed for diversion from wildlife point of view
(i).
Details of wildlife present in and around the forest land proposed for diversion :
elephant, monkey , leopard etc
(ii).
Whether forms part of national park, wildlife sanctuary, biosphere reserve,tiger reserve, elephant corridor, wildlife migration corridor etc. :
Yes
Details and comments on the impact of Project on such areas :
It is Notified as part of Shivalik Elephant Reserve and also notified part of buffer zone of Rajaji tiger reserve. Apart from buffer zone of Raja ji national park ,t is also act as corridor for the free movement of elephants in the area .Eco-friendly measures to mitigate impact impact of road needs to be taken up .
(iii).
Whether the forest land proposed for diversion is located within eco-sensitive zone(ESZ) of the Protected Area notified under Wildlife(Protection) Act,1972 (Note: In case, ESZ of a Protected Area is not notified,then,10kms distance from boundary of the Protected Area should be treated as ESZ):
No
(iv).
Whether any national park, wildlife sanctuary, biosphere reserve, tiger reserve, elephant corridor, wildlife migration corridor etc., is located within 1 Km. from boundary of the forest land proposed for diversion :
Yes
Details and comments on the impact of Project on such areas :
It is Notified as part of Shivalik Elephant Reserve and also notified part of buffer zone of Rajaji tiger reserve. Apart from buffer zone of Raja ji national park ,t is also act as corridor for the free movement of elephants in the area .Eco-friendly measures to mitigate impact impact of road needs to be taken up
(v).
Whether any rare/endangered/unique species of flora and fauna found in the area :
No
9.
Details of any protected archaeological/heritage site/defence establishment or any other important monument located in the area, if any
(i).
Whether any protected archaeological/heritage site/defence establishment or any other important monument is located in the area :
No
10.
Comment as to the reasonability of the extent of the forest land proposed for diversion
(i).
Whether the requirement of forest land as proposed by the user agency is unavoidable and bare minimum for the project :
Yes
11.
Details of violation(s), if any ,committed
(i).
Whether any work in violation of the Act or guidelines issued under the Act has been carried out :
No
12.
Whether work in violation is still in progres(Yes/No) :
NIL
13.
Details of compensatory afforestation scheme
(i).
Patch wise details of non-forest or Revenue forest land to be provided by User Agency for CA
Patch Wise Details
S.no
District Name
Village
Area(in ha.)
khasra
KML file
Present Owner file
1
Pauri Garhwal
Mohini Akari Sakri Pujari
1.1
585
(ii).
Upload a scanned copy of the Geo-referenced map of the forest land proposed for C.A. prepared by using DGPS or Total Station:
(iii).
Upload a copy of Survey of India Toposheet indicating boundary of forest land proposed for C.A:
(iv).
Copy of CA scheme details:
(iv).
Copy of CA scheme details:
NA
Additional information Details
S. No.
Documents
Remarks
1
BarChart
2
Map
3
Land Schedule
4
Undertaking for FRA Certificate
5
Geologist Report
6
Forest & Non-Forest land details
7
Undertaking for the proposed project is not a part of Protected Area or National Park
8
Statement showing Details showing area of forest Land
9
Length & width certificate
10
muck disposal plan
11
Joint inspection report
12
Length width certificate
13
Aerial distance Certificate 1
14
List of trees affected
15
Justification
16
Proof of non-availability of alternative land
17
Certificate for the proposed project is not a part of Monument or religious place
18
certificate of non-commencement
19
EDS Reply with Cover Letter of KOTDWAR by pass road
20
NPV Calculation
21
Point wise report of objections raised by Government of India on 1/2/25
22
EDS Reply By NHAI
23
Cover letter regarding CA land details
24
Complaint Resolution Details
25
SIR NEW FORMATE
26
Minutes of meeting of NBWL for Wild life Clearance of 1.1 Ha Forest Land
14.
District Profile
S.no
District Name
Geographical area of the district (in ha.)
Forest area of the district (in ha.)
Total forest area diverted since 1980 (in ha.)
No. of Approved Cases
Forest Land including penal C.A. (in ha.)
Progress of compensatory afforestation as on(date)
A) Forest land (in ha.)
B) Non-forest land (in ha.)
1
Pauri Garhwal
532900
385094.2
1597.8
485
1935.8
30/06/2020
1587.7076
710.51
15.
Site inspection report of the DFO/CCF/Nodal Officer highlighting important facts pertaining to the forest land
Division Name
Circle
Site inspected By
Whether site inspected
No. of times site visited
Site inspection report
Date of visit
Lansdowne
Shivalik
DFO
Yes
One
29/08/2023
Shivalik
CF
No
No Data
(Specific recommendation of the DFO/CCF/Nodal Officer with(Part II,III & Part IV))
16.
Specific recommendation of the DFO/CCF/Nodal Officer for acceptance or otherwise of the proposal with reason
Division
Circle
Recommendation By
Recommendation
Reason
Letter
Whether CF agreed
Lansdowne
Shivalik
DFO
Recommended
Recommended for approval in public interest.
Shivalik
CF
Recommended
Yes
Nodal Officer
Recommended
Recommended
Specific recommendation of the State Government(Part V)
17.
Specific recommendation of the State Government for acceptance or otherwise of the proposal with reason ( Part V)
State
Recommendation By
Recommendation
Recommendation Date
Remarks
Signing Authority
Notification
Recommendation Letter
Uttarakhand
State Secretary
Recommended
12/09/2024
Recommendation
State Govt. Officer
No Data
17.
Stage-I Clearance Report
Regional Office
Recommendation By
MoEF File No.
Date of Stage-I Clearance
Clearance Letter
Dehradun
Regional Office
8B/UCP/06/35/2024/FC8B/UCP/06/35/2024/FC
05/05/2025
18.
Payment made by User Agency
Proposal No.
Application No.
Total Amount (Rs.)
Recieved Amount (Rs.)
Transaction Date
Transaction ID
Bank Name
Mode of Payment
Demmand Generated By User Agency
Demmand Verified By Nodal Officer
Uploaded Demand Letter
FP/UK/ROAD/157584/2022
ROAD1575842022155
14,948,789.70
14,948,800.00
Union Bank Of India
NEFT/RTGS (Challan)
17/06/2025
17/06/2025
23.
Stage-II Clearance Details
Proposal No.
Date of Stage-II Clearance
Proposal Status
Clearance Letter
FP/UK/ROAD/157584/2022
Approved In-Principle
No Data
Print
Checklist for State Nodal Officer
×