FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/CG/Others/7694/2014   (ii). Name of Project for which Forest Land is required : NMDC SLURRY PIPELINE PROJECT   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : NMDC INTENDS TO TRANSPORT BENEFICIATED IRON ORE CONCENTRATE THROUGH UNDERGROUND SLURRY PIPELINE FROM KIRANDUL TO NAGARNAR.   (iv). State : Chhattisgarh   (v). Category of the Proposal : Others   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 400000   (viii). Area of forest land proposed for diversion(in ha.): 83.831   (ix). Non-forest land required for this project(in ha.): 296.735   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : NMDC LIMITED   (ii). Address1 : REGD OFFICE 10 3 311A KHANIJ BHAVAN CASTLE HILLS MASAB TANK HYDERABAD 500028   (iii). Address2 : REGD OFFICE 10 3 311A KHANIJ BHAVAN CASTLE HILLS MASAB TANK HYDERABAD 500028   (iv). State : Telangana   (v). District : Hyderabad   (vi). Pin : 500028   (vii). Landmark : 10 3 311A   (viii). Email address : jayapalreddy@nmdc.co.in   (ix). Landline Telephone No. : 40-23538773   (x). Fax No. : 40-23536760   (xi). Mobile No. : 9490491714   (xii). Website (if any) : www.nmdc.co.in   (xiii). Legal status of User Agency : Central PSU
A-3. Details of Person Making Application
  (i). First Name: M JAYAPAL REDDY   (ii). Middle Name: NIL   (iii). Last Name: REDDY   (iv). Gender: Male   (v). Designation: CHIEF GENERAL MANAGER (RESOURCE PLANNING)   (vi). Address 1: REGD OFFICE 10 3 311A KHANIJ BHAVAN CASTLE HILLS MASAB TANK HYDERABAD 500028   (vii). Address 2: REGD OFFICE 10 3 311A KHANIJ BHAVAN CASTLE HILLS MASAB TANK HYDERABAD 500028   (viii). State: Telangana   (ix). District: Hyderabad   (x). Tehsil: NIL   (xi). Pin: 500028   (xii). Landmark: 10 3 311A   (xiii). Email Address: jayapalreddy@nmdc.co.in   (xiv). Landline Telephone No.: 40-23538773   (xv). Fax No.: 23536760   (xvi). Mobile No.: 9490491714   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1InprincipleFP/JH/MIN/1068/20118-101/2011-FC402.91402.9111 Apr 2013
2InprincipleFP/JH/MIN/912/20108-36/2010-FC778.23778.2307 Nov 2013
Total 1181.14 1181.14
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Dantewada42.788115.661
2.Bastar41.043181.074
Total83.831296.735
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Dantewada42.788115.661
1.Bastar41.043181.074
Total83.831296.735
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Padapur9.3412.453
2Bade Bacheli015.321
3Bade Kameli05.462
4Porokameli0.9794.237
5Bhansi2.343.046
6Dhurli3.40111.269
7Gamawada0.30914.489
8Kumharras1.7389.796
9Karenjnar02.23
10Patarras0.153.72
11Dantewada6.0137.534
12Teknar5.8597.412
13Gumda4.5164.495
14Hournar0.5353.641
15Geedam0.5451.471
16Jawanga0.368.733
17Bagmundi0.1050
18Bade Paneda1.9815.846
19Bagmundii2.23613.03
20Bahanpur00.18
21Bastanar12.72519.32
22Irpa0.4532.33
23Jamgaon0.090
24Killepal2.98127.19
25Kodenar0.4335.12
26Tirthum0.9116.9
27Gurram3.8361.68
28Katakanda03.8
29Dilmilli0.7247.28
30Mavlibhatta2.35313.48
31Patharli udwa01.21
32Mandwa0.1910.03
33Raikot5.1079.47
34Duganpal01.48
35Erendwal0.5781.1
36Bade Arapur0.5077.42
37Parpa0.2583.21
38Tokapal04.54
39Bade Parakot03.01
40Keslur05.29
41Telimarenga0.2725.66
42Dongari Guda0.8380
43Burungpal0.4870
44Pandripani0.4710
45Niyanar0.560
46Nerli4.6174.506
Total 78.8 258.391
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Dantewada42.788115.659
2Bastar41.043181.074
Total 83.831 296.733
C. Maps of forest land proposed to be diverted
Division 1. : Bastar
  (i). Area of forest land proposed to be diverted(in ha.) : 41.043   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.41.043    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Dantewada
  (i). Area of forest land proposed to be diverted(in ha.) : 42.788   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.42.788    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 125   (iii). Temporary Employment(Number of person-days): 500
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : Yes   (a). Status of the Environmental Clearance to the Project: EC under process   (ii). Environmental Clearance File No.: NIL
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : Yes
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
Additional information Details
Documents
S.No Documents
Remarks
1
2reply for the quries raised on 3 9 2015
3safety zone letter from Director
4re validated DD
5EDS reply dated 29 9 2015
6DGPS REPORT DANTEWADA FOREST DIVISION
7DGPS REPORT BASTAR FOREST DIVISION