Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Sambalpur)
|
EDS
|
User Agency (mis.support@idco.in)
|
05/01/2019
|
1. Details of land schedule with map for the diversion of forest land already submitted and acquired previously for the project must be submitted.
2. Component wise break up for forest land and non-forest land must be submitted with proposal land use map.
3. Details of cost-benefit analysis for the project must be submitted as per now revised guidelines.
|
|
2
|
User Agency (mis.support@idco.in)
|
REPLY
|
DFO (Sambalpur)
|
18/04/2019
|
The correction have been made as per the instruction received
|
|