TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/IND/36821/2018              (ii). Name of Project for which Forest Land is required : IDCO has allotted 279 Acres of land to M/s Shyam Metalics & Energy Ltd. for establishment of Industry in the village-Pandloi and Nishanbhnaga of Rengali-Tahsil ,District-Sambalpur for establishment o              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : M/s Shyam Metalics & Energy Ltd. steel project is located at village- Pandoloi and nishanbhanga, in Sambalpur district of Odisha. The project site is at latitude 210 40’ 50.43’’ N and longitude 840 02’ 30.63’’ E, MSL 208m.              (iv). File no. : 5-ORC32/2019-BHU              (v). State : Orissa              (vi). Category of the Project : Industry              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 8.361
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/OR/IND/36821/201802/11/2018aa03/11/2018   06/11/2018 Sambalpur :06/11/2018Sambalpur:
  14/06/2019 (Sambalpur)

Orissa:
08/07/2019
Orissa:
20/08/2019
Bhubaneswar:
07/09/2019
23/12/2019
By :Regional Office
Orissa
16/01/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Sambalpur) on:05/01/2019  
Replied by UA on :18/04/2019  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Bhubaneswar) on:23/08/2024  
Replied by State Government(Orissa) on:21/09/2024  
Query raised by Regional Office (Bhubaneswar) on:29/10/2024  
Replied by State Government(Orissa) on:15/01/2025  
Query raised by Regional Office (Bhubaneswar) on:15/01/2025  
Query raised by State Government (Orissa) on:02/12/2024  
Replied by Nodal Officer (Orissa) on:24/12/2024  
Query raised by State Government (Orissa) on:30/01/2025  
Query raised by Nodal Officer on:01/02/2025  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .