Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Rajasthan FP/RJ/Others/31027/2017 8B/Raj/09/35/2019/FC Conctruction of Passanger Ropeway at Jodhpur Siddhnath Shiv temple is located between Takhat Sagar hills Applied Area 0.8958 ha. Others ROK INNOVATON PVT LTD 0.8962 APPROVED
Proposal received(at Nodal Officer)electronically on : 03 Jan 2018
Stage-I Approval on : 21 Jan 2020
Compliance Report Submitted by User Agency on : 13 Mar 2020
13 May 2020
2 Rajasthan FP/RJ/SubStation/42955/2019 8B/Raj/04/4/2020/FC Construction of 765 /400 kV Sub Station at Village- Jasrapur, Tehsil- Khetri, District–Jhunjhunu under Transmission System Associated with LTA Applications for Rajasthan Solar Energy Zone, Part -C which inter-alia includes 765 kV D/C Khetri-Jhatikra (Delhi) Hexa Zebra Transmission Line, 400 kv D/C K Sub Station POWERGRID KHETRI TRANSMISSION SYSTEM LIMITED 35.1938 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Nov 2019
Stage-I Approval on : 20 Feb 2020
Compliance Report Submitted by User Agency on : 17 Mar 2020
12 May 2020
3 Rajasthan FP/RJ/ROAD/22585/2016 8B/RAJ/06/25/2017/FC Diversion of 12.75 Ha Forest land for up gradation & Strengthening work of existing road of NH 89 section Ajmer to Nagaur. Ch. 0/00 to 161/00. The forest area falls in ajmer district, In nagaur district only repair and maintenance work is to be done. The work is on DFBOT Basis. Road PWD JAIPUR 12.75 APPROVED
Proposal received(at Nodal Officer)electronically on : 07 Dec 2016
Stage-I Approval on : 15 Feb 2018
Compliance Report Submitted by User Agency on : 20 May 2019
06 May 2020
4 Rajasthan FP/RJ/ROAD/36624/2018 8B/RAJ/06/28/2019/FC Construction of Approach Road for Proposed Nayara Energy Limited (Formerly Essar Oil Ltd.) Retail Outlet on Ajmer - Nagaur Road NH-89 (New NH-58) Chainage: 79.792 to 79.827, RHS in Khasra No. 959/639, At Village-Lanchha ki Dhani, Tehsil-Merta, Dist.-Nagaur, Rajasthan Road NAYARA ENERGY LIMITED FORMERLY ESSAR OIL LIMITED 0.175 APPROVED
Proposal received(at Nodal Officer)electronically on : 14 Nov 2018
Stage-I Approval on : 11 Nov 2019
Compliance Report Submitted by User Agency on : 14 Feb 2020
11 Mar 2020
5 Rajasthan FP/RJ/WATER/23333/2016 1(31)Forest/2019 Construction of Over Head Reservoir in Khonagoriyan Village Jaipur Drinking Water PHED 0.172 APPROVED
Proposal received(at Nodal Officer)electronically on : 01 Feb 2017
Stage-I Approval on : 14 Aug 2019
Compliance Report Submitted by User Agency on : 30 Jan 2020
27 Feb 2020
6 Rajasthan FP/RJ/ROAD/35699/2018 8B/Raj/06/34/2019/FC Diversion of 0.1022 ha forest land for construction of approach road for a new R/O of Nayara Energy Ltd. along the SH-19 (Didwana –Nagaur ROAD), Part of khasra no. 459(673/459 & 781/459), at village Fagali, Tehsil & District. Nagaur, (Rajasthan). Between k.m. stone 4-5 (4.637-4.672)RHS Road NAYARA ENERGY LIMITED 0.1022 APPROVED
Proposal received(at Nodal Officer)electronically on : 08 Apr 2019
Stage-I Approval on : 21 Nov 2019
Compliance Report Submitted by User Agency on : 03 Feb 2020
25 Feb 2020
7 Rajasthan FP/RJ/ROAD/40450/2019 1(76)forest/2019 PROPOSED FOREST LAND FOR DIVERSION ON FOR CONSTRUCTION OF CC ROAD NEAR VILLAGE- HASAMPUR TO RELA IN VILLAGE HASAMPUR ,RANGE - PATAN,TASHIL- NEEM KA THANA , DISTT.- SIKAR (RAJ.) Road MISSING LINK ROAD ,PWD NEEM KA THANA ,SIKAR 0.44 APPROVED
Proposal received(at Nodal Officer)electronically on : 03 Jun 2019
Stage-I Approval on : 31 Dec 2019
Compliance Report Submitted by User Agency on : 05 Feb 2020
19 Feb 2020
8 Rajasthan FP/RJ/TRANS/28926/2017 8B/RJ/04/10/2018/FC 400 KV D/C Barmer – Bhinmal Transmission Line is required for Evacuation of Renewable Power from Solar PP & Wind Farms located in Western Part of Rajasthan Transmission Line RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD BARMER 3.2236 APPROVED
Proposal received(at Nodal Officer)electronically on : 01 Sep 2017
Stage-I Approval on : 09 May 2018
Compliance Report Submitted by User Agency on : 10 Jan 2020
17 Feb 2020
9 Rajasthan FP/RJ/ROAD/35385/2018 8B/RAJ/06/11/2019/FC Construction of Approach Road for Proposed Nayara Energy Limited (Formerly Essar Oil Ltd.) Retail Outlet on Suratgarh - Ganganagar Road (NH-62) Between km Stone 187 - 188 (Chainage: 187.931 - 187.966) LHS in Stone No. : 41/333, Kila No. 3, 4 & 5 At Village-17 STB, Tehsil-Suratgarh, Dist.-Sri Gangan Road NAYARA ENERGY LIMITED MS ESSAR OIL LTD 0.351 APPROVED
Proposal received(at Nodal Officer)electronically on : 04 Sep 2018
Stage-I Approval on : 21 Jun 2019
Compliance Report Submitted by User Agency on : 10 Jan 2020
07 Feb 2020
10 Rajasthan FP/RJ/TRANS/34645/2018 8B/Raj/04/17/2019/FC Construction of 765 KV D/C Bikaner - Moga Transmission line (Part - I) Village Jamsar AP-01 to Village- Suin AP-30 Disticti Boundary Bikaner , District - Bikaner (Rajasthan) Transmission Line POWER GRID CORPORATION OF INDIA LIMITED 2.0146 APPROVED
Proposal received(at Nodal Officer)electronically on : 11 Jul 2018
Stage-I Approval on : 05 Nov 2019
Compliance Report Submitted by User Agency on : 24 Dec 2019
21 Jan 2020
11 Rajasthan FP/RJ/RAIL/34272/2018 8B/RAJ/07/02/2019/FC DFCCIL already have received the forest land diversion of 5.9882 hectare from MoEF but due to change in alignment in Sirohi and Ajmer division additional forest land is required, hence the fresh proposal is being submitted for diversion of additional Forest land. Railway DFCCIL JAIPUR 1.2061 APPROVED
Proposal received(at Nodal Officer)electronically on : 21 Jun 2018
Stage-I Approval on : 22 Aug 2019
Compliance Report Submitted by User Agency on : 13 Dec 2019
16 Jan 2020
12 Rajasthan FP/RJ/ROAD/19132/2016 8B/RAJ/06/05/2019/FC The proposed project road is essentially a highway up-gradation project and involved of conversion of existing single lane to 2-lane with paved shoulder as per NH standard. Road PUBLIC WORKS DEPARTMENT NH DIVISION 79.471 APPROVED
Proposal received(at Nodal Officer)electronically on : 28 Apr 2016
Stage-I Approval on : 08 Jul 2019
Compliance Report Submitted by User Agency on : 24 Oct 2019
24 Dec 2019
13 Rajasthan FP/RJ/ROAD/37041/2018 8B/RAJ/06/25/2019/FC Diversion of 0.1276 hectare Forest Land for Construction of Approach Road for Proposed Nayara Energy Limited (Formerly Essar Oil Ltd.) Retail Outlet on Nindar - Phalodi Road (SH-19) Between KM Stone No. 132-133 (Chainage: 132.125 - 132.160) RHS in Khasra No. 1692/1676 & 1693/1677, At Village-Singad Road NAYARA ENERGY LIMITED 0.1276 APPROVED
Proposal received(at Nodal Officer)electronically on : 24 Nov 2018
Stage-I Approval on : 24 Sep 2019
Compliance Report Submitted by User Agency on : 27 Nov 2019
18 Dec 2019
14 Rajasthan FP/RJ/Others/33509/2018 8B/RAJ/09/13/2019/FC Construction of passenger ropeway from Annapurna Temple to Mata Vaishnav Devi Temple Khole ke Hanumanji 0.8735 ha.The proposed alignment is the shortest in terms of land diversion as it has been taken from the place which is closest to the temple, road, nearest LT power line, minimum disturbance Others ROK INNOVATON PVT LTD 0.8735 APPROVED
Proposal received(at Nodal Officer)electronically on : 07 May 2018
Stage-I Approval on : 17 Jun 2019
Compliance Report Submitted by User Agency on : 11 Nov 2019
29 Nov 2019
15 Rajasthan FP/RJ/ROAD/21142/2016 8B/RAJ/06/29/2017/FC The project Road is Start near Salasar Bus Stand Total(Sikar) at design chainage km 0.000 and ends at design chainage km 75.460 on RIDCOR Mega highway junction in Jaswangarh. Total Length of Road is 75.460 km. SH-20 AND 20A Road PWD JAIPUR 4.1524 APPROVED
Proposal received(at Nodal Officer)electronically on : 29 Aug 2016
Stage-I Approval on : 20 Feb 2018
Compliance Report Submitted by User Agency on : 16 Apr 2019
21 Nov 2019
16 Rajasthan FP/RJ/ROAD/37883/2018 8B/RAJ/06/22/2019/FC Construction of Approach Road for Proposed Nayara Energy Limited (Formerly Essar Oil Ltd.) Retail Outlet on Parbatsar - Kuchaman Road (SH-7) Between KM Stone No. 49-50 (Chainage: 49.740 - 49.780) LHS in Khasra No. 996/995, At Village-Gangwa, Tehsil-Parbatsar, District-Nagaur, Rajasthan Road NAYARA ENERGY LIMITED 0.136 APPROVED
Proposal received(at Nodal Officer)electronically on : 05 Jan 2019
Stage-I Approval on : 27 Aug 2019
Compliance Report Submitted by User Agency on : 24 Oct 2019
21 Nov 2019
17 Rajasthan FP/RJ/ROAD/33529/2018 8B/RAJ/06/23/2019/FC Construction of Approach Road for Proposed Nayara Energy Limited (Formerly Essar Oil Ltd.) Retail Outlet on Nagaur - Jodhpur Road NH-65 (New NH-62) Between km Stone No. 185-186 (Chainage No.-185.645 - 185.680) RHS in the part of Khasra No. 372 At Village-Kharnal, Tehsil-Mundwa, District.-Nagaur (Ra Road Essar Oil Limited 0.168 APPROVED
Proposal received(at Nodal Officer)electronically on : 09 May 2018
Stage-I Approval on : 04 Sep 2019
Compliance Report Submitted by User Agency on : 24 Oct 2019
13 Nov 2019
18 Rajasthan FP/RJ/ROAD/29748/2017 8B/RAJ/06/1/2019/FC "ESSAR OIL LIMITED, Jodhpur" for “Construction of Approach Road for Proposed ESSAR Retail Outlet on Barmer - Dhanera Road (NH-15) Between km Stone No. 285 - 286 (Chainage No.-285.013 - 285.058) RHS in Khasra No. 854 At Village-B Dhanisanchore, Tehsil-Sanchore, Dist.-Jalore, Rajasthan" Road ESSAR OIL LTD 0.1513 APPROVED
Proposal received(at Nodal Officer)electronically on : 16 Oct 2017
Stage-I Approval on : 06 Aug 2019
Compliance Report Submitted by User Agency on : 04 Oct 2019
11 Nov 2019
19 Rajasthan FP/RJ/WATER/21709/2016 8B/RAJ/08/21/2017/FC Forest clearance for laying of 700 mm M.S. pipe line in road boundary along the NH-15 Barmer-Sanchore from Km. 194.600(Bachharu Fanta) to Km. 232.050 (Arniyali Fanta) Drinking Water PUBLIC HEALTH ENGINEERING DEPARTMENT 9.29 APPROVED
Proposal received(at Nodal Officer)electronically on : 07 Jan 2017
Stage-I Approval on : 09 Mar 2018
Compliance Report Submitted by User Agency on : 05 Jun 2018
07 Nov 2019
20 Rajasthan FP/RJ/TRANS/38501/2019 8B/RAJ/04/15/2019/FC Diversion of Forest Land for Construction of 765 KV D/C Bhadla to Bikaner Transmission Line Part-II, Village- Beetnokh AP-26 TO Village- Jamsar AP -66 . Associated With Green Energy Corridors Interstate Transmission Scheme (ISTS). Transmission Line POWER GRID CORPORATION OF INDIA LIMITED 1.0617 APPROVED
Proposal received(at Nodal Officer)electronically on : 28 Jan 2019
Stage-I Approval on : 19 Jun 2019
Compliance Report Submitted by User Agency on : 22 Aug 2019
05 Nov 2019
21 Rajasthan FP/RJ/ROAD/34460/2018 1(15)forest/2019 Construction of Approach Road for Proposed IOCL Retail Outlet on Suratgarh - Anupgarh Road (MDR-103) New (SH-94) Between Chainage No. 109-110 (Ch. 109+438 - 109+473) LHS in Murbba No.: 8, 57GB Plot No.: 230/447 Kila No.: 13, 14, 17, 18 At Village- Ramsinghpur Mandi (57GB) Tehsil - Anupgarh, Distric Road Indian Oil Corporation Limited 0.165 APPROVED
Proposal received(at Nodal Officer)electronically on : 19 Jul 2018
Stage-I Approval on : 27 May 2019
Compliance Report Submitted by User Agency on : 19 Sep 2019
04 Nov 2019
22 Rajasthan FP/RJ/ROAD/26711/2017 8B/Raj/06/16/2018/FC Construction of Approach Road for Proposed Essar Oil Ltd. Retail outlet on Suratgarh - Sri Ganganagar (NH-62) Road at Part of Murba No. 48, Kila No. 9&10, Stone No. 40/300 at village-23 LGW "B", Tehsil- Suratgarh, District-Sri Ganganagar (Rajasthan). Road ESSAR OIL LTD 0.1379 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Jun 2017
Stage-I Approval on : 16 Apr 2019
Compliance Report Submitted by User Agency on : 13 Aug 2019
31 Oct 2019
23 Rajasthan FP/RJ/TRANS/32877/2018 8B/RAJ/04/23/2018 765 KV D/C BANASKANTHA – CHITTORGARH TRANSMISSION LINE PART-III ASSOCIATED WITH GREEN ENERGY CORRIDORS INTER STATE TRANSMISSION SCHEME (ISTS PART – B ) Transmission Line POWERGRID CORPORATION OF INDIA LIMITED 10.5324 APPROVED
Proposal received(at Nodal Officer)electronically on : 01 Apr 2018
Stage-I Approval on : 16 Aug 2018
Compliance Report Submitted by User Agency on : 05 Oct 2018
17 Oct 2019
24 Rajasthan FP/RJ/ROAD/13599/2015 F.1(16)Forest/2018 Construction of road mohanpura road to ganeshpura lodhan under RRSMP IN RAJASTHAN Road EXECUTIVE ENGINEER 0.984 APPROVED
Proposal received(at Nodal Officer)electronically on : 30 Jun 2015
Stage-I Approval on : 22 Feb 2018
Compliance Report Submitted by User Agency on : 06 Sep 2019
15 Oct 2019
25 Rajasthan FP/RJ/WATER/29336/2017 8B/Raj/08/1/2018/FC LIFT WATER SUPPLY PROJECT POKARAN FALSOOND BALOTRA SIWANA CLUSTER PACKAGE SPR - IV B REQUIRED FOREST LAND FOR THE WORK TO SUPPLY OF WATER FROM GRAVITY MAIN OFF-TAKE AT BOARWAS-KHER, JASOL, JASOL FANTA, KUSEEP FANTA, SIWANA, VARIYA VARECH, SINLI, KITPALA, KALOORI, OAKHAN, MITHORA, BHOOKHA BAGAT SINGH Drinking Water PHED 1.517 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Sep 2017
Stage-I Approval on : 31 May 2018
Compliance Report Submitted by User Agency on : 13 Sep 2019
11 Oct 2019
26 Rajasthan FP/RJ/TRANS/35279/2018 8B/Raj/04/14/2019/FC Proposed Transmission line will start from Proposed 765/400/220 KV Sub Station Noore Ki Bhurj, Tehsil – Bap ( Northing – 3036080, Easting – 210750) and will End Tower Location No. 26 A/0 ( Northing – 3080618, Easting – 274833), Village – Bithnok, Tehsil – Kolayat, District – Bikaner (Raj.) Transmission Line POWER GRID CORPORATION OF INDIA LIMITED 10.299 APPROVED
Proposal received(at Nodal Officer)electronically on : 28 Aug 2018
Stage-I Approval on : 04 Jul 2019
Compliance Report Submitted by User Agency on : 08 Aug 2019
11 Sep 2019
27 Rajasthan FP/RJ/TRANS/32743/2018 8B/RAJ/04/10/2019/FC Power Grid, a central Transmission Utility is engaged in establishment and Operation of regional and National Power Grids of Facilitated the transfer of power within and across the region's to cater the load requirement of Fast developing Rajasthan area creation of Facilities for reliable Power Supp Transmission Line POWER GRID CORPORATION OF INDIA LIMITED 1.5766 APPROVED
Proposal received(at Nodal Officer)electronically on : 27 Mar 2018
Stage-I Approval on : 05 Apr 2019
Compliance Report Submitted by User Agency on : 10 May 2019
05 Sep 2019
28 Rajasthan FP/RJ/Others/27597/2017 8B/RAJ/09/22/2018 TO ESTABLISH ROPEWAY AT NEEMACH MATA TEMPLE,BY UIT UDAIPUR (RAJASTHAN) FOR ECO-TOURISM Others URBAN IMPROVEMENT TRUST UDAIPUR RAJASTHAN 0.4 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Aug 2017
Stage-I Approval on : 09 Aug 2018
Compliance Report Submitted by User Agency on : 09 Aug 2019
04 Sep 2019
29 Rajasthan FP/RJ/IRRIG/15138/2015 8B/RAJ/02/26/2018 BHIKA BHAI CANAL,MIS-VII,RD 79.60 TO 81.09 KM & MIS-VIII,RD 93.93 TO 94.076 KM Irrigation WATER RESOURCES DEPARTMENT 3.87 APPROVED
Proposal received(at Nodal Officer)electronically on : 03 Sep 2015
Stage-I Approval on : 07 Sep 2018
Compliance Report Submitted by User Agency on : 19 Feb 2019
03 Sep 2019
30 Rajasthan FP/RJ/ROAD/31252/2018 1(11)Forest/2019 Construction of Approach Road for Proposed Indian Oil Corporation Ltd. Retail Outlet (LHS) on Sanchore - Gujarat Road (NH-15) between Km. Stone No. 291-295(Chainage-292/85 - 292/130),Khasra No.2797/3508 & 2797 At Village- Mokhupura, Tehsil - Sanchore, District-Jalore,Rajasthan. Road Indian Oil Corporation Limited 0.231 APPROVED
Proposal received(at Nodal Officer)electronically on : 28 Jan 2018
Stage-I Approval on : 27 May 2019
Compliance Report Submitted by User Agency on : 16 Aug 2019
30 Aug 2019
31 Rajasthan FP/RJ/TRANS/32123/2018 8B/RAJ/04/27/2018 The line is proposed to feed the load of Kuakhera and nearby area in Rawatbhata tehsil of Chittorgarh District, Rajasthan Transmission Line RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD CHITTORGARH 24.3853 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Feb 2018
Stage-I Approval on : 14 Feb 2019
Compliance Report Submitted by User Agency on : 17 Jul 2019
27 Aug 2019
32 Rajasthan FP/RJ/ROAD/7441/2014 F.1(51)Forest/2016 The village Badbela is proposed for Connectivity by all weather road by Bituminous, under RRSMP (WB)Scheme Road PMGSY 0.9934 APPROVED
Proposal received(at Nodal Officer)electronically on : 02 Oct 2014
Stage-I Approval on : 29 Dec 2016
Compliance Report Submitted by User Agency on : 24 Jun 2019
20 Aug 2019
33 Rajasthan FP/RJ/TRANS/40050/2019 1(18)Forest/2019 Power Diversion from Tower no. 445 of existing 400 KV D/C (QUAD) Bhadla - Bikaner Transmission lineof RVPNL to newely constructing 400/765 KV Sub-Station of POWERGRID at Jamsar Sub - Stationm Bikaner (Raj.) Transmission Line POWER GRID CORPORATION OF INDIA LIMITED 0.9079 APPROVED
Proposal received(at Nodal Officer)electronically on : 01 May 2019
Stage-I Approval on : 12 Jun 2019
Compliance Report Submitted by User Agency on : 09 Jul 2019
31 Jul 2019
34 Rajasthan FP/RJ/Others/21735/2016 8-55/2017-FC Proposel for Extention of Existing run way 1700 mtr. to 3000 mtr. for using 120.4062 hact.forest land at kolana , jhalawar (raj) Others PUBLIC WORKS DEPARTMENT JHALAWAR 120.4062 APPROVED
Proposal received(at Nodal Officer)electronically on : 07 Oct 2016
Stage-I Approval on : 13 Apr 2018
Compliance Report Submitted by User Agency on : 15 Nov 2018
18 Jul 2019
35 Rajasthan FP/RJ/TRANS/29318/2017 8B/RAJ/04/25/2018 400 KV D/C LINE RAMGARH BHADLA TRANSMISSION line is required for Evacuation of Renewable Power from Solar & Wind generator connected at 400 kv Ramgarh GSS to 400 kv GSS Bhadla. Transmission Line RVPNL RAMGARH JAISALMER RAJASTHAN 19.711 APPROVED
Proposal received(at Nodal Officer)electronically on : 16 Oct 2017
Stage-I Approval on : 14 Sep 2018
Compliance Report Submitted by User Agency on : 21 Dec 2018
16 Jul 2019
36 Rajasthan FP/RJ/ROAD/32288/2018 8B/RAJ/06/29/2018/FC Diversion of 0.1310 ha forest land for Essar oil ltd new retail outlet along Maulasar-Daulatpura road (SH-7)Between KM stone 98-99(CH.98.912-98.947)LHS in the khasra no 394/138, at village chhapari kalan, tehsil didwana district Nagaur Rajasthan Road Essar Oil Limited 0.131 APPROVED
Proposal received(at Nodal Officer)electronically on : 25 Mar 2018
Stage-I Approval on : 30 Apr 2019
Compliance Report Submitted by User Agency on : 19 Jun 2019
09 Jul 2019
37 Rajasthan FP/RJ/TRANS/19223/2016 8B/RAJ/04/11/2017/FC To meet out the load growth and improve to existing system parameter in the tehsil Mandrayal and karauli, it is proposed to creat a 132 KV GSS Mandrayal capicity 25 MVA by laying of 132 KV S/C Karauli mandrayal Transmission line. Transmission Line RRVPNL 37.665 APPROVED
Proposal received(at Nodal Officer)electronically on : 06 May 2016
Stage-I Approval on : 23 Aug 2017
Compliance Report Submitted by User Agency on : 28 Jun 2018
12 Jun 2019
38 Rajasthan FP/RJ/ROAD/17799/2016 F.1(16)Forest/2017 Upgradation fo Road from Bishangarh to Govindpurabaseri Via Radawas,Dhanota,Murlipura km 0/0 to 18/175 under PMGSY Package No. RJ-16BN-UG-11. Road PUBLIC WORK DEPARTMENT 0.98 APPROVED
Proposal received(at Nodal Officer)electronically on : 01 Feb 2016
Stage-I Approval on : 14 Mar 2017
Compliance Report Submitted by User Agency on : 10 May 2019
30 May 2019
39 Rajasthan FP/RJ/ROAD/31880/2018 8B/RAJ/06/4/2019/FC Construction of Approach Road for Proposed ESSAR Oil Retail Outlet on Bikaner - Ganganagar Road (NH-15) Between km Stone No. 023- 024 (Chainage No.-023.404 - 023.439) LHS in Murbba No. 148/31, Kila No. 17/2 & 18 At Village-2 J.M.D. , Tehsil & District - Bikaner, Rajasthan. Road ESSAR OIL LTD 0.1283 APPROVED
Proposal received(at Nodal Officer)electronically on : 10 Feb 2018
Stage-I Approval on : 20 Feb 2019
Compliance Report Submitted by User Agency on : 14 May 2019
30 May 2019
40 Rajasthan FP/RJ/ROAD/22166/2016 F.1(36)Forest/2018 Construction of Missing Link Road Bandikui to Bhandera Chainage 00/00 to 1/500 km 0.70875 Ha.This road is Connected to Bandikui pwd block , Sikrai Block and NH-11 Manpur bus Stand. Road PUBLIC WORK DEPARTMENT 0.70875 APPROVED
Proposal received(at Nodal Officer)electronically on : 08 Nov 2016
Stage-I Approval on : 28 May 2018
Compliance Report Submitted by User Agency on : 23 Apr 2019
23 May 2019
41 Rajasthan FP/RJ/TRANS/15911/2015 8B/Raj/04/8/2016/FC Construction of 220 KV D/C Transmission line from 220 KV GSS Kishangarh to 220 KV TSS for DFCC at Kishangarh Transmission Line RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LIMITED 9.002 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Oct 2015
Stage-I Approval on : 06 Jan 2017
Compliance Report Submitted by User Agency on : 02 May 2018
01 May 2019
42 Rajasthan FP/RJ/TRANS/19845/2016 8B/RJ/04/03/2017/FC For Construction of New Proposed 132KV GSS Mamoni power supply Transmission Line RAJASTHAN RAJYA VIDHYUT PRASARAN NIGAM 3.942 APPROVED
Proposal received(at Nodal Officer)electronically on : 03 Jun 2016
Stage-I Approval on : 30 Mar 2017
Compliance Report Submitted by User Agency on : 23 Nov 2017
02 Apr 2019
43 Rajasthan FP/RJ/RAIL/6845/2014 8B/RAJ/07/34/2015 Phase -IV - ( Forest land from Gindore village ) - Ramganjmandi- Bhopal new BG line project- To Construct New Broad Gauge Railway line form Ramganjmandi up to Bhopal a distance of about 276 Km via District Kota,Jhalawar in Rajasthan state also connecting District Rajgarh, Sihor and Bhopal of Madhya Railway WEST CENTRAL RAILWAY 2.718 APPROVED
Proposal received(at Nodal Officer)electronically on : 05 Sep 2014
Stage-I Approval on : 06 Jan 2017
Compliance Report Submitted by User Agency on : 07 Feb 2019
07 Mar 2019
44 Rajasthan FP/RJ/ROAD/26414/2017 8B/UP/06/21/2018 Diversion of 0.1276 Ha forest land to construct the approach road for New Essar Retail outlet on Badi Khatu-Tarnau road SH-90, Bwtween KM Stone 173-174(Ch. 173.516-173.551) in The part of khasra no 2509/2253 at village Khatu Kalan Tehsil Jayal District Nagaur Rajasthan Road Essar Oil Limited 0.1276 APPROVED
Proposal received(at Nodal Officer)electronically on : 28 May 2017
Stage-I Approval on : 20 Sep 2018
Compliance Report Submitted by User Agency on : 04 Feb 2019
07 Mar 2019
45 Rajasthan FP/RJ/ROAD/25888/2017 F.1(46)Forest/2018 “Construction of Approach Road for Proposed Hindustan Petroleum Corporation Ltd. Retail Outlet(LHS) along the Bikaner-Jaipur Road (NH-11) At Khasara No. 1889/1438, NH-11, Village – Sheruna, Tehsil – Shri Dungargarh, District – Bikaner, State – Rajasthan. At Chainage No. 525.581 to 525.613”. Road HINDUSTAN PETROLEUM COORPERATION LIMITED 0.1421 APPROVED
Proposal received(at Nodal Officer)electronically on : 27 Apr 2017
Stage-I Approval on : 09 Aug 2018
Compliance Report Submitted by User Agency on : 05 Mar 2019
05 Mar 2019
46 Rajasthan FP/RJ/Others/31178/2018 8B/RAJ/09/20/2018 Construction fo Sewerage Treatment Plant (STP) at Churu 0.90 Ha.under AMRUT Gol scheme of Churu Town. Others NAGAR PRISHAD CHURU,RAJASTHAN 0.9 APPROVED
Proposal received(at Nodal Officer)electronically on : 04 Jan 2018
Stage-I Approval on : 18 Sep 2018
Compliance Report Submitted by User Agency on : 21 Dec 2018
24 Jan 2019
47 Rajasthan FP/RJ/ROAD/11471/2015 F.1(53)Forest/2017 The land is required for the access (BT Road) Darunda to Baswa Ki Dhani. Administrative & Financial sanction for PMGSY works under World Bank Assisted Project - RRP-III (Transche-IV)in 18 districts of Rajasthan for the year 2013-14, Phase-XII, Pop. 350-399 (T&D) Area - New Connectivity of Rural Road Road PWD 0.266 APPROVED
Proposal received(at Nodal Officer)electronically on : 21 May 2015
Stage-I Approval on : 26 Oct 2017
Compliance Report Submitted by User Agency on : 03 Jan 2019
23 Jan 2019
48 Rajasthan FP/RJ/ROAD/25937/2017 F.1(41)Forest/2018 Construction of road marukheri to bardiya UNDER (MISSING LINK Scheme in rajasthan Road PUBLIC WORK DEPARTMENT BHAWANI MANDI 0.9648 APPROVED
Proposal received(at Nodal Officer)electronically on : 02 May 2017
Stage-I Approval on : 11 Jun 2018
Compliance Report Submitted by User Agency on : 09 Oct 2018
04 Jan 2019
49 Rajasthan FP/RJ/ROAD/26978/2017 F.1(31)Forest/2018 Proposed Construction of Urban Gaurav Path Pushkar on Ajmer – Pushkar Road From Chainage 10/400 to 8/400, District-Ajmer (Rajasthan). Road PWD JAIPUR HEAD OFFICE 0.0817 APPROVED
Proposal received(at Nodal Officer)electronically on : 07 Jul 2017
Stage-I Approval on : 22 May 2018
Compliance Report Submitted by User Agency on : 07 Jan 2019
04 Jan 2019
50 Rajasthan FP/RJ/RAIL/9021/2014 8B/Raj/07/10/2016/FC Construction of New BG line 56 kms from Thaiyat Hamira to Sanu exclusively for lime stone loading at Sanu siding. Railway NORTH WESTERN RAILWAY 42.06 APPROVED
Proposal received(at Nodal Officer)electronically on : 17 Apr 2015
Stage-I Approval on : 29 May 2017
Compliance Report Submitted by User Agency on : 05 Mar 2018
27 Dec 2018