FORM - B
Form for seeking prior approval under Section-2 of the proposals by the State Governments and other authorities, in respect of renewal of leases,
which have been earlier granted clearance under Forest (Conservation) Act,1980
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/ROAD/40975/2019
(ii). Name of Project for which Forest Land is required :
Construction of Chinyalisaur-Jogath motor road to Pujargaon Bhadeshwar mandir motor road in Chinyalisaur Block under State Sector.
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The length of this motor road is 1.825 km, Whereby village Pungargaon will be connected directly to the block Chinyalisaur. the creation of this motor road, villagers will be able to carry their cash crops and carry the daily commodity's goods. The ancient Bhadeshwar temple situated in Pujaragaon, w
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
150
(viii). Area of forest land proposed for diversion(in ha.):
1.4385
(ix). Non-forest land required for this project(in ha.):
0.119
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
EXECUTIVE ENGINEER
(ii). Address1 :
Construction Division PWD, Chinyalisaur
(iii). Address2 :
Uttarkashi
(iv). State :
Uttarakhand
(v). District :
Uttarkashi
(vi). Pin :
249196
(vii). Landmarks :
NIL
(viii). Email address :
eecdpwd_uki@rediffmail.com
(ix). Landline Telephone No. :
237084
(x). Fax No. :
NIL
(xi). Mobile No. :
7579186700
(xii). Website (if any) :
NIL
(xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
(xiv). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
suresh
(ii). Middle Name:
Kumar
(iii). Last Name:
tomar
(iv). Gender:
Male
(v). Designation:
Executive Engineer
(vi). Address 1:
Construction Division, P.W.D., Chinyalisaur
(vii). Address 2:
Uttarkashi
(viii). State:
Uttarakhand
(ix). District:
Uttarkashi
(x). Tehsil:
NIL
(xi). Pin:
249196
(xii). Landmarks:
NIL
(xiii). Email Address:
eecdpwd_uki@rediffmail.com
(xiv). Landline Telephone No.:
237084
(xv). Fax No.:
01371237084
(xvi). Mobile No.:
7579186700
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-7.
Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
A-9.
Details of Transfer of Lease
Serial No
Name of person
Address of person
Date of transfer
MMDR File
Transfer Deed
Conservation
MoEF_file No
Date of approval
MoEF file
NIL
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
(i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. :
No
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Uttarkashi
1.4385
0.119
Total
1.4385
0.119
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Uttarkashi
1.4385
0.119
Total
1.4385
0.119
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Bagori
1.4385
0.119
1.4385
0.119
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Road
1.1585
0.119
2
Muck Disposal No. 1
0.16
0
3
Muck Disposal No.
0.12
0
Total
1.4385
0.119
C.
Maps of forest land proposed to be diverted
Division 1. : Uttarkashi
(i). Area of forest land proposed to be diverted(in ha.) :
1.4385
(ii).Shape of forest land proposed to be diverted :
Linear
(b). No. of Segments :
One
Segments wise details
Segmenst
Segment Area(in ha.)
Kml File of Segments
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
1.4385
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
2500
(iii). Temporary Employment(Number of person-days):
2000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
One
District 1. : Uttarkashi
(a). Village:
Bagori
(b). Area(in ha.):
2.877
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
3373
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using DGPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No
Documents
Remarks
1
EDS letter 03-11-2022
2
1 partiveden
3
3 auchiya purn aakhya
4
4 go
5
5 Fincial Sanction
6
abel defence certificate
7
Praroop 2
8
Part II
9
Part III
10
part iv
11
part v
12
Bhandeshwar motor road eds 4-01-2022
13
Pre inpection report
14
Land Shedule forest land
15
Land Shedule Non Forest Land
16
Land Shedule Summary
17
Effective Tree list
18
Effective Tree Estimate
19
Tree patan Certificate
20
Certificate of Distance from national park
21
appati letter
22
status of village to be benifit
23
Geological Report
24
EDS letter 31-07-2020
25
Banj Tree patan certificate
26
EDS letter 09-11-2020
27
eds letter 5-9-20
28
Digital map CA
29
letter eds 21-11-2019
30
CA Estimate
31
EDS letter 4-6-2022
32
Certificate of Double Amount of CA
33
Khatoni detail
34
Bar Chart
35
Certificate of CA in Blank Space
36
appati letter
37
Certificate of CA in x10
38
Certificate of length and width of yojana
39
Certificate of Cancelle Alternative Alignment
40
Alignment
41
Certificate of unstrated work
42
geojolist report
43
Task force Certificate
44
Certificate of No Loss of wild life
45
Certificate of non Religious place
46
Certificate of Benifits village families
47
Enviorment Sancation certificate
48
Forest Land Value Certificate
49
Certificate of Revised Rate of NPV
50
NPV Extra Amount
51
Mulya labh certificate
52
Isthal Vishist
53
Certificate of Supply of Carosion oil and Gas
54
Muck Disposal Plan
55
Manak Sharte
56
Pillar Nirman Estimate
57
Certificate of Land Ownership for CA
58
Certificate of Forest Act 1980
59
Certificate of Density of Vegetation
60
Site map
61
Check List
62
EDS letter Bhandeshwar 14-9-2021
63
eds 05-07-2021
64
Road map
65
Annexure 22 Banj Tree Paatan
66
eds letter 29-6-21
67
aapati 1 detail narrative
68
aapati 2 Part 2
69
aapati 3 Pre Joint Inpection Report
70
AApati 4 Van Adhiniyam 1980
71
Aapati 5 Van bhumi mulya laabh certificate
72
EDS letter
73
EDS online date 26-7-23
74
EDS_online_dt_22-08-2024
75
EDS 4-10-24
76
EDS 27-9-23
77
EDS 27-9-23
78
EDS 13-10-2025