  (i). Proposal No. : FP/UK/ROAD/157584/2022   (ii). Name of Project for which Forest Land is required : Construction of 4-laning of Kotdwar bypass of NH-119 connecting Najibabad-Kotdwar to Kotdwar-Pauri road in the state of Uttar Pradesh and Uttrakhand under Bharatmala Pariyojana Lot-4/Pakage-2   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 1.10 Ha reserved foreest land for Construction of 4-laning of Kotdwar bypass of NH-119 connecting Najibabad-Kotdwar to Kotdwar-Pauri road in the state of Uttar Pradesh and Uttrakhand under Bharatmala Pariyojana Lot-4/Pakage-2.   (iv). State : Uttarakhand   (v). Category of the Proposal : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 30057   (viii). Area of forest land proposed for diversion(in ha.): 1.1   (ix). Non-forest land required for this project(in ha.): 13.0323   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : NHAI PIU MEERUT   (ii). Address1 : A-1, Vaishno Dham, Near Gayatri Heights, Kankerkhera   (iii). Address2 : NH-58, Meerut, Uttar Pradesh   (iv). State : Uttar Pradesh   (v). District : Meerut   (vi). Pin : 250001   (vii). Landmarks : Near Gayatri Heights   (viii). Email address : piu_meerut@yahoo.co.in   (ix). Landline Telephone No. : 2631228   (x). Fax No. : 2631228   (xi). Mobile No. : 9868126926   (xii). Website (if any) : NIL   (xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past  
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1InprincipleFP/UP/ROAD/1189/20087-UPB073/2008-LUC4.1054.10506 Aug 2008
2InprincipleFP/UP/ROAD/1946/20067-UPA048/2006-LUC54.954.904 Jun 2006
3Under Processing at State GovernmentFP/UP/ROAD/39712/20191.89450
4InprincipleFP/UP/ROAD/34548/20188B/UP/06/78/2018/FC/5121.5721.57220 Nov 2018
5InprincipleFP/UP/ROAD/30178/2018B/UP/06/41/2018/FC/22949.2949.2927 Jun 2018
Total 111.7615 109.867
  (xiv). Legal status of User Agency : Central Government
A-3. Details of Person Making Application
  (i). First Name: Santosh   (ii). Middle Name: Kumar   (iii). Last Name: Bajpai   (iv). Gender: Male   (v). Designation: PD   (vi). Address 1: A-1, Vaishno Dham, Near Gayatri Heights   (vii). Address 2: Kankerkhera, NH-58, Meerut   (viii). State: Uttar Pradesh   (ix). District: Meerut   (x). Tehsil: NIL   (xi). Pin: 250001   (xii). Landmarks: Near Gayatri Heights   (xiii). Email Address: piu_meerut@yahoo.co.in   (xiv). Landline Telephone No.: 2631228   (xv). Fax No.: 01212631228   (xvi). Mobile No.: 9868126926   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-7. Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
A-9. Details of Transfer of Lease
Serial No Name of person Address of person Date of transfer MMDR File Transfer Deed Conservation MoEF_file No Date of approval MoEF file
NIL
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
  (i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. : No
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Lansdowne1.113.0323
Total1.113.0323
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Pauri Garhwal1.113.0323
Total1.113.0323
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Kashirampur00.5616
2Nathupur-Saneh00.3307
3Vishnupur-Saneh03.1331
4Jeetpur-Sahen00.4499
5Ratanpur-Saneh04.6587
6Garstinganj-Saneh02.5434
7Kotdwar Gaon Saneh1.11.3549
1.1 13.0323
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1construction of kotdwar by pass greenfield alignm1.113.0323
Total 1.1 13.0323
C. Maps of forest land proposed to be diverted
Division 1. : Lansdowne
  (i). Area of forest land proposed to be diverted(in ha.) : 1.1   (ii).Shape of forest land proposed to be diverted : Linear   (b). No. of Segments : One
Segments wise details
Segmenst Segment Area(in ha.) Kml File of SegmentsTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.1.1    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 50   (iii). Temporary Employment(Number of person-days): 10000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : Yes   (a). Whether Project or a part thereof is located within a Protected Area ? : Yes   (b). Status of approval of the Supreme Court : Application yet to b   (ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project : Application yet to be submitted
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: NIL   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: NIL   (iii) . Reason for not providing Non-Forest Land: NIL
Additional information Details
Documents
S.No Documents
Remarks
102 Detailed not on project uploaded
215 Certificate for non commencement of work uploaded
324 Aerial distance certificate uploaded
438 NPV Estimation
5Joint inspection report
6muck disposal plan
725th January 2023 Clarificaiton on processing the proposal of PARIVESH 1
8Justification
906 Topomap showing Project Location in Forest Land
10Geo-Refrenced Map
1101 Fact Sheet
1203 Form A, Part-1
1304 Project Sanction Letter
1408 Alignment Options Study
1510 Land Schedule
1612 Statement showing Details showing area of forest Land
1713 Statement showing details of Non Forest Land
1809 Non Availability of Alternative Land
1914 Bar Chart
2031 Certificate for the proposed project is not a part of Monument or religious place
2117 List of trees falls under Private land
2218 List of trees falls under Village Panchayat land
2319 List of trees falls under Government land
24EDS Compliances Letter
2520 Undertaking for Maximum 98 nos Felling of Trees
2621 Details of Total Valus of Tree
2722 Undertaking for not cutting of Banjh Tree
28DGPS MAP of NFL Proposed for CA
2923 Undaterking for minimum felling of Trees
30FRA Certificate issed by DM Pauri Garhwal
3124 Undertaking for the proposed project is not a part of Protected or National Park
32Land Suitability Certificate by DFO Lansdowne
3326 Undertaking for FRA Certificate
3427 Geo-Technical Report
3528 Undertaking for compliance of Geologist report
3629 Task Force Certificate
3730 Undertaking for compliace of general Conditions
3832 Undertaking for No Harm will be impacted on wildlife
3933 Undertaking for Provide Fuel to the Labours
40Letter from PD Regarding Compliences of EDS Raised by Nodal Officer on 22nd Feb, 2024
4134 Certificate of Project Benefits towards Villagers
4236 Undertaking for Payment of Compensatory Afforestation
43Letter of DM for Allocation of Forest Land Proposed for CA
4439 Undertaking for Payment of Cost of Additional NPV
45Location of NFL Marked on Toposheet
4640 Certificate for non violation of FCA 1980
47Wildlife Management and Soil Moisture Conservation Plan
4841 Authorization Letter
49Undertaking for no dumping of garbage in forest land