FORM - B
Form for seeking prior approval under Section-2 of the proposals by the State Governments and other authorities, in respect of renewal of leases,
which have been earlier granted clearance under Forest (Conservation) Act,1980
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/UP/Others/19811/2016   (ii). Name of Project for which Forest Land is required : Renewal of diversion of 3.79 he. of forest land in favor of Grasim industries limited Renukoot for pump house, pipe line over head transmission line.   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Renewal of diversion of 3.79 he. of forest land in favor of Grasim industries limited Renukoot for pump house, pipe line over head transmission line   (iv). State : Uttar Pradesh   (v). Category of the Proposal : Others   (vi). Shape of forest land proposed to be diverted : Non Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 500   (viii). Area of forest land proposed for diversion(in ha.): 3.79   (ix). Non-forest land required for this project(in ha.): 0   (x). Total period for which the forest land is proposed to be diverted(in years): 25
A-2. Details of User Agency
  (i). Name : GRASIM INDUSTRIES LIMITED CHEMICAL DIVISION   (ii). Address1 : Birlagram, Nagda-456331   (iii). Address2 : NIL   (iv). State : Madhya Pradesh   (v). District : Ujjain   (vi). Pin : 456331   (vii). Landmarks : Birlagram   (viii). Email address : gil-rnq.uhoffice@adityabirla.com   (ix). Landline Telephone No. : 252055   (x). Fax No. : 252088   (xi). Mobile No. : 9415004720   (xii). Website (if any) : www...   (xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past  
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
  (xiv). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: S   (ii). Middle Name: N   (iii). Last Name: Sastry   (iv). Gender: Male   (v). Designation: Unit Head   (vi). Address 1: Grasim Industries Limited Chemical Division Renukoot, Renukoot-231217   (vii). Address 2: NIL   (viii). State: Uttar Pradesh   (ix). District: Sonbhadra   (x). Tehsil: Robertsganj   (xi). Pin: 231217   (xii). Landmarks: Grasim Industries limited, Near Railway Station   (xiii). Email Address: gil-rnq.uhoffice@adityabirla.com   (xiv). Landline Telephone No.: 252055   (xv). Fax No.: 05446252088   (xvi). Mobile No.: 9415004720   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-4. Details of approvals under the Forest (Conservation) Act , 1980 accorded in the past
Serial No Proposal No MoEF File No Date of approval Area of forest land diverted Period of diversion
1FP/UP/OTHERS/411/19917-UPB001/1991-LUC23 May 19953.78825
A-5. Status of compliance to conditions stipulated in the previous approvals
Serial No Proposal No MoEF File No Conditions stipulated by the MoEF Details of the compliance
1FP/UP/OTHERS/411/19917-UPB001/1991-LUC1) There will be no change in legal situation of Forest land. 2) The lease period will be valid upto 31.3.13. 3) The use of Forest land will be only for the purpose given in the letter enclosed.If it is found that forest land is being used for other purpose then approval will be rejected and forest land will be returned to Deptt. 4) Forest Deptt. will do compensatory afforestation on non forest land equal to the approved land on the exp. of user agency. 5) The non forest land will be declared reserve forest.1) No change was made in the legal status of the forest land. 2) Accepted. 3) The forest land is only be used for the purpose approval was received. 4) Completed. 5) Complied.
A-6. Details of payments made in respect of the approval under the Forest (Conservation) Act , 1980 accorded in the past
Serial No Proposal No MoEF File No Item/Nature Amount paid (in Rupees) Date of Payment
1FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1626751208 Jun 2016
2FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684712 Apr 1996
3FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684728 Apr 1997
4FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684709 Jul 1997
5FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684723 Apr 1998
6FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684702 Aug 1999
7FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684719 Apr 2000
8FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684712 Apr 2001
9FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684706 Apr 2002
10FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684705 Apr 2003
11FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684731 Mar 2004
12FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684704 Apr 2005
13FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684712 Apr 2006
14FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684709 Mar 2007
15FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684703 Apr 2008
16FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684702 Apr 2009
17FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684705 Apr 2010
18FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684702 Apr 2011
19FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers1684709 Apr 2012
20FP/UP/OTHERS/411/19917-UPB001/1991-LUCOthers189500009 Aug 2021
A-7. Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
  (i). Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency: No
Serial No Area No of patch Area of patch Uploaded patch Uploaded GPS Date of return Authority Uploaded documentary proof
NIL
A-9. Details of Transfer of Lease
Serial No Name of person Address of person Date of transfer MMDR File Transfer Deed Conservation MoEF_file No Date of approval MoEF file
NIL
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
  (i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. : No
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Forest Division Renukoot3.790
Total3.790
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Sonbhadra3.790
Total3.790
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Murdhawa Compartment no. 133.790
3.79 0
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Area for Renewal of lease for water pipe lines3.790
Total 3.79 0
C. Maps of forest land proposed to be diverted
Division 1. : Forest Division Renukoot
  (i). Area of forest land proposed to be diverted(in ha.) : 3.79   (ii).Shape of forest land proposed to be diverted : Non Linear   (a). No. of patches : One
Patch wise details
Patch No. Area of Patch(in ha.) Kml File of Patches To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.3.79    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined
  (i). Copy of note containing justification for locating the Project in forest land:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 12   (iii). Temporary Employment(Number of person-days): 0
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : Yes   (a). Status of the Environmental Clearance to the Project: EC obtained   (b). Environmental Clearance File No.: GIL/LKO/30/90   (c). Copy of Environmental Clearance to the Project:   (d). Date of grant of Environmental Clearance to the Project: 08 Mar 2016
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: Others
Additional information Details
Documents
S.No Documents
Remarks
1Brief Note
2Grant of Lease
3Original Lease Deed
4Extension of Lease
5Extension Notification by GoUP
6Undertaking of NPV
7Undertaking of CA
8Condition of GOI
9Lease deed certificate
10FRA Certificate
11Resolution KCIL
12Renewal of Lease application
13Order of Ranchi and Indore High Court
14Undertaking for Vanswarup
15Undertaking of NPV
16Premium and lease rent
17Wildlife undertaking
18Land schedule certificate
19NPV Calculation
20Standard Conditins
21GOI letter dated 17-6-1994
22Forest gazette
23Muck disposal plan
24Appendix IV
25EDS Reply Dated 19.12.2023