FORM - B
Form for seeking prior approval under Section-2 of the proposals by the State Governments and other authorities, in respect of renewal of leases,
which have been earlier granted clearance under Forest (Conservation) Act,1980
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/ROAD/11032/2015
(ii). Name of Project for which Forest Land is required :
Palarichhina-Mallidhana-Naini motor road in District-Bageshwar
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Proposal for diversion of 4.6584 ha. forest land for construction of motor road. detail narrative attached form-11 (2.1) in additional enclosure.
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
220.5
(viii). Area of forest land proposed for diversion(in ha.):
4.6584
(ix). Non-forest land required for this project(in ha.):
0.7416
(x). Total period for which the forest land is proposed to be diverted(in years):
50
A-2.
Details of User Agency
(i). Name :
PROVINCIAL DIVISION PWD BAGESHWAR
(ii). Address1 :
Provincial Division PWD Bageshwar
(iii). Address2 :
NIL
(iv). State :
Uttarakhand
(v). District :
Bageshwar
(vi). Pin :
263642
(vii). Landmarks :
Kathayatbara
(viii). Email address :
pdpwdbgr@gmail.com
(ix). Landline Telephone No. :
220006
(x). Fax No. :
NIL
(xi). Mobile No. :
9719974196
(xii). Website (if any) :
NIL
(xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
(xiv). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Nawal
(ii). Middle Name:
Kishor
(iii). Last Name:
Diwedi
(iv). Gender:
Male
(v). Designation:
Assistant Engineer
(vi). Address 1:
Provincial Division PWD Bageshwar
(vii). Address 2:
NIL
(viii). State:
Uttarakhand
(ix). District:
Bageshwar
(x). Tehsil:
Bageshwar
(xi). Pin:
263642
(xii). Landmarks:
Kathayatbara
(xiii). Email Address:
pdpwdbgr@gmail.com
(xiv). Landline Telephone No.:
220006
(xv). Fax No.:
05963220006
(xvi). Mobile No.:
9719974196
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-7.
Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
A-9.
Details of Transfer of Lease
Serial No
Name of person
Address of person
Date of transfer
MMDR File
Transfer Deed
Conservation
MoEF_file No
Date of approval
MoEF file
NIL
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
(i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. :
No
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Bageshwar
4.6584
0.7416
Total
4.6584
0.7416
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Bageshwar
4.6584
0.7416
Total
4.6584
0.7416
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Dewaldhar
0.9225
0.09
2
Joshipalari
0.864
0.27
3
Naini
0.8919
0.3816
4
Jhiroli R.F.
1.98
0
4.6584
0.7416
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Road
4.6584
0.7416
Total
4.6584
0.7416
C.
Maps of forest land proposed to be diverted
Division 1. : Bageshwar
(i). Area of forest land proposed to be diverted(in ha.) :
4.6584
(ii).Shape of forest land proposed to be diverted :
Linear
(b). No. of Segments :
One
Segments wise details
Segmenst
Segment Area(in ha.)
Kml File of Segments
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
4.6584
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
350
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
One
District 1. : Bageshwar
(a). Village:
Kandey
(b). Area(in ha.):
9.317
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
3984,3985
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using DGPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No
Documents
Remarks
1
objection 16.01.2018 removed by EE latter No 1466/2EVB, Dt. 02.06.2018
2
NOC Van Panchayat
3
objection 17.06.2016 removed by EE Latter No 2987/2EVB, Dt. 22.12.2016
4
objection 18.01.2017 removed by EE latter No 209/2EVB, Dt 28.01.2017
5
objection removed
6
objection 10.08.2017 removed by EE latter No 2766/2EVB, Dt. 06.11.2017
7
Additional hard copy Submitted to DFO Bageshwar on Vide Latter No 696/2E.F.L., Dt. 12.04.2016 (objection removed dt. 23.04.2016)
8
objection 25.05.2017 removed by EE Latter No 1597/2EVB, Dt. 10.07.2017, Hard Copy submitted by Nodal Dehradun Dt. 13.07.2017
9
Additional hard copy already received by Nodal Office Deharadun on Dt. 29.04.2016 Vide DFO Bageshwar Latter No 2962/12-1-2, Dt. 25.04.2016 (objection removed dt. 30.04.2016)
10
1.5 Justification
11
1.6 FRA
12
2.1 Short narrative
13
2.2 Financial Sanction
14
2.3 Joint Inspection
15
Additional hard copy Submitted to DFO Bageshwar on Vide Latter No 696/2E.F.L., Dt. 12.04.2016
16
2.4 comperative chart
17
2.5 cetificate from the DM
18
2.6 Land schedule
19
2.7 category wise
20
2.8 Bar chart
21
2.9 scheme in civil and soyam
22
2.11 undertaking by the user agency
23
2.12 road side/gap filling
24
2.13 undertaking by the user agency to bear the cost
25
2.15 details of the trees
26
2.16 filling the oak trees
27
2.18 certificate of felling minimum trees
28
2.19 Muck disposal
29
2.20 whather project area is a part of national park
30
2.21 project area is within 10km radius
31
2.22 project falling within the National park
32
2.23 No voilation has taken place
33
2.24 NOC from local gram sabhas
34
2.27 work has not been started
35
2.28 Geologist report
36
2.29 Task force report
37
2.30 standard condition
38
2.31 standard condition
39
2.32 geologist report/task force
40
2.33 No historical/monuental place
41
2.34 No amimal will be effecte
42
2.35 Fuelwood, Kerosene or LPG to labours involved in project
43
2.36 Benefited villages
44
objection 23.08.2018 removed by EE latter No 3185/2EVB, Dt. 05.11.2018
45
objection Dt. 12.03.2019 removed by EE latter No 1724/2EVB, Dt. 06.07.2019
46
objection 14.12.2018 removed by EE latter No 229/2EVB, Dt. 29.01.2019
47
objection 12.07.2019 removed by EE latter no 654/2EVB, Dt. 26.02.2020
48
Hard Copy submitted CF Office Almora on 7.5.2022 in 4 copies received letter attached
49
2.37 NPV calculation
50
2.43 Check lisht/Fact Sheet
51
objection dtd 7.7.2022 removed vide this office letter no. 2319/2E.Wa.Bhoo dtd 21.09.2022
52
objection removed vide this office letter no. 498/2E-Wa-Bhoo Dtd 24.03.2022
53
certificate regarding
54
objection 03.03.2020 removed by EE latter no 212/2EVB, Dt. 28.01.2022
55
CA scheme
56
Objection removed vide this office letter no. 2457 dtd 5.9.2024
57
Objection removed vide this office letter no. 1306 dtd 16.05.2023
58
objection removed vide this office letter no-815, Dt. 15.04.2026