FORM - B
Form for seeking prior approval under Section-2 of the proposals by the State Governments and other authorities, in respect of renewal of leases,
which have been earlier granted clearance under Forest (Conservation) Act,1980
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/RJ/TRANS/28622/2017   (ii). Name of Project for which Forest Land is required : Babai (RRPVNL) - Bhiwani (PG) 400kV D/C Transmission Line   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The project is initiated by ministry of Power, Govt. of India under “system strengthening scheme in northern region (NRSSXXXVI) along with LILO of sikar-Neemrana 400kV D/C line at Babai (RRVPNL)”. The necessary approvals from Ministry of power have been received for the construction of the above tra   (iv). State : Rajasthan   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 11000   (viii). Area of forest land proposed for diversion(in ha.): 13.015   (ix). Non-forest land required for this project(in ha.): 243.578   (x). Total period for which the forest land is proposed to be diverted(in years): 35
A-2. Details of User Agency
  (i). Name : NRSS XXXVI TRANSMISSION LIMITED   (ii). Address1 : Shatabdi Bhawan, B 12 & 13, Sector 4, Noida   (iii). Address2 : NIL   (iv). State : Uttar Pradesh   (v). District : Gautam Buddha Nagar   (vi). Pin : 201301   (vii). Landmarks : NIL   (viii). Email address : sect.nrss@gmail.com   (ix). Landline Telephone No. : NIL   (x). Fax No. : NIL   (xi). Mobile No. : 7042053497   (xii). Website (if any) : NIL   (xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past  
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
  (xiv). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Shashank Takawale   (ii). Middle Name: NIL   (iii). Last Name: NIL   (iv). Gender: NIL   (v). Designation: Head PMU   (vi). Address 1: NRSS XXXVI TRANSMISSION LIMITED, TATA Power Company Limited, Shatabdi Bhawan, B 12 & 13, Sector 4, Noida   (vii). Address 2: NIL   (viii). State: Tamil Nadu   (ix). District: Anantapur   (x). Tehsil: NIL   (xi). Pin: 201301   (xii). Landmarks: NIL   (xiii). Email Address: sect.nrss@gmail.com   (xiv). Landline Telephone No.: NIL   (xv). Fax No.: NIL   (xvi). Mobile No.: 7042053497   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-7. Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
A-9. Details of Transfer of Lease
Serial No Name of person Address of person Date of transfer MMDR File Transfer Deed Conservation MoEF_file No Date of approval MoEF file
NIL
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
  (i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. : No
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Jhunjhunu Territorial13.015243.578
Total13.015243.578
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.jhunjhunu13.015243.578
Total13.015243.578
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Sardarpura05.428
2Babai (CT)00.644
3Pratappura09.108
4Gadrata5.5632.349
5Pupurana7.08535.051
6Badalwas0.36716.377
7Tyonda019.285
8Dada Fatehpura08.372
9Nalpur07.912
10Gorir06.532
11Doodhwa Nangliya09.488
12Kakrai04.324
13Rawan07.82
14Ganeshpura04.048
15Balaha Khurd (147)06.072
16Balaha Kalan07.636
17Nawta05.796
18Pacheri kalan011.34
19Rasoolpur07.728
20Santor09.408
21Bamanwas06.716
22Panthorli03.036
23Ghaseda09.684
24Udamandi06.544
25Nimbas06.176
26Nanwas06.44
27kuhadwas06.9
28Jaitpur03.128
29Dalenwas010.236
13.015 243.578
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Construction of Transmission Line13.0149962243.5779994
Total 13.0149962 243.5779994
C. Maps of forest land proposed to be diverted
Division 1. : Jhunjhunu Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 13.015   (ii).Shape of forest land proposed to be diverted : Linear   (b). No. of Segments : Seven
Segments wise details
Segmenst Segment Area(in ha.) Kml File of SegmentsTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.5.563    View File
2.0.376    View File
3.6.709    View File
4.0.12    View File
5.0.034    View File
6.0.08    View File
7.0.133    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 10   (iii). Temporary Employment(Number of person-days): 164250
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : Yes   (a). Whether Project or a part thereof is located within a Protected Area ? : Yes   (b). Status of approval of the Supreme Court : Application yet to b   (ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project : Application under process   (a). Date of submission of proposals : 16 Feb 2018   (b). Current status : NIL
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1Compliance report dated 20/02/2018
2EDS reply
3coordinates of tower located in forest and non forest area
4Reply to EDS dated 06/11/2017
5No Other Alternate Route
6layout of line
7Environment Clearance not required
8Rehabilitation not required
9undertaking for Muck Disposal
10Employee Structure as per EDS
11Gadrata Village Map AP3 to AP4
12Reply to EDS II raised on dated 06/10/2017
13Gazette publication by Ministry of Power, Govt. Of India
14Letter of Intent - project award
15Sec-68 approval from CEA
16Cost Benefit analysis not required as area is below 20Ha
17Detail note on project
18Land schedule
19Land schedule for non forest
20Minimum use of forest land
21No other alternative available
22undertaking for NPV
23undertaking for FRA
24undertaking for CA
25Gadrata village Jamabandi
26Pupurna village Jamabandi
27Badalwas village Jamabandi
28Badalwas village map
29Pupurna village map
30Bar Chart
31Reply to EDS raised by DFO dated 12-12-2017
32undertaking for installating indolite Bird flight Diverters on transmission line conductors to save birds against collision & electrocution.