FORM - B
Form for seeking prior approval under Section-2 of the proposals by the State Governments and other authorities, in respect of renewal of leases,
which have been earlier granted clearance under Forest (Conservation) Act,1980
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/JH/TRANS/18900/2016   (ii). Name of Project for which Forest Land is required : 132 kV D/C Ramchandrapur-Jadugoda Transmission Line   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 132 kV D/C Ramchandrapur-Jadugoda Transmission Line is a part of State Corridor and shall evacuate power to benefit power situation in East Singhbhum District in Jharkhand State.   (iv). State : Jharkhand   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 3100   (viii). Area of forest land proposed for diversion(in ha.): 12.845   (ix). Non-forest land required for this project(in ha.): 15.72   (x). Total period for which the forest land is proposed to be diverted(in years): 50
A-2. Details of User Agency
  (i). Name : JHARKHAND URJA SANCHARAN NIGAM LIMITED   (ii). Address1 : Engineering Building , H.E.C, Dhurwa, Ranchi   (iii). Address2 : NIL   (iv). State : Jharkhand   (v). District : Ranchi   (vi). Pin : 834004   (vii). Landmarks : NIL   (viii). Email address : jcptatanagar@gmail.com   (ix). Landline Telephone No. : 2400483   (x). Fax No. : 2400123   (xi). Mobile No. : 9771463614   (xii). Website (if any) : NIL   (xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past  
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
  (xiv). Legal status of User Agency : State PSU
A-3. Details of Person Making Application
  (i). First Name: Rajesh   (ii). Middle Name: Kumar   (iii). Last Name: Saini   (iv). Gender: Male   (v). Designation: Manager   (vi). Address 1: 400 kV Sub station, POWER GRID Corporation of India Ltd. H. No. C-9 Vill: Ramchandrapur, PO: Gamharia, Distt: Saraikela Jharkhand-832108   (vii). Address 2: NIL   (viii). State: Jharkhand   (ix). District: Seraikela Kharsawan   (x). Tehsil: NIL   (xi). Pin: 832108   (xii). Landmarks: NIL   (xiii). Email Address: jcptatanagar@gmail.com   (xiv). Landline Telephone No.: 2944265   (xv). Fax No.: NIL   (xvi). Mobile No.: 9771463614   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-7. Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
A-9. Details of Transfer of Lease
Serial No Name of person Address of person Date of transfer MMDR File Transfer Deed Conservation MoEF_file No Date of approval MoEF file
NIL
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
  (i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. : No
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Dalbhum8.9934.51
2.Saraikela3.85211.21
Total12.84515.72
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.East Singhbhum8.9934.51
2.Seraikela Kharsawan3.85211.21
Total12.84515.72
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Jamshedpur6.9983.14
2Potka1.9251.31
3Musabani0.070.06
4Gamharia3.85211.21
12.845 15.72
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Tower0.27360.36
2Passing of Transmission Line conductor12.571415.36
Total 12.845 15.72
C. Maps of forest land proposed to be diverted
Division 1. : Saraikela
  (i). Area of forest land proposed to be diverted(in ha.) : 3.852   (ii).Shape of forest land proposed to be diverted : Linear   (b). No. of Segments : One
Segments wise details
Segmenst Segment Area(in ha.) Kml File of SegmentsTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.3.852    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
Division 2. : Dalbhum
  (i). Area of forest land proposed to be diverted(in ha.) : 8.993   (ii).Shape of forest land proposed to be diverted : Linear   (b). No. of Segments : One
Segments wise details
Segmenst Segment Area(in ha.) Kml File of SegmentsTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.8.993    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined
  (i). Copy of note containing justification for locating the Project in forest land: No Data   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: No
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis: No Data
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1Sir, Reply to Seraikela Forest Div query has been attached pl.
2JJ Land NOC JSR forest div.
3JJ Land Schedule JSR forest div.
4GM Land NOC JSR forest div.
5GM Land schedule JSR forest div.
6Forest (PF+RF) & JJ Land schedule JSR forest div.
7Total land schedule Forest (PF+RF),JJ & GM land schedule JSR & Seraikela forest div.
8Plan of line
9Tree summery PF RF JSR forest Div
10Tree summery JJ land JSR forest Div
11Undertaking Compensatary Afforestation
12Undertaking for NPV
13Undertaking for Min. use of Forest land R-J
14Undertaking for Trees to be felled or Pollard
15Geo map Mauza Talsha JSR Forest Div
16Geo map Mauza Turamdih JSR Forest Div
17Geo map Mauza Kudada JSR Forest Div
18Geo map Mauza Domjuri JSR Forest Div
19Geo map Mauza Khursi JSR Forest Div
20Geo map Mauza Mechuya JSR Forest Div
21Geo map Mauza Dhurku JSR Forest Div
22Geo map Mauza Ichra JSR Forest Div
23Compliance to query dated 07/05/2016
24NOC FRA Seraikela Forest Div.
25Forest JJ land schedule Seraikela Forest Div.
26NOC JJ land Seraikela Forest Div.
27NOC GM land Seraikela Forest Div.
28GM land schedule Seraikela Forest Div.
29Tree summery Seraikela forest Div
30Geo Ref. map Mauza Shrirampur Seraikela Forest Div.
31Geo Ref Map Mauza Dugdha Seraikela forest div.
32Geo Ref Map Mauza Guhandih Seraikela forest div.
33Geo Ref Map Mauza Sarupdih in Seraikela forest div.
34Geo Ref Map Mauza Khuchidih in Seraikela forest div.
35Geo Ref Map Mauza Birarajpur in Seraikela forest div.