FORM - B
Form for seeking prior approval under Section-2 of the proposals by the State Governments and other authorities, in respect of renewal of leases,
which have been earlier granted clearance under Forest (Conservation) Act,1980
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/JH/TRANS/153319/2022   (ii). Name of Project for which Forest Land is required : 132 KV DC KOLEBIRA KAMDARA TRANSMISSION LINE   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 132 KV D/C Kolebira - Kamdara Transmission Line   (iv). State : Jharkhand   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 15650.4416   (viii). Area of forest land proposed for diversion(in ha.): 7.1400215   (ix). Non-forest land required for this project(in ha.): 98.1599785   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : JHARKHAND URJA SANCHARAN NIGAM LIMITED   (ii). Address1 : KUSAI COLONY DORANDA RANCHI   (iii). Address2 : NIL   (iv). State : Jharkhand   (v). District : Ranchi   (vi). Pin : 834002   (vii). Landmarks : NIL   (viii). Email address : jusnl.simdega@gmail.com   (ix). Landline Telephone No. : 0651-223368   (x). Fax No. : NIL   (xi). Mobile No. : 9431707301   (xii). Website (if any) : NIL   (xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past  
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
  (xiv). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Rajeev   (ii). Middle Name: NIL   (iii). Last Name: Ranjan   (iv). Gender: NIL   (v). Designation: Dy. General Manager   (vi). Address 1: KUSAI COLONY DORANDA RANCHI   (vii). Address 2: NIL   (viii). State: Jharkhand   (ix). District: Ranchi   (x). Tehsil: NIL   (xi). Pin: 834002   (xii). Landmarks: NIL   (xiii). Email Address: jusnl.simdega@gmail.com   (xiv). Landline Telephone No.: NIL   (xv). Fax No.: NIL   (xvi). Mobile No.: 9431707301   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-7. Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
A-9. Details of Transfer of Lease
Serial No Name of person Address of person Date of transfer MMDR File Transfer Deed Conservation MoEF_file No Date of approval MoEF file
NIL
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
  (i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. : No
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Gumla3.272014560.8567755
2.Simdega3.86800737.303203
Total7.140021598.1599785
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Gumla3.272014560.8567755
2.Simdega3.86800737.303203
Total7.140021598.1599785
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Murga0.5314923.383692
2Kindarkela0.5530962.122218
3Areya0.5076652.988771
4Kelga0.2855082.17260253
5Konbir0.4516348.027239
6Basiya0.33655275.8798553
7Suturbula0.3481053.157161
8Nawatoli0.28610.6556
9Bhanwarpahari1.6200586.986879
10Kolebira0.7539320.213482
11Larba0.4924694.551633
12Jurkela0.1713571.370266
13Jamatoli010.29746
14Karamtoli05.097841
15Patura04.967155
16Kurdega00.998725
17Tirra04.553383
18Longa0.2579626.172251
19Garai05.933253735
20Kamdara05.332102735
21Jariya00.6013
22Agharma0.54409081.20358
7.1400215 86.6664503
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Tower0.07241.4
2Conductor7.067696.759978
Total 7.14 98.159978
C. Maps of forest land proposed to be diverted
Division 1. : Gumla
  (i). Area of forest land proposed to be diverted(in ha.) : 3.2720145   (ii).Shape of forest land proposed to be diverted : Linear   (b). No. of Segments : One
Segments wise details
Segmenst Segment Area(in ha.) Kml File of SegmentsTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.3.2720145    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
Division 2. : Simdega
  (i). Area of forest land proposed to be diverted(in ha.) : 3.868007   (ii).Shape of forest land proposed to be diverted : Linear   (b). No. of Segments : One
Segments wise details
Segmenst Segment Area(in ha.) Kml File of SegmentsTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.3.868007    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 6   (iii). Temporary Employment(Number of person-days): 186
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1DETAIL NOTE ON PROJECT
2FORM A
3FOREST LAND SCHEDULE SIMDEGA DISTRICT
4FOREST LAND SCHEDULE GUMLA DISTRICT
5All Undertaking
6CO LSD Kolebira Block
7CO LSD Kamdara Block
8CO LSD Basiya Block
9EDS Reply
10FRA Certificate issued by Simdega Dist.
11GMJJ NOC_Kolebira Kamdara TL_Gumla Dist
12GMJJ NOC_Kolabira Kamdara TL_Simdega Dist
13Tree Enumeration List ok Kolebira Kamdara TL
14FRA-NOCof Kolabira kamdara_Simdega TL_Simdega Dist with resolution
15FRA Form 1 kolebira kamdara TL_Gumla Dist with resolution
16Kolebira -kamdara EDS reply letter
17Patchwise Forest Area details of Simdega Division
18Patchwise Forest Area details of Gumla Division
19CA Demand note for 12 years raised by DFO,Gumla Forest Division.