A. General Details
A-1. Project Details
  (i). Proposal No. : FP/JH/RAIL/47332/2020   (ii). Name of Project for which Forest Land is required : Magadh Railway Siding   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The application for diversion of Forest Land for 121.29 Ha is intended for construction of railway siding for evacuation of Coal. The proposal includes construction of Railway siding, Silo, CHP, Belt conveyor, Culvert & Bridges, Green belt, Road, Infrastructure etc. The alignment has minimum forest   (iv). State : Jharkhand   (v). Category of the Proposal : Railway   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 40210   (viii). Area of forest land proposed for diversion(in ha.): 121.29   (ix). Non-forest land required for this project(in ha.): 130.22   (x). Total period for which the forest land is proposed to be diverted(in years): 30
A-2. Details of User Agency
  (i). Name : Central Coalfields Limited   (ii). Address1 : DARBHANGA HOUSE, CCL, RANCHI   (iii). Address2 : NIL   (iv). State : Jharkhand   (v). District : Ranchi   (vi). Pin : 834029   (vii). Landmarks : NIL   (viii). Email address : pomagadhccl@gmail.com   (ix). Landline Telephone No. : 2365806   (x). Fax No. : NIL   (xi). Mobile No. : 8987788576   (xii). Website (if any) : www.centralcoalfields.in   (xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past  
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
  (xiv). Legal status of User Agency : Central PSU
A-3. Details of Person Making Application
  (i). First Name: Sadala Satyanaran   (ii). Middle Name: NIL   (iii). Last Name: NIL   (iv). Gender: Male   (v). Designation: PO   (vi). Address 1: Office of Project Officer, Magadh, kundi, tandwa Jharkhand   (vii). Address 2: NIL   (viii). State: Jharkhand   (ix). District: Chatra   (x). Tehsil: NIL   (xi). Pin: 825321   (xii). Landmarks: NIL   (xiii). Email Address: pomagadhccl@gmail.com   (xiv). Landline Telephone No.: 236004   (xv). Fax No.: NIL   (xvi). Mobile No.: 8987788576   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-7. Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
A-9. Details of Transfer of Lease
Serial No Name of person Address of person Date of transfer MMDR File Transfer Deed Conservation MoEF_file No Date of approval MoEF file
NIL
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
  (i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. : No
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Chatra South17.010
2.Latehar104.28130.22
Total121.29130.22
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Chatra17.010
2.Latehar104.28130.22
Total121.29130.22
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Kundi10.280
2Kurlonga6.730
3Ara41.4567.27
4Chamatu16.8926.09
5Chetar14.038.37
6Seregada17.020.06
7Phulbasia13.3528.43
8Chedra/Charra1.540
121.29 130.22
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Bridge and Culvert0.550.46
2Conveyor, Silo etc2.2811.12
3Road3.462.35
4Railway Line and its embankment11533.33
5CHP & Ground Bunkers082.96
Total 121.29 130.22
C. Maps of forest land proposed to be diverted
Division 1. : Chatra South
  (i). Area of forest land proposed to be diverted(in ha.) : 17.01   (ii).Shape of forest land proposed to be diverted : Linear   (b). No. of Segments : One
Segments wise details
Segmenst Segment Area(in ha.) Kml File of SegmentsTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.17.01    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
Division 2. : Latehar
  (i). Area of forest land proposed to be diverted(in ha.) : 104.28   (ii).Shape of forest land proposed to be diverted : Linear   (b). No. of Segments : One
Segments wise details
Segmenst Segment Area(in ha.) Kml File of SegmentsTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.104.28    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 300   (iii). Temporary Employment(Number of person-days): 4725000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : Yes
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: NIL   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: NIL   (iii) . Reason for not providing Non-Forest Land: NIL
Additional information Details
Documents
S.No Documents
Remarks
1NOC of GMJJ Land
2Tree Enumeration of Magadh Railway Siding Chatra Division
3Cadastral Map Chatra Division
4Annexure 4 List of proposals submitted in Past and Offline Part-1 Form A
5Reply of EDS raised vide no 2107 dated 23 10 2024
6Reply of EDS raised vide letter no 218 dated 28.01.2025 from DFO Chatra South
7Revised Online Form A Part 1
8Reply of EDS raised vide letter no 558 dated 23.04.2024 from DFO Latehar
9CA Land Chatra Part Cadastral DGPS and Toposheet
10Annexure-7 Layout Land Use and Length and Width of Magadh Railway Siding
11Checklist No-07 Statement showing details of Forest Area proposed in Chatra South Division
12Authenticated Land Schedule of Magadh Railway Siding Laterhar Part
13Authenticated Land Schedule of Magadh Railway Siding Chatra Part
14Reply of EDS raised vide letter no 303 dated 13.02.2024 in respect of forest diversion from DFO Chatra South
15Reply of EDS raised vide letter no 461 dated 21.09.2024 in respect of forest diversion of Magadh Railway Siding
16Annexure-1 Authorization Letter
17Annexure-2 Acknowledgment Slip
18Annexure-3 Check list for Magadh Railway Siding Latehar Division Part as per JH Forest Dept. guidelines.
19Annexure-5 Detailed Note for Magadh Railway Siding
20Annexure-6 DGPS and Toposheet Latehar Portion
21Annexure-8 Checklist No-07 Details of Forest Land in Latehar Division
22Annexure-9 Statement of Non-Forest Land Latehar Division
23Annexure-10 Undertaking of No Alternative Suitable Non-Forest Land
24Annexure-11 Justification of Project Location
25Annexure-12 Minimum Use of Forest Land Latehar Division
26Annexure-13 Undertaking for Payment of CA Latehar Division
27Annexure-14 Undertaking for Payment of Net Present Value Latehar Division
28Annexure-15 Undertaking for FRA
29Annexure-16 Tree Enumuration Latehar Division Magadh Railway Siding
30Annexure-18 CA Land Latehar Part Cadastral DGPS Toposheet
31Annexure-21 Undertaking for obtaining NOC from State Pollution Control Board
32Annexure-22 Undertaking for Catchment Area Treatment Plan
33Annexure-23 Cost Benefit Analysis Report
34Annexure-24 Land Acquisition Details
35Annexure-25 Certificate in Prapatra I and II for Magadh Railway Siding
36Annexure-26 Alternate Route Analysis
37Annexure-27 Undertaking Regarding Land Details
38Annexure-28 Undertaking for Change in Condition
39Annexure-29 Justification for Modification of Proposal
40Annexure-30 Undertaking for Archaeological Structure
41Annexure-31 Undertaking For Ecological Sensitive Area
42Annexure-32 Undertaking for Wild Life Management Plan
43Annexure-33 Undertaking for Transportation Network
44Annexure-34 DPR Magadh Railway Siding
45Annexure-35 Cadastral Map CS Magadh Railway Siding Latehar
46Annexure-36 Cadastral Map RS Magadh Railway Siding Latehar
47Check List No-11 Minimum Use of Forest Land Chatra Division
48Check List No-12 Undertaking for Payment of CA Chatra Division
49Check List No-13 Undertaking for Payment of Net Present Value Chatra Division
50Checklist of Magadh Railway Siding as per JH Forest Dept. guidelines Chatra Division
51DGPS and Toposheet Magadh Railway Siding Chatra Division