FORM - B
Form for seeking prior approval under Section-2 of the proposals by the State Governments and other authorities, in respect of renewal of leases,
which have been earlier granted clearance under Forest (Conservation) Act,1980
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/HP/ROAD/151932/2022   (ii). Name of Project for which Forest Land is required : Construction of New 2 Lane with Paved Shoulder of Hamirpur Bypass of NH-88 (New NH-103 & 3 ) (Design Chainage-Km.121+175 to Km.138+295, Design Length-17.120 Km) in the State of Himachal Pradesh   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Hamirpur Bypass is a Green field alignment which is proposed to bypass the congested location of Hamirpur town. The bypass is 2 lane with Paved Shoulder which commences near Dravsai village in Hamirpur Tehsil at km 121+175 and ends at km 138+295 near Bhalun village in Nadaun Tehsil of Hamirpur d   (iv). State : Himachal Pradesh   (v). Category of the Proposal : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 71525   (viii). Area of forest land proposed for diversion(in ha.): 12.8537   (ix). Non-forest land required for this project(in ha.): 50.6327   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : National Highways Authority of India   (ii). Address1 : G-5 & 6, Sector-10, Dwarka, New DElhi-110075   (iii). Address2 : G-5 & 6, Sector-10, Dwarka, New DElhi-110075   (iv). State : Delhi   (v). District : South West   (vi). Pin : 110075   (vii). Landmarks : G-5 & 6,Sec-10   (viii). Email address : piuhamirpur@nhai.org   (ix). Landline Telephone No. : 25074200   (x). Fax No. : 25093543   (xi). Mobile No. : 8376900598   (xii). Website (if any) : www.nhai.org   (xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past  
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
  (xiv). Legal status of User Agency : Central Government
A-3. Details of Person Making Application
  (i). First Name: Vikram   (ii). Middle Name: Singh   (iii). Last Name: Meena   (iv). Gender: Male   (v). Designation: Project Director   (vi). Address 1: NATIONAL HIGHWAYS AUTHORITY OF INDIA   (vii). Address 2: PROJECT IMPLEMENTATION UNIT - HAMIRPUR, HOUSE NO.-218A, KANWAL COMPLEX, WARD NO.-1, KRISHNA NAGAR, HAMIRPUR   (viii). State: Himachal Pradesh   (ix). District: Hamirpur   (x). Tehsil: NIL   (xi). Pin: 171001   (xii). Landmarks: PAKABAROH CHOWK   (xiii). Email Address: piuhamirpur@nhai.org   (xiv). Landline Telephone No.: 223794   (xv). Fax No.: NIL   (xvi). Mobile No.: 8376900598   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-7. Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
A-9. Details of Transfer of Lease
Serial No Name of person Address of person Date of transfer MMDR File Transfer Deed Conservation MoEF_file No Date of approval MoEF file
NIL
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
  (i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. : No
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Hamirpur12.853750.6327
Total12.853750.6327
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Hamirpur12.853750.6327
Total12.853750.6327
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Dravsai (45/14)01.1606
2Sai Brahmana (45/21)01.7039
3Sai Ugialla (45/20)00.0471
4Lahad (46/30)07.583
5Jasor (46/14)1.54450.0279
6Masyana (37/17)6.14191.1059
7Payadkad (37/10)00.0855
8Bahdla (37/3)0.03422.3942
9D. P. F. Chak Bajuri (37/13)0.47220
10Kaswar (37/13)0.01922.0334
11Ghanotla (37/15)03.6057
12Khagal (37/14)0.01745.3665
13Kamlah (37/7)03.6884
14Baleta Khurd (37/22)02.2458
15Baleta Kalan (37/29)02.1628
16Dumpsite - Lahar00.984
17Dumpsite - Ghanotla01.7002
18Dumpsite - Khagal01.8462
19Dumpsite - Baleta Kalan00.1051
20Sanahi Kalan (26/10)00.7488
21Kohlwin (26/8)01.546
22Atialu (26/12)01.9955
23Telkad (26/4)01.6026
24Bharyal (26/1)0.25060.2698
25Badwana (26/23)02.4812
26DPF Kunna (25/27)2.55280.1091
27Kunna (25/27)00.0571
28Ralian-Di-Bahal (25/49)0.4470
29Syalan-Di-Bahal (25/35)0.04610.1304
30D.P.F. Loharkad (20/21)0.28950
31Loharkad (20/21)0.62511.5473
32Dangri (20/18)0.33671.6896
33Chilbahal (20/10)00.5326
34Bhalun (20/23)0.07650.0765
12.8537 50.6327
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Bypass Road12.478243.7631
2Bridges0.34980.7896
3VOP0.02570
4Wayside Amenities01.4445
5Disposal of excess earth04.6355
Total 12.8537 50.6327
C. Maps of forest land proposed to be diverted
Division 1. : Hamirpur
  (i). Area of forest land proposed to be diverted(in ha.) : 12.8537   (ii).Shape of forest land proposed to be diverted : Linear   (b). No. of Segments : One
Segments wise details
Segmenst Segment Area(in ha.) Kml File of SegmentsTo view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.12.8537    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 10   (iii). Temporary Employment(Number of person-days): 73000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: NIL   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: NIL   (iii) . Reason for not providing Non-Forest Land: NIL
Additional information Details
Documents
S.No Documents
Remarks
1Non-Availability Certificate-Reply to query raised by Nodal dated 24.05.2022
2Revised Disposal plan for excess earth-12.8537 ha.
3Revised Length and width of -12.8537 ha.
4Revised Undertaking FRA-12.8537 ha.
5Revised Undertaking CA-12.8537 ha.
6Revised Undertaking NPV -12.8537 ha.
7Revised Undertaking Additional NPV -12.8537 ha.
8NHAI Compliance letter to the EDS raised by Nodal Officer dated 11.02.2022
9Point No. 2 EDS Compliance - Village Certificate from concerned SDM
10Point No. 6 EDS Compliance - Distance from PA/ESZ obtained from DFO
11Point No. 7 EDS Compliance - Disposal Plan for excess earth quantity
12Point No. 8 EDS Compliance - Letter submitted to DC Hamirpur for obtaining Non-availability Certificate and Undertaking by User Agency to obtain the same.
13Point No. 9 EDS Compliance - Length and width of the proposed widening in forest and non forest land
14Compliance to EDS dated 19.05.2022 - Letter submitted to DC Hamirpur for obtaining Non-availability Certificate and Undertaking by User Agency to obtain the same.
15Revised Disposal Plan of Excess earth
16Revised Length and width of proposed road in forest and non-forest land
17Revised Certificate of non-availability of non-forest land for the project for 14.6061 ha of forest land proposed for the project
18Revised Undertaking for Additional NPV
19Revised Undertaking for CA
20Revised Undertaking for NPV
21Revised Undertaking for FRA
22Compliance to Shortcomings raised as per REC MoM dated 25.05.2023
23Point-wise Compliance to EDS raised by IRO on 19.04.2023 along with Enclosure - Single PDF file uploaded
24Compliance to Point No. 1 of IRO EDS dated 19.04.2023 - Disposal Plan for excess earth quantity
25Compliance to observations of IRO dated 21.06.2023 post REC meeting
26Compliance to Point No. 1 of IRO EDS dated 19.04.2023 - Length & Width
27Compliance to Point No. 1 of IRO EDS dated 19.04.2023 - FRA Undertaking