FORM - B
Form for seeking prior approval under Section-2 of the proposals by the State Governments and other authorities, in respect of renewal of leases,
which have been earlier granted clearance under Forest (Conservation) Act,1980
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/HP/IRRIG/155846/2022
(ii). Name of Project for which Forest Land is required :
Construction of Adi Badri Dam
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Haryana Government has conceptualized the construction of Adi badri Dam on Somb Nadi for the rajuvenation of Sarasvati River. Flood water will be checked by construction of this Dam and it will be diverted from a barrage to be constructed aprox. 2km d/s of dam to Sarasvati Reservoir. Thereafter stor
(iv). State :
Himachal Pradesh
(v). Category of the Proposal :
Irrigation
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
21533
(viii). Area of forest land proposed for diversion(in ha.):
31.72
(ix). Non-forest land required for this project(in ha.):
0.67
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
IRRIGATION AND WATER RESOURCES DEPARTMENT HARYANA
(ii). Address1 :
Sinchai Bhawan, Sec-5, Panchkula, Haryana
(iii). Address2 :
Executive Engineer, Sarasvati Heritage Division No. 1, Jagadhri
(iv). State :
Haryana
(v). District :
Panchkula
(vi). Pin :
135001
(vii). Landmarks :
Canal Colony
(viii). Email address :
xenshdjdr@gmail.com
(ix). Landline Telephone No. :
237027
(x). Fax No. :
NIL
(xi). Mobile No. :
9896531219
(xii). Website (if any) :
NIL
(xiii). Details of Proposals seeking prior approval of Central Government under the Act for diversion of forest land submitted by the User Agency in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
(xiv). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Vikas
(ii). Middle Name:
NIL
(iii). Last Name:
Kataria
(iv). Gender:
Male
(v). Designation:
S.D.O
(vi). Address 1:
Sarasvati Heritage Sub Division No. 4, Canal Colony, Jagadhri, Haryana
(vii). Address 2:
NIL
(viii). State:
Haryana
(ix). District:
Yamunanagar
(x). Tehsil:
Jagadhri
(xi). Pin:
135001
(xii). Landmarks:
Hotel Sapphire
(xiii). Email Address:
xenshdjdr@gmail.com
(xiv). Landline Telephone No.:
237027
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9896531219
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
A-7.
Details of the forest land returned back to the State Forest Department or any other Authority from the forest land diverted in favour of the user agency
A-9.
Details of Transfer of Lease
Serial No
Name of person
Address of person
Date of transfer
MMDR File
Transfer Deed
Conservation
MoEF_file No
Date of approval
MoEF file
NIL
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
(i). Whether any proposal seeking prior approval of Central Government under the Act for diversion of forest land required for the project has been submitted in the past?. :
No
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Nahan
31.72
0.67
Total
31.72
0.67
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Sirmaur
31.72
0.67
Total
31.72
0.67
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Matar
20.62
0.67
2
Bheron
11.1
0
31.72
0.67
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Submerged Area
27.23
0.67
2
Control room, rest room and parking space
0.19
0
3
Main structure
4.29
0
Total
31.71
0.67
C.
Maps of forest land proposed to be diverted
Division 1. : Nahan
(i). Area of forest land proposed to be diverted(in ha.) :
31.72
(ii).Shape of forest land proposed to be diverted :
Non Linear
(a). No. of patches :
One
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
31.72
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using DGPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
50
(iii). Temporary Employment(Number of person-days):
60000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
Others
Additional information Details
Documents
S.No
Documents
Remarks
1
Aerial Distance map of Adi Badri Dam from Kalesar & Simbalwara NP
2
Undertaking for payment of additional NPV
3
certificate of DC concerned that no alternative suitable non forest land is available
4
MoU/Consent letter
5
Implementation agreement/TEC
6
NPV undertaking
7
CA undertaking
8
Reply to the Nodal officer observation dated 01.06.2022
9
certificate of DC Sirmaur for non availability of land for CA
10
NOC from IPH Department H.P.
11
NOC from G.P Matar.
12
NOC from wild life Haryana
13
NOC from wild life H.P
14
Copy of Signed MoU between Haryana & H.P
15
NOC from Fisheries department H.P
16
notification of ESZ of Kalesar Wildlife Sanctuary
17
NOC for Muck dumping site
18
reply to EDS of DFO dated 02 dec 2022
19
copy of sale deed
20
certificate for FRL
21
Signed copy of complete proposal folder
22
Certificates from DC Sirmair
23
FRL certificate
24
Layout plan
25
reply to EDS 02.05.2024
26
reply to EDS 17.05.2024
27
Joint inspection report
28
CAT Plan
29
updated checklist no 8
30
Land suitability certificate for CA site by DFO Fatehabad
31
Environment clearance
32
Undertaking for FRA for providing complete proceedings
33
Undertaking for payment of cost for implementation of SMCP
34
Muck Management Plan
35
Reply to EDS dated 11.07.2023
36
DGPS map of CA site
37
Shifting of Electricity Lines
38
Reply to EDS dated 11.07.2023
39
Certificate from SDM nahan
40
check list no. 7 updated and legal status of Forest land addede
41
CSMRS report on Adi Badri Dam Quarry site in Jaitpur Haryana
42
EDS complaince on dated 19.07.2024