FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/UK/ROAD/11039/2015   (ii). Name of Project for which Forest Land is required : Construction of Diwalikhal-Kimoli to Narayanbagar Motor Road   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Diwalikhal-Kimoli to Narayanbagar Motor Road -This Road will connect Gairsain to Narayanbagar,Tharali,and Dewal Block and reduces travel distance of about 29 km in connecting two Blocks   (iv). State : Uttarakhand   (v). Category of the Proposal : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 364   (viii). Area of forest land proposed for diversion(in ha.): 6.52   (ix). Non-forest land required for this project(in ha.): 0   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : PWD CD GAIRSAIN   (ii). Address1 : Construction Division PWD Gairsain   (iii). Address2 : NIL   (iv). State : Uttarakhand   (v). District : Chamoli   (vi). Pin : 246428   (vii). Landmark : NIL   (viii). Email address : eecdgairsain@gmail.com   (ix). Landline Telephone No. : 1363-278533   (x). Fax No. : 1363-   (xi). Mobile No. : 9897163389   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Aditya   (ii). Middle Name: Nath   (iii). Last Name: Thakur   (iv). Gender: Male   (v). Designation: Assistant Engineer   (vi). Address 1: Construction Division PWD Gairsain   (vii). Address 2: NIL   (viii). State: Uttarakhand   (ix). District: Chamoli   (x). Tehsil: Gair Sain   (xi). Pin: 246428   (xii). Landmark: NIL   (xiii). Email Address: eecdpwdgairsain@gmail.com   (xiv). Landline Telephone No.: 1363-278533   (xv). Fax No.: NIL   (xvi). Mobile No.: 9897258773   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Badrinath,Gopeshwar6.520
Total6.520
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Chamoli6.520
Total6.520
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Diwalikhal3.50
2Kimoli2.870
Total 6.37 0
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Muck Disposal 10.0250
2Muck Disposal 20.0250
3Muck Disposal 30.050
4Muck Disposal 40.050
5Road kedarnath wild life2.80
6Road badrinath gopeshwar3.570
Total 6.52 0
C. Maps of forest land proposed to be diverted
Division 1. : Badrinath,Gopeshwar
  (i). Area of forest land proposed to be diverted(in ha.) : 6.52   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.6.52    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 0   (iii). Temporary Employment(Number of person-days): 10000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Yes   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii). No. of districts involved for raising Compensatory Afforestation: 1   (iv). No. of patches: Two
District 1. : Chamoli
  (a). Village: Gherbunga   (b). Area(in ha.): 11.5   (c). Copy of KML file of the patch:     View File   (d). Khasra details: 432   (e). Present owner: Others   (f). Copy of ownership proof:   (g). Copy of Mou/agreement executed between the Present owner and the User Agency:   (h). Copy of non encumberence certificate for the forest land:
District 2. : Chamoli
  (a). Village: Gherbunga   (b). Area(in ha.): 1.544   (c). Copy of KML file of the patch:     View File   (d). Khasra details: 432   (e). Present owner: Others   (f). Copy of ownership proof:   (g). Copy of Mou/agreement executed between the Present owner and the User Agency:   (h). Copy of non encumberence certificate for the forest land:
  (v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:   (vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No Documents
Remarks
1Joint Inspction Report
2Non Availability of other land and minimum land certificate
3Land Schedule
4Categorywise Length width and Area
5Bar Chart with Index
6Trees details with scientific names
7Oak trees details
8Falling of minimum trees
9National park or sanctuary certificate
10NOC Gram sabha
11Work not started Certificate
12Geologist Report
13No animal effected certificate
14Fuel wood provided certificate
15Benefited villages
16NPV Evalution
17Varied NPV will be paid certificate
18Muck disposal plan
19Demarcation of forest land by RCC pillar
20Non Violation of Forest act 1980
21NOC Van Panchayat
22Cost Benefit Analysis
23Google Map Of Ca
24rate list of trees
25task force
26manak sharten
27rikt sthano par vriksharopan
28Importance of Project
29NOC Gram Sabha
30EDS Reply soughted by RO on 01/08/2016
31NOC Vanpanchayat
32Joint Inspction Report
33EDS reply
34EDS
35eds 4/8/2017
36EDS reply 3/10/2018
37eds reply
38Eds reply 16/01/2019
39Justification
40FRA
41CB Anilysis
42Revised CA Sehme
43Shukta Nirikshan
44EDS Reply 18/04/2019
45EDS Reply 22/102019