FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/RJ/WATER/154215/2022
(ii). Name of Project for which Forest Land is required :
Laying of Pipe Line Hindoli-Nainwa Water Supply Project District-Bundi From Chambal-Bhilwara WSP (PHASE-I) District -Bundi (Rajasthan)
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Laying of Pipe Line Hindoli-Nainwa Water Supply Project District-Bundi From Chambal-Bhilwara WSP (PHASE-I) District -Bundi(Rajasthan) Total Diversion Area= 4.9975 ha.
(iv). State :
Rajasthan
(v). Category of the Proposal :
Drinking Water
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
97384
(viii). Area of forest land proposed for diversion(in ha.):
4.9975
(ix). Non-forest land required for this project(in ha.):
43.8452
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
PUBLIC HEALTH ENGINEERING DEPARMENT RAJASTHAN
(ii). Address1 :
EXECUTIVE ENGINEER PROJECT DIVISION, BUNDI,RAJASTHAN
(iii). Address2 :
NIL
(iv). State :
Rajasthan
(v). District :
Bundi
(vi). Pin :
323001
(vii). Landmark :
NIL
(viii). Email address :
eeproj.bun.phed@rajasthan.gov.in
(ix). Landline Telephone No. :
0--
(x). Fax No. :
0-
(xi). Mobile No. :
9928355995
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Ram
(ii). Middle Name:
Ratan
(iii). Last Name:
Doie
(iv). Gender:
NIL
(v). Designation:
Executive Engineer
(vi). Address 1:
EXECUTIVE ENGINEER PROJECT DIVISION, BUNDI,RAJASTHAN
(vii). Address 2:
NIL
(viii). State:
Rajasthan
(ix). District:
Bundi
(x). Tehsil:
NIL
(xi). Pin:
323001
(xii). Landmark:
NIL
(xiii). Email Address:
rrdoie123@gmail.com
(xiv). Landline Telephone No.:
0-
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9928355995
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Bhilwara Territorial
0.8676
5.2482
2.
Ramgarh Vishdhari Tiger Reserve (Core), Bundi
0.5706
2.8961
3.
Bundi Territorial
3.5593
35.7009
Total
4.9975
43.8452
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Bhilwara
1.17
5.2482
1.
Bundi
3.8275
38.597
Total
4.9975
43.8452
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Aroli
0
0.315
2
Jhareli
0
0.2655
3
Kesarpura
0
0.297
4
Salavatiya
0
0.324
5
Berisal
0
0.3555
6
Kalyanpura
0
0.3075
7
Nayagaov
0
0.3735
8
Kesharganj
0
0.3117
9
Bijoliya
0
0.462
10
Undarvo ka Khera
0
0.192
11
Bhawani Singh ka Khera
0
0.3135
12
Mal Ka Khera
0
0.3294
13
Saipipla
0
0.249
14
Gampura
0
0.258
15
Ralayta
0
0.246
16
Mangatala
0
0.2775
17
Jakholi Khurd
0
0.4725
18
Mardaya
0
0.5247
19
Owan
0
0.537
20
Khejra
0.1551
0.4485
21
Basoli
0.7215
0.432
22
Baliyagurd
0
0.4515
23
Ruppan
0
0.477
24
Nehgarh
0
0.522
25
Khinya
0
0.4995
26
Mahampura
0
0.4935
27
Datunda
0.2265
0.8055
28
Badi Ka khera
0.2673
0.4125
29
Narayanpura
0.0612
0.423
30
Gudha
0.1362
0.4005
31
Madhopura
0
0.789
32
Goverdhanpura
0
0.3165
33
Bada Nayagaov
0
0.348
34
Bhojgarh
0.2425
0.223
35
kherkata
0.0226
0.38
36
Amarpura
0
0.267
37
Gujarniya
0.091
0.359
38
Barda
0
0.335
39
Kundla
0
0.317
40
Mangli kalan
0
0.344
41
Rughnathpura
0
0.322
42
Thana
0.0951
0.289
43
Salvaliya
0.0019
0.296
44
Bhisanpura
0
0.281
45
Babaji ka Barda
0
0.308
46
Hindoli
0.0229
0.382
47
Kharkheri
0
0.264
48
Bikaran
0
0.275
49
Tonkara
0.0303
0.377
50
Paich ki Bavri
0
0.283
51
Deva ka Khera
0
0.367
52
Kalmandi
0
0.308
53
Roshana
0
0.232
54
Kishanganj
0.0667
0.298
55
Pangra
0.0688
0.282
56
Maliyo ka Jhonpa
0.1066
0.362
57
Balola
0.4435
0.3505
58
Parera
0
0.3906
59
Ganeshganj
0.0876
0.375
60
Mandi
0.0088
0.368
61
Sukhpura
0.0185
0.329
62
Ramalwas
0
0.268
63
Baradiya
0
0.325
64
Danta
0
0.332
65
Thikharda
0
0.305
66
Ramchandraji ka Khera
0
0.377
67
Sayana
0
0.369
68
Borda
0
0.392
69
Naya Gonv
0
0.302
70
Kalabhata
0
0.243
71
Alod
0
0.331
72
Chetan ka Jhonpra
0
0.344
73
Ananganj
0
0.318
74
Dablana
0
0.3675
75
Bhawanipura
0
0.3415
76
Ran
0
0.3565
77
Sarsod
0
0.2835
78
Kumariya
0
0.393
79
Dhardari
0
0.3652
80
Roneeja
0.0387
0.3728
81
Bundi ka Gothra
0
0.352
82
Bal
0
0.3175
83
Ranipura
0
0.3484
84
Rishanada
0
0.3516
85
Khera
0
0.334
86
Takla
0
0.318
87
Soran
0
0.345
88
Raghunatpura
0
0.369
89
Kodi
0
0.386
90
Pandula
0
0.229
91
Sanwatgarh
0.0124
0.3525
92
Bansi
0.0802
0.3754
93
Sareda
0.087
0.3235
94
Kalanala
0.1812
0.358
95
Bharmar
0
0.3574
96
Dungri
0
0.3278
97
Anv ka Khera
0.0463
0.3442
98
Manpura
0.074
0.3505
99
Nenwa -II
0.0456
0.3845
100
Nenwa -I
0.123
0.363
101
Khanpura
0.0212
0.391
102
Diyali
0
0.3835
103
Korma
0
0.3275
104
Bachhola
0
0.2891
105
Jajawar
0.0511
0.395
106
Khori
0.0139
0.3753
107
Hanuwantpura
0
0.288
108
Suwaniya
0
0.2958
109
Suntha
0
0.3345
110
Rajlota
0
0.342
111
Fuleta
0
0.3456
112
Bari priyap
0
0.3685
113
Banjari Bavri
0
0.304
114
Bambuli
0
0.339
115
Bhajaneri
0.047
0.223
116
Dokun
0
0.278
117
Nainganv
0
0.261
118
Dei
0.1313
0.3666
119
Delpura
0
0.256
120
Dev ji ka Gudha
0
0.263
121
Kholkhera
0
0.214
122
Malera
0
0.25
123
Bansoli
0
0.209
124
Murdiya
0
0.365
125
Modsa
0
0.198
126
Dhandoon
0
0.344
127
Kesubilas
0.9378
0.1341
128
Dhanwara
0.2322
0.237
Total
4.9975
43.8452
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
100mm to 600mm Pipe line
2.2597
30.2438
2
600 up to 800 mm Pipe Line
2.7377985
13.6014
Total
4.9974985
43.8452
C.
Maps of forest land proposed to be diverted
Division 1. : Bhilwara Territorial
(i). Area of forest land proposed to be diverted(in ha.) :
0.8676
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Three
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.0894
View File
2.
0.0174
View File
3.
0.7608
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Bundi Territorial
(i). Area of forest land proposed to be diverted(in ha.) :
3.5593
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
3.5593
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 3. : Ramgarh Vishdhari Tiger Reserve (Core), Bundi
(i). Area of forest land proposed to be diverted(in ha.) :
0.5706
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Two
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.3024
View File
2.
0.2682
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
Laying Pipe Line Existing Road Row
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
7
(iii). Temporary Employment(Number of person-days):
532900
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
One
District 1. : Bundi
(a). Village:
Kota Khurd
(b). Area(in ha.):
4.9975
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
1346
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No
Documents
Remarks
1
Authorization Letter
2
ADMINISTRATIVE AND FINANCIAL SANCTION
3
TECHNICAL SANCTION
4
Government of India Ministry of Jal Shakti Letter
5
Project Report
6
Jamabandi Kesuvilas Bhilwara Division
7
Jamabandi part-1
8
Jamabandi part-2
9
Jamabandi part-3
10
EDS Reply to DCF Bhilwara-14-02-2023
11
AREA CALCULATION SHEET - RAMGARH VISHDHARI TIGER RESERVE (CORE) BUNDI
12
AREA CALCULATION SHEET (BHILWARA TERRITORIAL DIVISION)
13
AREA CALCULATION SHEET (BUNDI TERRITORIAL DIVISION)
14
CERTIFICATE FOR MINIMUM USE OF FOREST LAND
15
JUSTIFICATION FOR LOCATING THE PROJECT IN FOREST AREA
16
UNDERTAKING FOR ALL TYPE FOREST INCLUDED
17
UNDERTAKING FOR CA LAND (Non-Forest Land)
18
UNDERTAKING FOR CONSERVATION OF FLORA-FAUNA DURING
19
UNDERTAKING FOR MUCK DISPOSAL DURING LAYING
20
UNDERTAKING FOR NO CHANGES IN STATUTORY POSITION OF DIVERTED FOREST LAND
21
UNDERTAKING FOR NO TREE CUTTING DURING LAYING PIPE LINE
22
UNDERTAKING FOR PAYMENT OF ANY OTHER COST AND CONDITION
23
UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
24
UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
25
UNDERTAKING FOR PIPE LINE LAYING WORK WILL BE EXECUTE
26
UNDERTAKING FOR USE OF ANY MATERIAL FROM SURROUNDED
27
UNDERTAKING FOR USE OF FOREST LAND
28
UNDERTAKING FOR WASTE MANAGEMENT DURING LAYING PIPE LINE ACTIVITY
29
UNDERTAKING OF FRA CERTIFICATE
30
UNDERTAKING OF Muck Restoration Plan
31
Details of Permanent Employment to be Generated
32
SEGMENT WISE AREA CALCULATION SHEET
33
MAP SHOWING FOR GEO-REFERENCED SURVEY OF INDIA TOPOSHEET WITH PROSPOED WATER PIPE LINE ROUTE ALIGNMENT SOI TOPOSHEET SCALE 1 : 50000 (Bhilwara Division) Part-1
34
MAP SHOWING FOR GEO-REFERENCED SURVEY OF INDIA TOPOSHEET WITH PROSPOED WATER PIPE LINE ROUTE ALIGNMENT SOI TOPOSHEET SCALE 1 : 50000 (Bundi Territorial Division) Part-2
35
MAP SHOWING FOR GEO-REFERENCED SURVEY OF INDIA TOPOSHEET WITH PROSPOED WATER PIPE LINE ROUTE ALIGNMENT SOI TOPOSHEET SCALE 1 : 50000 (RVTR and Bundi Territorial Division) Part-3
36
GEO-REFERENCED DGPS MAP SHOWING FOR REQUIRED LAND COORDINATE WITH PROSPOED WATER PIPE LINE ROUTE ALIGNMENT SOI TOPOSHEET DGPS MAP (Bhilwara -Division and RVTR ) Part-1
37
GEO-REFERENCED DGPS MAP SHOWING FOR REQUIRED LAND COORDINATE WITH PROSPOED WATER PIPE LINE ROUTE ALIGNMENT SOI TOPOSHEET DGPS MAP Bundi -Division and RVTR ) Part-2
38
GEO-REFERENCED DGPS MAP SHOWING FOR REQUIRED LAND COORDINATE WITH PROSPOED WATER PIPE LINE ROUTE ALIGNMENT SOI TOPOSHEET DGPS MAP Bundi -Division and RVTR ) Part-3
39
Combined Digital Map
40
Combined Toposheet Map
41
Village Wise Area Calculation Sheet
42
Khasra Wise Area Calculation Sheet (Bhilwara Division)
43
Khasra Wise Area Calculation Sheet (Bundi Territorial Division)
44
Khasra Wise Area Calculation Sheet (RVTR Bundi Division)
45
Khasra Map Super Imposed (Bhilwara Divsion) Scale 1-4000
46
Khasra Map Super Imposed (RVTR Core Bundi Division) Scale 1-4000
47
Khasra Map Super Imposed (Bundi Division) Part- I Scale 1-4000
48
Khasra Map Super Imposed (Bundi Division) Part- II Scale 1-4000
49
EDS Reply-23-02-2023
50
EDS Reply- TO DCF BUNDI -29-03-2023
51
EDS Reply-to RVTR DCF Bundi 29-03-2023
52
Allotment Letter NFL by District Collector Bundi
53
JAMABANDI FOR CA NFL
54
KHASRA MAP FOR CA NFL LAND SCALE 1: 4000
55
GEO-REFERENCED DGPS MAP FOR CA LAND
56
GEO-REFERENCED TOPOSHEET WITH PROPOSED FOR Compensatory Afforestation SCALE 1 : 50000
57
District Collector Bundi TO PHED
58
EDS Reply-15-05-2023
59
Cross Section pipeline
60
Area Calculation Sheet WLS and Territorial Forest
61
Detail of Area Calculation sheet