FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/RJ/TRANS/44981/2020   (ii). Name of Project for which Forest Land is required : Construction of 765 KV DC Fatehgarh II to Bhadla II Transmission Line, District - Jodhpur, Raj   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 765 KV DC Fatehgarh II to Bhadla II Transmission Line, District - Jodhpur, Rajasthan (total Length 183.872 km)   (iv). State : Rajasthan   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 57790   (viii). Area of forest land proposed for diversion(in ha.): 2.8874   (ix). Non-forest land required for this project(in ha.): 1229.055   (x). Total period for which the forest land is proposed to be diverted(in years): 50
A-2. Details of User Agency
  (i). Name : POWERGRID CORPORATION OF INDIA LIMITED   (ii). Address1 : Plot No.115 Nandpuri Colony   (iii). Address2 : Nagaur Road Phalodi Jodhpur   (iv). State : Rajasthan   (v). District : Jodhpur   (vi). Pin : 342301   (vii). Landmark : NIL   (viii). Email address : pankajs@powergridindia.com   (ix). Landline Telephone No. : 151-2233135   (x). Fax No. : 151-2233135   (xi). Mobile No. : 9403770239   (xii). Website (if any) : www.powergridindia.com   (xiii). Legal status of User Agency : Central PSU
A-3. Details of Person Making Application
  (i). First Name: Pankaj   (ii). Middle Name: NIL   (iii). Last Name: Suthar   (iv). Gender: Male   (v). Designation: Manager   (vi). Address 1: Plot No.115 Nandpuri Colony   (vii). Address 2: Nagaur Road Phalodi Jodhpur   (viii). State: Rajasthan   (ix). District: Jodhpur   (x). Tehsil: Phalodi   (xi). Pin: 342301   (xii). Landmark: NIL   (xiii). Email Address: pankajs@powergridindia.com   (xiv). Landline Telephone No.: 151-2233135   (xv). Fax No.: 01512233135   (xvi). Mobile No.: 9403770239   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1ApprovedFP/RJ/TRANS/35279/20188B/RAJ/04/14/2019/FC10.29910.29904 Jul 201911 Sep 2019
Total 10.299 10.299
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Jodhpur Territorial2.88741229.055
Total2.88741229.055
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Jaisalmer0549.2191
1.Jodhpur2.8874679.8359
Total2.88741229.055
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Sanwata056.0589
2Achla028.408
3Lakhasar049.2316
4Khuhra039.2151
5Sadrasar019.2357
6Sankra040.334
7Khetasar049.245
8Dalpatpura030.3778
9Jaswantpura016.8371
10Jalmlan057.0505
11Teliwara028.3611
12Chainpura013.4335
13Madwa020.5154
14Jhalariya065.8677
15Dhoorsar035.0477
16Lalpura031.9523
17Khera Bagoriya024.4349
18Dediya0.236150.6118
19Dhadhoo056.5011
20Matol chak035.6775
21Khara022.8738
22Hopardi020.7499
23Bithri0.234855.945
24Kundal017.286
25Sadawata09.782
26Bhojka05.0116
27Gopa010.4654
28Baori046.9201
29Khirwa1.930775.1472
30Bari Dhani039.329
31Ghator052.3471
32Gadna0.237643.0475
33Bari Sird0.248265.8677
34Kansingh Ki Sird015.886
Total 2.8874 1229.055
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Stringing Area0.6464272.9854
2Tower Foundation Area09.72
3Remaining ROW2.241946.3496
Total 2.8874 1229.055
C. Maps of forest land proposed to be diverted
Division 1. : Jodhpur Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 2.8874   (ii). Nature of the Project: Linear   (b). No. of Segments : Five
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.2361    View File
2.0.2348    View File
3.1.9307    View File
4.0.2376    View File
5.0.2482    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 12   (iii). Temporary Employment(Number of person-days): 550
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
Additional information Details
Documents
S.No Documents
Remarks
1CERTIFICATE FOR MINIMUM USE OF FOREST LAND.
2Details of Permanent Employment to be generated.
3COMPLETE ALIGNMENT TOWER COORDINATES.
4Component Wise Area Calculation Sheet.
5Geo Referenced Zoom view Digital map Segment 1.
6Geo Referenced Zoom view Digital map Segment 3.
7Geo Referenced Zoom view Digital map Segment 4.
8Geo Referenced Zoom view Digital map Segment 5.
9COMPARATIVE STATEMENT OF ALTERNATIVE ROUTE 765 kv.
10Section 68 approval Fatehgarh II.
11Project Report.
12EDS Reply Letter dated 15_05_2020 765 kv.
13Other Land Details.
14TWO TIME DEGRADED FOREST LAND UNDERTAKING.
15UNDERTAKING FOR CONSERVATION OF FLORA FAUNA DURING TRANSMISSION LINE.
16UNDERTAKING FOR FRA CERTIFICATE.
17Undertaking for Muck Disposal Plan.
18UNDERTAKING FOR NO CHANGES IN STATUTORY POSITION OF DIVERTED FOREST LAND.
19UNDERTAKING FOR PAYMENT OF ANY OTHER COST AND CONDITION.
20UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION.
21Undertaking for Payment of Cost of Medicinal Pland under Transmission line.
22UNDERTAKING FOR SUBMISSION OF MISSING OR REQUIRED ADDITIONAL DOCUMENTS.
23Undertaking for Use of Any Material From Forest Land.
24UNDERTAKING FOR USE OF FOREST LAND.
25Undertaking to Pay the Cost of Plantation.
26Khasra Map and Jamabandi.
27UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF Forest Land.
28Village Wise Area Calculation Sheet.
29Segment Wise Area Calculation Sheet.
30Geo Referenced Zoom view Digital map Segment 2.
31Geo Referenced Toposheet map Total Alignment 50000 scale all.
32Bar chart Status.
33UNDERTAKING FOR NO OTHER FEASIBLE ALTERNATIVE.
34Alternative Route Map.
35NHAI NoC Undertaking.
36Canal NoC.
37Reply Letter of 25 January 2021 EDS.