FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/RJ/IRRIG/27263/2017
(ii). Name of Project for which Forest Land is required :
SUBMERGANCE OF HATHIADEH MEDIUM IRRIGATION PROJECT
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Submergance of hathiadeh midium irrrigation project dist.- baran area - 286.47 hact.
(iv). State :
Rajasthan
(v). Category of the Proposal :
Irrigation
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
23253
(viii). Area of forest land proposed for diversion(in ha.):
286.47
(ix). Non-forest land required for this project(in ha.):
580.17
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
WATER RESOURCES DEPARTMENT
(ii). Address1 :
Near Railway Over Bridge Kota Road Baran
(iii). Address2 :
NIL
(iv). State :
Rajasthan
(v). District :
Baran
(vi). Pin :
325205
(vii). Landmark :
NIL
(viii). Email address :
eewrdiv3baran@gmail.com
(ix). Landline Telephone No. :
7453-237209
(x). Fax No. :
7453-
(xi). Mobile No. :
9460745028
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Manoj
(ii). Middle Name:
Kumar
(iii). Last Name:
Goyal
(iv). Gender:
Male
(v). Designation:
EXECUTIVE ENGINEER
(vi). Address 1:
WATER RESOURCES DIVISION III, BARAN
(vii). Address 2:
NIL
(viii). State:
Rajasthan
(ix). District:
Baran
(x). Tehsil:
Baran
(xi). Pin:
325205
(xii). Landmark:
NIL
(xiii). Email Address:
eewrdiv3baran@gmail.com
(xiv). Landline Telephone No.:
7453-237209
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9460745028
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Baran Territorial
286.47
580.17
Total
286.47
580.17
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Baran
286.47
580.17
Total
286.47
580.17
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Baman deh
8.01
0
2
Gordhanpura
61.88
0
3
Karwari khurd
64.93
240.5
4
Karwari kalan
151.65
339.67
Total
286.47
580.17
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
dam line
9.521
23.224
2
submergance
276.949
556.946
Total
286.47
580.17
C.
Maps of forest land proposed to be diverted
Division 1. : Baran Territorial
(i). Area of forest land proposed to be diverted(in ha.) :
286.47
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
Two
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
9.521
View File
2.
276.949
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
30
(iii). Temporary Employment(Number of person-days):
2500000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
Yes
(a). Total Number of families :
388
(b). Number of Scheduled Caste families :
5
(c). Number of Schedule Tribes families :
222
(d). Number of other families :
161
(ii). Copy of Rehabilitation and Resettlement Plan:
(a). Copy of approval to Ministry of Tribal Affairs,Government of India to Rehabilitation and Resettlement:
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
Three
District 1. : Baran
(a). Village:
TIKOD PATUNDA
(b). Area(in ha.):
242.5
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
56,57,58,59,60,61,63,547/64,546/80,81,82,1337,1360,1397,2377/1398,2463/2,2465/8,9,2451/10,204,317,2453/1025,2455/1026,2457/1109,2459/1113,2461/1114,1115,1116,1200,1201,1202,2376/1203
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
District 2. : Baran
(a). Village:
NACHANA KHERA
(b). Area(in ha.):
26.336
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
201,196,197,198,209,210,211
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
District 3. : Baran
(a). Village:
AKLERA SAGAR
(b). Area(in ha.):
17.66
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
257
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
0
(ii). Total command area of the Project(in ha.):
6885
(a). Copy of the approval of competent authority to the Catchment Area Treatment Plan (CAT Plan):
(b). Copy of the approved CAT plan:
Additional information Details
Documents
S.No
Documents
Remarks
1
salient feature
2
performa report
3
khasara detail
4
repply of eds
5
KHASARA DETAIL
6
FRA
7
FOREST KHASARA DETAIL
8
CERTIFICATE MINIMUM USE OF FOREST
9
CERTIFICATE PAYMENT OF COST OF CA
10
CERTIFICATE OF NPV
11
JUSTIFICATION OF DAM
12
CERTIFICATE OF CONSERVATION OF FALORA FUNA
13
CERTIFICATE OF PAYMENT OF ANY OTHER COST
14
CERTIFICATE OF USE OF ANY MATERIAL
15
CERTIFICATE OF MUK DISPOSAL
16
REPLY OF EDS 2 4 18
17
A & F of project
18
jamabandi record
19
CERTIFICATE FOR NO FOREST LAND WILL COME IN CANAL ALIGNMENT
20
INDEX PLAN FOR CANAL ALIGNMENT
21
MP Govt. NOC
22
Chapter 1 General introduction hathiadeh
23
reply of eds
24
rr undertaking
25
reply of eds 22 5 19
26
justification of capacity
27
bar chart
28
r and r plan
29
dhara 11 report
30
contour capacity map
31
r and r dhara 4 7
32
khathoni patunda
33
reply 19 9 19
34
reply of eds 24 2 20
35
reply 25 5 20
36
reply 24 2 2020
37
reply of eds 26 3 21
38
r & r plan
39
reply 11 6 21
40
moka report for ca
41
reply 2 12 2021
42
REPLY OF 28 1 22
43
undertaking of ca
44
reply of eds 30 4 22
45
DCF REPLY FOR INCLOSEMENT
46
REPLY OF EDS 4 8 22
47
EDS Reply-20-09-2022
48
REPLY 24 12 22
49
REPLY 14 1 23
50
reply of eds 20 2 23
51
undertaking for revised cat plan
52
APPROVED CAT PLAN
53
APPROVED RR PLAN
54
PATUNDA AND TIKOD PATWARI REPORT FOR INCLOSEMENT
55
UNDERTAKING FOR REVISED CAT PLAN
56
CA LAND ALLOTMENT LATTER
57
Moka report on dated 15 5 24
58
patunda jamabandhi CA
59
Tikod jamabandhi CA
60
undertaking muk disposal by SE WRD
61
BC RATIO
62
REPLY OF EDS 19 6 24