FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/KL/HYD/37079/2018
(ii). Name of Project for which Forest Land is required :
Valanthode Small Hydro Electric Project
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
A 7.50MW/ 15.291 MU SHEP constructing a weir of 101m in Kurumanpuzha, in Chaliyar basin at Thottappally in Akampadam village of Chaliyar Panchayath of Nilambur Taluk in Malappuram District and 591m rectangular channel, 25m dia forebay tank, 396m penstock of 1.8m dia and a Power house.
(iv). State :
Kerala
(v). Category of the Proposal :
Hydel
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
6911
(viii). Area of forest land proposed for diversion(in ha.):
0.9354
(ix). Non-forest land required for this project(in ha.):
3.747
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
KERALA STATE ELECTRICITY BOARD LTD
(ii). Address1 :
Office of the Project Manager, Valanthode Small HEP, Chandakkunnu P.O, Nilambur
(iii). Address2 :
NIL
(iv). State :
Kerala
(v). District :
Malappuram
(vi). Pin :
679342
(vii). Landmark :
NIL
(viii). Email address :
pmashep@gmail.com
(ix). Landline Telephone No. :
4931-220133
(x). Fax No. :
4931-
(xi). Mobile No. :
9446008410
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State PSU
A-3.
Details of Person Making Application
(i). First Name:
Ismail
(ii). Middle Name:
NIL
(iii). Last Name:
Pattupara
(iv). Gender:
Male
(v). Designation:
ProjectManager
(vi). Address 1:
Office of the Project Manager, Valanthode Small HEP, Chandakkunnu P.O, Nilambur
(vii). Address 2:
NIL
(viii). State:
Kerala
(ix). District:
Malappuram
(x). Tehsil:
Nilambur
(xi). Pin:
679342
(xii). Landmark:
NIL
(xiii). Email Address:
pmashep@gmail.com
(xiv). Landline Telephone No.:
4931-220133
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9446008410
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
NIlambur North
0.9354
3.747
Total
0.9354
3.747
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Malappuram
0.9354
3.747
Total
0.9354
3.747
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Akampadam
0.9354
3.747
Total
0.9354
3.747
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Weir
0.6485
0.0858
2
Canal
0.2727
1.3597
3
Forebay
0
0.2361
4
Penstock
0
0.4938
5
Power House
0.0142
0.7116
6
Access Roads
0
0.86
Total
0.9354
3.747
C.
Maps of forest land proposed to be diverted
Division 1. : NIlambur North
(i). Area of forest land proposed to be diverted(in ha.) :
0.9354
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
Two
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
0.9212
View File
2.
0.0142
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
10
(iii). Temporary Employment(Number of person-days):
4000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
7.5
(ii). Total command area of the Project(in ha.):
0
Additional information Details
Documents
S.No
Documents
Remarks
1
2
Undertaking regarding willingness to pay additional NPV if any as per revision by Hon Supreme Court
3
Reply letter to the EDS
4
Study Report to the EDS
5
Study Report to the EDS
Print