FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/HR/Canal/152229/2022
(ii). Name of Project for which Forest Land is required :
Diversion of 33.71 Ha of Forest Land for construction of channel for supply 180 Cs water to Nuclear Power Plant at Gorakhpur, Tehsil & District Fatehabad through old abandoned Sirsa Branch from RD 388
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Diversion of 33.71 Ha of Forest Land for construction of channel for supply 180 Cs water to Nuclear Power Plant at Gorakhpur, Tehsil & District Fatehabad through old abandoned Sirsa Branch from RD 388500 to 424780 under Forest Division District Hisar, District Jind and District Fatehabad
(iv). State :
Haryana
(v). Category of the Proposal :
Canal
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
44627
(viii). Area of forest land proposed for diversion(in ha.):
33.71
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
EXECUTIVE ENGINEER ADAMPUR WATER SERVICES DIVISION HISAR
(ii). Address1 :
Executive Engineer Adampur water services Division Hisar canal colony Hisar
(iii). Address2 :
NIL
(iv). State :
Haryana
(v). District :
Hisar
(vi). Pin :
125001
(vii). Landmark :
Near laxmi bai chouk
(viii). Email address :
xenawsdn@gmail.com
(ix). Landline Telephone No. :
1662-230030
(x). Fax No. :
1662-0
(xi). Mobile No. :
9416330246
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Dalbir
(ii). Middle Name:
NIL
(iii). Last Name:
Singh
(iv). Gender:
Male
(v). Designation:
Executive Engineer
(vi). Address 1:
Executive Engineer, Adampur Water Services Division, Hisar
(vii). Address 2:
NIL
(viii). State:
Haryana
(ix). District:
Hisar
(x). Tehsil:
Hisar
(xi). Pin:
125001
(xii). Landmark:
Near Laxmi Bai Chowk
(xiii). Email Address:
xenawsdn@gmail.com
(xiv). Landline Telephone No.:
1662-230030
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9416414544
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Jind
5.69
0
2.
Hisar
17.79
0
3.
Fatehabad
10.23
0
Total
33.71
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Jind
5.69
0
1.
Hisar
17.79
0
3.
Fatehabad
10.23
0
Total
33.71
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Danoda Khurd
5.69
0
2
Bithmara
12.79
0
3
Kundapura
5.23
0
4
Hansawala
10
0
Total
33.71
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Jind
5.69
0
2
Hisar
17.79
0
3
Fatehabad
10.23
0
Total
33.71
0
C.
Maps of forest land proposed to be diverted
Division 1. : Fatehabad
(i). Area of forest land proposed to be diverted(in ha.) :
10.23
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
10.23
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Hisar
(i). Area of forest land proposed to be diverted(in ha.) :
17.79
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
17.79
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 3. : Jind
(i). Area of forest land proposed to be diverted(in ha.) :
5.69
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
5.69
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
30
(iii). Temporary Employment(Number of person-days):
120
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
Yes
(a). Status of the Environmental Clearance to the Project:
EC application yet to be submitted
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
Linear or 'strip' plantation declared as protected forest along with road/rail/canal sides for widening or expansion of road/rail/canal
Additional information Details
Documents
S.No
Documents
Remarks
1
Justification
2
Annexure-A
3
Admin Approval (Annexure-B)
4
NOC B&R
5
Govt. approval
6
Layout Plan Fatehabad
7
Layout Plan Hisar
8
Layout Plan Jind
9
MoU Agreement
10
DGPS Fatehabad
11
DGPS Hisar
12
DGPS Jind
13
Checklist Hisar
14
Checklist Jind
15
Checklist Fatehabad
16
Toposheet
17
reply of ACS, Forest Haryana letter dt. 21.04.2022
18
Land Detail Jind
19
Land Detail Hisar
20
Land Detail Fatehabad
21
Letter reply of observations dated 25.07.2022 as pointed out by the IRO (MoEFCC)
22
FRA undertaking as desired by the IRO (MoEFCC) letter dated 25.07.2022