FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UP/TRANS/22423/2016
(ii). Name of Project for which Forest Land is required :
400 kV D/C Tanda - Gonda Transmission Line
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
400 kV D/C Gonda to Tanda Transmission Line required to evacuate power from Tanda NTPC TPS to UPPTCL Sub Station Basti
(iv). State :
Uttar Pradesh
(v). Category of the Proposal :
Transmission Line
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
2184.75
(viii). Area of forest land proposed for diversion(in ha.):
1.5872
(ix). Non-forest land required for this project(in ha.):
430
(x). Total period for which the forest land is proposed to be diverted(in years):
40
A-2.
Details of User Agency
(i). Name :
SOUTH EAST UTTAR PRADESH POWER TRANSMISSION COMPANY LIMITED
(ii). Address1 :
Shalimar Titanium, 601-602, 6th Floor, Plot No. TC/G-1/1, Vibhuti Khand, Gomati Nagar
(iii). Address2 :
Lucknow, Uttar Pradesh
(iv). State :
Uttar Pradesh
(v). District :
Lucknow
(vi). Pin :
226010
(vii). Landmark :
Near Indira Patisthan
(viii). Email address :
info@seupptcl.com
(ix). Landline Telephone No. :
522-4923208
(x). Fax No. :
522-0
(xi). Mobile No. :
8756700132
(xii). Website (if any) :
www.seupptcl.com
(xiii). Legal status of User Agency :
State PSU
A-3.
Details of Person Making Application
(i). First Name:
SANJAI
(ii). Middle Name:
KUMAR
(iii). Last Name:
SINGH
(iv). Gender:
Male
(v). Designation:
GENERAL MANAGER (TRANSMISSION
(vi). Address 1:
Levana Cyber Heights Building, 1st Floor, Office Space-116, Vibhuti Khand, Gomati Nagar
(vii). Address 2:
Lucknow, Uttar Pradesh
(viii). State:
Uttar Pradesh
(ix). District:
Lucknow
(x). Tehsil:
NIL
(xi). Pin:
226010
(xii). Landmark:
Near Indira Patisthan
(xiii). Email Address:
info@seupptcl.com
(xiv). Landline Telephone No.:
522-4304998
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9454647975
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
1
Inprinciple
FP/UP/TRANS/4709/2013
8B/U.P./04/27/20014/F.C./199
0.279
0.279
13 Jun 2014
2
Inprinciple
FP/UP/TRANS/4655/2013
8B/U.P./04/27/20014/F.C./198
2.796
2.796
13 Jun 2014
3
Inprinciple
FP/UP/TRANS/15893/2014
8B/U.P./04/36/2016/F.C./336
1.104
1.104
18 Oct 2016
4
Inprinciple
FP/UP/TRANS/15520/2015
8B/U.P./04/31/2016/FC/159
22.6006
22.6006
29 Jun 2016
5
Inprinciple
FP/U.P./TRANS/13285/2015
8B/U.P./04/99/2017/FC/570
3.177404
3.177404
21 Mar 2017
6
Approved
FP/U.P./TRANS/4709/2013
8B/U.P./04/27/2014/FC/199
0.279
0.279
13 Jun 2014
18 Sep 2015
7
Approved
FP/U.P./TRANS/4655/2013
8B/U.P./04/27/2014/FC/198
2.796
2.796
13 Jun 2014
26 Aug 2015
8
Approved
FP/UP/Trans/15893/2014
8B/U.P./04/36/2016/FC/510
1.104
1.104
18 Oct 2016
02 Nov 2021
9
Inprinciple
FP/UP/Trans/ 15520/2015
8B/U.P./04/31/2016/FC/159
22.0305
22.0305
29 Jun 2016
Total
56.166504
56.166504
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Forest Division Gonda
1.1217
291
2.
Social Forestry Division Basti
0.4655
139
Total
1.5872
430
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Gonda
1.1217
291
1.
Basti
0.4655
139
Total
1.5872
430
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Tikri
0.0421
1.0895
2
Sirsa
0.1542
1.5386
3
Pandit Purwa
0.1542
0.9176
4
Laua Tapra
0.1542
2.3988
5
Laua Tapra-1
0.1542
2.2976
6
Laua Tapra-2
0.1542
0.5358
7
Laua Birpur
0.15425
8.5723
8
Rani Chhatar
0.14025
1.663
9
Bithelapur
0.09255
7.9161
10
Chapilon
0.09255
1.4163
11
Tikrii
0.15425
2.2884
12
Nathpur
0.14025
0.8626
Total
1.5872
31.4966
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
NER Rail line (Nawabganj-Mankapur)AP51-AP52
0.0420624
1.0895376
2
Katra-Nawabganj Road-AP44A-AP44B
0.1542288
2.2883712
3
Nawabganj-Gonda Road-AP53A-AP53A/1
0.1542288
0.85719712
4
Nwabganj-Mankapur Road-AP52-AP52A
0.1542288
0.15385712
5
Nawbganj-Tarabganj Road-AP57B-AP57C
0.1542288
0.09175712
6
Pakri-Tarabganj Road-AP64-AP64/1
0.1542288
0.23987712
7
Ragadganj-Tarabganj Road-AP70-AP71
0.1542288
0.22975712
8
Gonda-Belsar Road-AP78-Gantry
0.1542288
0.05357712
9
Babhnan-Harraiya Road-AP9-AP10
0.140208
0.0862592
10
Saryu canal - AP12-AP13
0.09253728
0.7916048
11
Hiyarupur canal-AP27/4-AP28
0.09253728
0.141626272
12
Babhnan-Vikramjot Road - AP30/1-31
0.140208
0.1662992
Total
1.58715456
6.189720992
C.
Maps of forest land proposed to be diverted
Division 1. : Social Forestry Division Basti
(i). Area of forest land proposed to be diverted(in ha.) :
0.4655
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Four
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.1402
View File
2.
0.0925
View File
3.
0.0925
View File
4.
0.1402
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Forest Division Gonda
(i). Area of forest land proposed to be diverted(in ha.) :
1.1217
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Eight
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.0421
View File
2.
0.1542
View File
3.
0.1542
View File
4.
0.1542
View File
5.
0.1542
View File
6.
0.1542
View File
7.
0.1542
View File
8.
0.1542
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
9
(iii). Temporary Employment(Number of person-days):
65000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
For laying of transmission lines
Additional information Details
Documents
S.No
Documents
Remarks
1
Forest Gazatee Notification Gond
2
Forest Gazatee Notification Basti
3
Area Calculation Sheet
4
Project Gazatee Notification
5
Transmission License
6
Project Approval Under Sec 68
7
Area Change request
8
Durlabh Vanaspati aur Prani certificate
9
ETT Certificate
10
Forest Area Details
11
FRA Undertaking - Basti
12
FRA Undertaking - Gonda
13
Justification of Route
14
Kshatipoorak Vraksharopan Certificate
15
Lease Rent Certificate
16
Manak Sharten
17
Muck Disposal Plan
18
Neuntam Van Bhoomi Certificate
19
No centuary in 10 km radius
20
No sensitive forest area certificate
21
No work start certificate
22
Prabhavit vanbhoomi ke swamitva
23
Three Alternate Route
24
Van sanrakshan certificate
25
Vanswaroop kshetron sambandhi
26
Vanya jeev certificate
27
Joint Inspection Report -Basti
28
Joint Inspection Report - Gonda
29
Reply Letter - 130125
Print