FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/UP/TRANS/146255/2021   (ii). Name of Project for which Forest Land is required : Construction of 765 KV D/C Sikar-II -Aligarh Transmission line(Package-TW03) Under Transmission Scheme for evacuation of power from Solar Energy Zones in Rajasthan (8.1GW)under phase=II part-D, through tariff based competitive bidding (TBCB) Route in District Mathura & Aligarh (Utter Pradesh)   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : “Construction of 765 KV D/C Sikar-II -Aligarh Transmission line(Package-TW03) Under Transmission Scheme for evacuation of power from Solar Energy Zones in Rajasthan (8.1GW)under phase=II part-D, through tariff based competitive bidding (TBCB) Route in District Mathura & Aligarh (Utter Pradesh)” To   (iv). State : Uttar Pradesh   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 100600   (viii). Area of forest land proposed for diversion(in ha.): 0.5293   (ix). Non-forest land required for this project(in ha.): 287.4903   (x). Total period for which the forest land is proposed to be diverted(in years): 50
A-2. Details of User Agency
  (i). Name : SIKAR -II ALIGARH TRANSMISSION LIMITED (A 100% WHOLLY OWNED SUBSIDIARY OF POWERGRID CORPORATION OF INDIA LIMITED)   (ii). Address1 : PLOT NO-339 , SHANTI KUNJ SCHEME, ALWAR (RAJASTHAN)   (iii). Address2 : NIL   (iv). State : Rajasthan   (v). District : Alwar   (vi). Pin : 301001   (vii). Landmark : NIL   (viii). Email address : kanchan@powergrid.in   (ix). Landline Telephone No. : 0-   (x). Fax No. : 0-   (xi). Mobile No. : 9560690612   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Central PSU
A-3. Details of Person Making Application
  (i). First Name: Kanchan   (ii). Middle Name: Kumar   (iii). Last Name: Choudhary   (iv). Gender: Male   (v). Designation: Sr General Manager   (vi). Address 1: PLOT NO 339 , SHANTI KUNJ SCHEME , ALWAR-RAJASTHAN   (vii). Address 2: NIL   (viii). State: Rajasthan   (ix). District: Alwar   (x). Tehsil: Alwar   (xi). Pin: 301001   (xii). Landmark: NIL   (xiii). Email Address: kanchan@powergrid.in   (xiv). Landline Telephone No.: 0-   (xv). Fax No.: NIL   (xvi). Mobile No.: 9560690612   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Social Forestry Division Mathura0.5293230.1852
2.Social Forestry Division Aligarh057.3051
Total0.5293287.4903
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Mathura0.5293230.1852
1.Aligarh057.3051
Total0.5293287.4903
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Lalpur016.8572
2Umrala012.194
3Karman011.792
4Hathana014.204
5Sheikhsai0.529315.7584
6Barka013.467
7Aliwara012.864
8Nangla011.859
9Sirauli011.323
10Shahpur012.395
11Kushalgarhi011.256
12Raipur011.3967
13Tilakgarhi05.025
14Bhagwangarhi06.834
15Khajpur06.298
16Murwaka06.5325
17Mangarhi06.164
18Abhaipura05.2662
19Awakhera06.1975
20Chandpur Khurri06.566
21Bhartiyanka05.3399
22Kaneka06.633
23Mithauli07.5978
24Sakatpur06.365
25Pankhodana010.0634
26Rahugarhi06.4186
27Baghragarhi06.0367
28Salpur04.958
29Hansagarhi06.432
30Nagariya Jharana05.896
31Mathnagarhi04.757
32Kilpur06.499
33Mohsinpur06.2444
Total 0.5293 287.4903
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Construction of 765 KV D/C Sikar-II -Aligarh Trans0.5293230.1852
2Construction of 765 KV D/C Sikar-II -Aligarh Trans057.3051
Total 0.5293 287.4903
C. Maps of forest land proposed to be diverted
Division 1. : Social Forestry Division Mathura
  (i). Area of forest land proposed to be diverted(in ha.) : 0.5293   (ii). Nature of the Project: Linear   (b). No. of Segments : Two
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.26465    View File
2.0.26465    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Social Forestry Division Aligarh
  (i). Area of forest land proposed to be diverted(in ha.) : 0   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 15   (iii). Temporary Employment(Number of person-days): 420864
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
Additional information Details
Documents
S.No Documents
Remarks
1AUTHORIZATION LETTER
2Section 68 Approval
3Aligarh DFO Noc
4Geo-Referenced Digital Map With Proposed Construction of 765 KV D/C Sikar-II -Aligarh Total Route Alignment
5EDS Reply 19-10-2021
6DFO Mathura Letter with Forest Notification
7CERTIFICATE FOR MINIMUM USE OF FOREST LAND
8COMPARATIVE STATEMENT OF ALTERNATIVE ROUTE
9COMPLETE ALIGNMENT TOWER COORDINATES
10Details of Permanent Employment to be Generated
11JUSTIFICATION FOR LOCATING THE PROJECT IN FOREST AREA
12Muck Disposal and Management Plan
13OWNER DEPARTMENTS UNDERTAKING FOR NO OBJECTION CERTIFICATE
14Segment Wise Area Calculation Sheet
15Standard Conditions -1980-82 Forest Section-3
16STATEMENT SHOWING DETAILS OF FORESTAREA ( DIVISION -Aligarh )
17STATEMENT SHOWING DETAILS OF FORESTAREA -( DIVISION -MATHURA)
18Undertaking CCF and Nodal UP Letter No 343_11C dated 14_08_2020
19UNDERTAKING FOR CONSERVATION OF FLORA-FAUNA DURING CONSTRUCTION OF TRANSMISSION LINE
20Undertaking For Entire Tree Transplant (ETP)
21Undertaking for FRA Certificate
22UNDERTAKING FOR MEDICIANAL PLANTS
23UNDERTAKING FOR MUCK DISPOSAL
24Undertaking for No any other Alternative
25UNDERTAKING FOR NO CHANGE S IN STATUTORY POSITION OF DIVERTED FOREST LAND
26Undertaking for No wildlife Sanctuary
27UNDERTAKING FOR PAYMENT OF ADDITIONAL-NPV
28UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
29UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
30Undertaking for Sr No 7 Related Certificate
31Undertaking for Task force
32UNDERTAKING FOR TWO TIME DEGRADED FOREST LAND
33UNDERTAKING FOR USE OF ANY MATERIAL
34UNDERTAKING FOR USE OF FOREST LAND
35Undertaking for Van Savroop Ref Court Cash Letter 11-11-2011
36Undertaking for Work Not Started Without Permission
37UNDERTAKING REGARDING NON VIOLATION OF FOREST (CONSERVATION) ACT 1980
38Village Wise Area calculation Sheet Forest and Non-Forest Land
39Alternative Route- Toposheet Map
40Alternative Route Digital Map
41EDS -II Reply -13-11-2021
42Geo-Referenced Segment DGPS Map Segment-1 -2 ( Forest Division -Mathura)
43Total Route DIGITAL Map Alignment
44EDS-III reply -01-12-2021
45Geo-Referenced Survey of India Toposheet Full toposheet no 54 E-5 and 54 E-9 Scale 1 : 50000 (Forest Division-Mathura)
46Geo-Referenced Survey of India Toposheet Full toposheet no 54 E-9 Scale 1 : 50000 (Forest Division-Aligarh)
47EDS REPLY-10-12-2021
48EDS Reply-28-02-2022