FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UP/ROAD/43253/2019
(ii). Name of Project for which Forest Land is required :
Forest Land Diversion proposal for "Improvement and Up-gradation to 4-lane configuration of Meerut-Nazibabad section of NH-119 between Km 39+165 to Km 78+635 in the state of Uttar Pradesh".
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
This proposal is of up-gradation of existing Highway no 119 to 4 lane with paved shoulder. This proposal also require realignment and bypasses.
(iv). State :
Uttar Pradesh
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
72620
(viii). Area of forest land proposed for diversion(in ha.):
38.8514
(ix). Non-forest land required for this project(in ha.):
137.8947
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
NHAI PIU MEERUT
(ii). Address1 :
A-1, Vaishno Dham, Near Gayatri Heights, Kankerkhera
(iii). Address2 :
NH-58, Meerut, Uttar Pradesh
(iv). State :
Uttar Pradesh
(v). District :
Meerut
(vi). Pin :
250001
(vii). Landmark :
Near Gayatri Heights
(viii). Email address :
piu_meerut@yahoo.co.in
(ix). Landline Telephone No. :
121-2631228
(x). Fax No. :
121-2631228
(xi). Mobile No. :
9868126926
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Central PSU
A-3.
Details of Person Making Application
(i). First Name:
Santosh
(ii). Middle Name:
Kumar
(iii). Last Name:
Bajpai
(iv). Gender:
Male
(v). Designation:
PD
(vi). Address 1:
A-1, Vaishno Dham, Near Gayatri Heights
(vii). Address 2:
Kankerkhera, NH-58, Meerut
(viii). State:
Uttar Pradesh
(ix). District:
Meerut
(x). Tehsil:
NIL
(xi). Pin:
250001
(xii). Landmark:
Near Gayatri Heights
(xiii). Email Address:
piu_meerut@yahoo.co.in
(xiv). Landline Telephone No.:
121-2631228
(xv). Fax No.:
01212631228
(xvi). Mobile No.:
9868126926
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
1
Inprinciple
FP/UP/ROAD/1189/2008
7-UPB073/2008-LUC
4.105
4.105
06 Aug 2008
2
Inprinciple
FP/UP/ROAD/1946/2006
7-UPA048/2006-LUC
54.9
54.9
04 Jun 2006
3
Under Processing at State Government
FP/UP/ROAD/39712/2019
1.8945
0
4
Inprinciple
FP/UP/ROAD/34548/2018
8B/UP/06/78/2018/FC/512
1.572
1.572
20 Nov 2018
5
Inprinciple
FP/UP/ROAD/30178/201
8B/UP/06/41/2018/FC/229
49.29
49.29
27 Jun 2018
Total
111.7615
109.867
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Social Forestry Division Muzaffarnagar
27.7284
74.4287
2.
Social Forestry Division Bijnor
11.123
63.466
Total
38.8514
137.8947
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Muzaffarnagar
27.7284
74.4287
1.
Bijnor
11.123
63.466
Total
38.8514
137.8947
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Samaspur
0
3.125
2
Basi Viran
0
0.66
3
Rajupur
0
5.7
4
Fatehatpur hansapur
0
3.15
5
Bahasuma
0
7.95
6
Sadarpur
0
3.6
7
Mod kala
0
5.1
8
Mod Khurd (Bhogi)
0
9.3
9
Mohamadpur Shakist
0
3.75
10
Saifpur Firojpur
0
11.7
11
Samana
0
1.9226
12
Hashampur
0
1.4688
13
Putti Ibrahimpur
2.2808
2.2648
14
Tikola
0
8.4204
15
Mubarikpur
0
0.7305
16
Mahmudpur Bangar
0
4.537
17
Rasulpur
0
2.4992
18
Rasulpur Ah.
0.5808
1.1536
19
Babra
0.3484
0.346
20
Sikreda
2.6622
2.6434
21
Shivpuri
2.2168
2.2012
22
Kailapurjasamor
4.9564
4.9216
23
Kasimpur Kola
3.8529
0
24
Isahakwala
1.847
1.834
25
Jaitpur Gaursiwala
2.9428
2.9222
26
Gawandi Gair Ahatmatal
1.8586
1.8456
27
Ujayali Khurd Gair Ahatmatal
2.8631
1.2576
28
Ujayali Khurd Ahatmatal
1.3339
6.4224
29
Bijnor
7.3361
7.0554
30
Faridpur Kaji
2.416
2.3224
31
Jhakdi Bangar
0
3.9641
32
Islampurdas
0
1.6379
33
Islampur Dipa
0
2.46
34
Taimurpur
0.12
0
35
Tarikampur Rupchand
0
4.8062
36
Rasulpur Pruthi
0
1.2496
37
Chinchroli Bangar
0
2.8646
38
Faridpur Mira
0.12
0
39
Gokulpur Kasam
0
6.9978
40
Murtajapur Bulaki
0
2.3646
41
Kachhapura
1.1156
0.7462
Total
38.8514
137.8947
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Bridges & Culverts
1.33
11.8873
2
Pavement
37.5214
126.0074
Total
38.8514
137.8947
C.
Maps of forest land proposed to be diverted
Division 1. : Social Forestry Division Bijnor
(i). Area of forest land proposed to be diverted(in ha.) :
11.123
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
11.123
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Social Forestry Division Muzaffarnagar
(i). Area of forest land proposed to be diverted(in ha.) :
27.7284
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
27.7284
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
100
(iii). Temporary Employment(Number of person-days):
240000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
Yes
(a). Whether Project or a part thereof is located within a Protected Area ? :
Yes
(b). Status of approval of the Supreme Court :
Approval under cons
(ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project :
Application under process
(a). Date of submission of proposals :
03 Nov 2020
(b). Current status :
NIL
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
Compliance details for EDS dated 12-12-2019 of the NODAL officer and submission letter from Project Authority
2
Compliance details for EDS dated 12-12-2019 of the NODAL officer -Forest&Wildlife Gazette Notification attested copy
3
Compliance details for EDS dated 12-12-2019 of the NODAL officer -Project Sanction Letter
4
Compliance details for EDS dated 12-12-2019 of the NODAL officer -Project Strip Plan (Signed , seal with date)
5
Compliance details for EDS dated 12-12-2019 of the NODAL officer -Project Typical Cross Section (Signed , seal with date)
6
Compliance of your (NODAL) EDS dated 29-01-2020.
7
Compliance of EDS from office of NODAL dated 01-06-2020
8
Compliance of EDS issued from office of DFO dated 3-2-2021
9
Undertaking for Entire Tree Transplantation (ETT) Muzaffarnagar
10
Undertaking for Entire Tree Transplantation (ETT) Bijnor
11
Compliance of EDS issued from office of DFO-Muzaffarnagar on 10-9-2021 Study for Biodiversity and wildlife conservation/ mitigation is under progress. Also, wildlife clearance proposal is being processed separately. All the mitigation measure suggested by WII will be fully obeyed in true respect.
12
Land Statement- Meerut ( No- Forest land required but road alignment falls in Meerut also)
13
Compliance of EDS dated 27-12-2021-RO-Lucknow
14
project Brief
15
project Cost
16
Cost Benefit Analysis report
17
Forest Land Statement Muzaffarnagar
18
Forest Land Statement Bijnor
19
Project Location Map
20
Alternative Analysis Report for different alignments
21
Muck Disposal Plan
22
Typical Cross sectional map
23
Project Sanction Letter
24
Strip Plan
25
Wildlife Study Report
26
Geo-Digital Map MuzaffarNagar
27
Geo-Digital Map Bijnor
28
Reply on EDS - MoEFCC RO Lucknow dated 11-04-2022 through DFO dated 19-05-2022
29
All undertakings and certificates from office of USER Agency
30
Compliance of EDS-DFO Muzaffarnagar dated 3-11-2022
31
Compliance of EDS (DFO) date 22-10-2022
32
Compliance of EDS issued in REC meeting dated 30-05-2023
Print