FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/UP/ROAD/34116/2018   (ii). Name of Project for which Forest Land is required : Rehabilitation and widening of GT Road section at Begum Bazar at km 185+800 to Chaufatka at km 194+000 (total length 8.200 km) in district Allahabad, Uttar Pradesh.   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : In view of Ardh Kumbh Mela 2019, the Governor, Uttar Pradesh through Chief Engineer ( HQ-1), has directed to widen the road section. The project is located in district and division Allahabad.   (iv). State : Uttar Pradesh   (v). Category of the Proposal : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 2494.71   (viii). Area of forest land proposed for diversion(in ha.): 6.418   (ix). Non-forest land required for this project(in ha.): 0   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : CD ONE PWD UP ALLAHABAD   (ii). Address1 : Construction Division-1 , UP-PWD Allahabad   (iii). Address2 : NIL   (iv). State : Uttar Pradesh   (v). District : PRAYAGRAJ   (vi). Pin : 211002   (vii). Landmark : NIL   (viii). Email address : eecd1pwdalld@gmail.com   (ix). Landline Telephone No. : 532-2544312   (x). Fax No. : 532-   (xi). Mobile No. : 9415457258   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Ashok   (ii). Middle Name: Kumar   (iii). Last Name: Dwivedi   (iv). Gender: Male   (v). Designation: EXECUTIVEENGINEER   (vi). Address 1: Construction Division-1, UP-PWD, Allahabad   (vii). Address 2: NIL   (viii). State: Uttar Pradesh   (ix). District: PRAYAGRAJ   (x). Tehsil: Allahabad   (xi). Pin: 211002   (xii). Landmark: NIL   (xiii). Email Address: eecd1pwdalld@gmail.com   (xiv). Landline Telephone No.: 532-2544312   (xv). Fax No.: NIL   (xvi). Mobile No.: 9415457258   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Social Forestry Division Allahabad6.4180
Total6.4180
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.PRAYAGRAJ6.4180
Total6.4180
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Barmoli2.640
2Chack Mundera2.160
3DhumanGanj0.320
4Sulev Sarai1.120
5Chaufatka0.1780
Total 6.418 0
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Road Widening Work6.4180
Total 6.418 0
C. Maps of forest land proposed to be diverted
Division 1. : Social Forestry Division Allahabad
  (i). Area of forest land proposed to be diverted(in ha.) : 6.418   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.6.418    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: No   (a). Reason for not providing such map: The project is of additional widening along 4 lane
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 0   (iii). Temporary Employment(Number of person-days): 9000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: Linear or 'strip' plantation declared as protected forest along with road/rail/canal sides for widening or expansion of road/rail/canal
Additional information Details
Documents
S.No Documents
Remarks
1Details of Compliance made for nodal office EDS dated 18-06-2018
2Project Brief Note
3Project Cost
4Forest Land Statement
5Forest Gazette Notification
6Project Location Map
7Non-applicability of Cost Benefit Report
8Digital Map showing Project road alignment on Satellite Imagery
9Muck disposal Plan
10Undertaking regarding FRA
11Compliance of EDS sought on 27thJune2018 " Acknowledgement slip of DM Allahabad is without seal of the office. Upload again with the seal in the receiving letter."
12Compliance Letter of User Agency for EDS-RO dated 24th July 2018
13Government Order - Compliance from User Agency for EDS-RO dated 24th July 2018
14Typical Cross Sectional Map - Compliance from User Agency for EDS-RO dated 24th July 2018
15All Applicable Undertakings- Compliance from User Agency for EDS-RO dated 24th July 2018