FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/WATER/43413/2019
(ii). Name of Project for which Forest Land is required :
Pitthuwala Dtrinking Water Supply Scheme
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
This Drinking Water Supply Scheme will provide drinking water to Chandrabani Khalsa ans Chandrabani Grant habitation having population about 2500.
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Drinking Water
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
260.03
(viii). Area of forest land proposed for diversion(in ha.):
0.03
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
20
A-2.
Details of User Agency
(i). Name :
EE CONSTRUCTION DIVISION UTTARAKHAND PAYJAL NIGAM DEHRADUN
(ii). Address1 :
EE Construction Div Uttarakhand Payjal Nigam Kamala Nagar Dehradun
(iii). Address2 :
NIL
(iv). State :
Uttarakhand
(v). District :
Dehradun
(vi). Pin :
248001
(vii). Landmark :
Opp ONGC Hospital
(viii). Email address :
eecdupjnddn@gmail.com
(ix). Landline Telephone No. :
1352-2755703
(x). Fax No. :
1352-2755703
(xi). Mobile No. :
7830600060
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State PSU
A-3.
Details of Person Making Application
(i). First Name:
Narender
(ii). Middle Name:
NIL
(iii). Last Name:
Singh
(iv). Gender:
Male
(v). Designation:
Add Assistant Engineer
(vi). Address 1:
Office of the Exicutive Engineer Uttarakhand Payjal Nigam Nigam Dehradun
(vii). Address 2:
NIL
(viii). State:
Uttarakhand
(ix). District:
Dehradun
(x). Tehsil:
Dehradun
(xi). Pin:
248001
(xii). Landmark:
Opp ONGC Hospital
(xiii). Email Address:
quantum_nary@yahoo.co.in
(xiv). Landline Telephone No.:
135-2755703
(xv). Fax No.:
01352755703
(xvi). Mobile No.:
7579069609
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Dehradun
0.03
0
Total
0.03
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Dehradun
0.03
0
Total
0.03
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Chandrabani Khalsa
0.03
0
Total
0.03
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
OHT and Pump house
0.03
0
Total
0.03
0
C.
Maps of forest land proposed to be diverted
Division 1. : Dehradun
(i). Area of forest land proposed to be diverted(in ha.) :
0.03
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.03
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
Pipeline already exists, hence no alternate is ava
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
200
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
Prativedan
2
Form_A_Part 1
3
Administrative_Financial_Saction
4
Joint_Inspection_Report
5
Land_Schedule
6
Length_Width
7
Bar_Chart
8
Component_Wise_Breakup
9
Beneficial_Villages
10
No_Alternate_Land_and_MInimum_Land_requirment
11
Not_a_Part_of_NP
12
Certificate_reg_Geogolist_Report
13
Task_Force_Report
14
Standerd_Condition
15
Certificate_reg_Geogolist_Report
16
Certificate_reg_Increased_NPV
17
Calculation_of_NPV
18
Certificate_reg_Alternate_Fuel
19
Certificate_reg_Lease_Period
20
Certificate_reg_Flora_Fauna
21
Certificate_reg_Payment_of_Dues
22
Certificate_reg_Trees
23
Distance_From_Park
24
Work_Not_Started
25
Certificate_reg_Muck_Disposal
26
Cost_of_Land_lease_Rent
27
Digital_Map
28
Geo_Reference_Map
29
FRA_2006
30
PITHUWALA_DWSS_DFO_Office_EDS_Reply
31
Reply of EDS dated 03-04-2021