FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/WATER/157192/2022
(ii). Name of Project for which Forest Land is required :
Nagrasu Water Supply Scheme
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Nagrasu Village is situated at Rishikesh- Badrinath highway. The existing water supply Scheme of nagrasu is severely damaged due to most important project of Rishikesh Karnprayag railway line. So that the new water supply scheme is proposed for 2284 population of Nagrasu village uder the R& R Plan
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Drinking Water
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
300
(viii). Area of forest land proposed for diversion(in ha.):
0.1874
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
30
A-2.
Details of User Agency
(i). Name :
UTTARAKHAND PEYJAL NIGAM
(ii). Address1 :
Construction Division Uttarakhand peyjal nigam Rudraprayag
(iii). Address2 :
NIL
(iv). State :
Uttarakhand
(v). District :
Rudraprayag
(vi). Pin :
246171
(vii). Landmark :
Belani
(viii). Email address :
cdupjnrudraprayag@gmail.com
(ix). Landline Telephone No. :
1364-233207
(x). Fax No. :
1364-
(xi). Mobile No. :
9410568370
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Naval
(ii). Middle Name:
NIL
(iii). Last Name:
Kumar
(iv). Gender:
Male
(v). Designation:
EE
(vi). Address 1:
Construction Division Uttarakhand Peyjal Nigam Rudraprayag
(vii). Address 2:
NIL
(viii). State:
Uttarakhand
(ix). District:
Rudraprayag
(x). Tehsil:
Rudraprayag
(xi). Pin:
246171
(xii). Landmark:
NIL
(xiii). Email Address:
cdupjnrudraprayag@gmail.com
(xiv). Landline Telephone No.:
1364-233207
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9410568370
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Rudraprayag
0.1874
0
Total
0.1874
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Rudraprayag
0.1874
0
Total
0.1874
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Nagrasu
0.1874
0
Total
0.1874
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
BFG
0.0009
0
2
RF
0.0005
0
3
Pipe line
0.186
0
Total
0.1874
0
C.
Maps of forest land proposed to be diverted
Division 1. : Rudraprayag
(i). Area of forest land proposed to be diverted(in ha.) :
0.1874
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.1874
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
3
(iii). Temporary Employment(Number of person-days):
1800
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
Format 2 (Pre permission form Rule 2 & DFO Recommendation Part II)
2
Format 3 (Administrative and Financial approval )
3
Format 4 (Joint Inspection Report)
4
Format 6 (Site Map of Scheme)
5
Format 7 (digital and Geo referenced map)
6
Format 8 (Certificate of cancellation of optional alignment)
7
Format 9 (Comparative statement of various options and certificate of reason for their cancellation)
8
Format 10 (Certificate of non-availability of alternative land and minimum demand for forest land)
9
Format 11 (Land Schedule)
10
Format 12 (Project Length Width Description)
11
Format 14 (Work not started certificate)
12
Format 16 (baanj trees falling certificate)
13
Format 17 to 17.1( Minimum tree felling certificate and In case the tree is not affected, the certificate given by DFO)
14
Format 18 (Certificate of the project site not being part of any National Park Wildlife Sanctuary)
15
Format 19 (Certificate of distance from National Park Wildlife Sanctuary)
16
Format 20 (No Objection Certificate of Chief Wildlife Warden)
17
Format 21 (No Objection Certificate of General Assembly)
18
Format 22 to 22.2 (Cost Benefit Ratio Chart)
19
Format 23 to 23.4(C23 No Objection Certificate under Forest Rights Act 2006)
20
Format 24 (Item wise land wise area wise details of various components of the proposed project)
21
Format 25 (Lay Out Plan)
22
Format 26 (Geological Report Compliance Certificate)
23
Format 27 (Certificate of Compliance of Geologist's Recommendations and Suggestions)
24
Format 28 (Task Force Certificate)
25
Format 29 (Standard terms)
26
Format 30 (Certificate of not being a place of religious mythological historical importance)
27
Format 31 (Certificate of no damage to wild life and flora)
28
Format 32 (Certificate of providing kerosene cooking gas to the workers working in the project)
29
Format 34 (Certificate of value of forest land annual lease rent)
30
Format 39 (Estimate maintenance for planting ten times trees or minimum 100 trees in lieu of trees to be cut)
31
Format 41 (Certificate of Debris Disposal Project)
32
Format 42 (Estimation of amount of NPV)
33
Format 43 (Certificate of depositing additional amount according to the increased rates of NPV)
34
Format 44 (Estimates of demarcation by RCC pillars of forest land to be repatriated for the proposed project)
35
Format 45 (Lease term certificate)
36
Format 46 (Certificate of non violation of Forest Conservation Act 1980)
37
Format 47 (Catchment Treatment Plan for Proposed Hydroelectric Project)
38
Bar Chart Format 13
39
Format 33 Population Certificate
40
Format 15 Tree Effecting Certificate
41
Format 1 Partvedan
42
Letter for remove proposal objection
43
Letter for remove proposal objection