FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/UK/WATER/148037/2021   (ii). Name of Project for which Forest Land is required : Hansidhunga Gujrukot Group of Village Pumping water supply scheme   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Hansidhuga Gujrukot Group of village pumping water supply projects for drinking water supply for the Villagers of block-Sult District Almora . The construction of water tanks and pipe line is essential for this project therefor the land is required for pipe line laying in this project.   (iv). State : Uttarakhand   (v). Category of the Proposal : Drinking Water   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 3471   (viii). Area of forest land proposed for diversion(in ha.): 0.794   (ix). Non-forest land required for this project(in ha.): 0   (x). Total period for which the forest land is proposed to be diverted(in years): NIL
A-2. Details of User Agency
  (i). Name : CONSTRUCTION DIVISION UTTARAKHAND PEYJAL NIGAM BHIKIYASAIN   (ii). Address1 : Naula, Bhikiyasain,   (iii). Address2 : Dist. Almora, Uttarakhand   (iv). State : Uttarakhand   (v). District : Almora   (vi). Pin : 263658   (vii). Landmark : Peyjal Nigam Office   (viii). Email address : eecd.bksain@gmail.com   (ix). Landline Telephone No. : 5966-242056   (x). Fax No. : 5966-   (xi). Mobile No. : 9557169232   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Vipin   (ii). Middle Name: Kumar   (iii). Last Name: Ravi   (iv). Gender: Male   (v). Designation: Executive Engineer   (vi). Address 1: Uttarakhand Peyjal Nigam, Naula, Bhikiyasain   (vii). Address 2: Dist. Almora   (viii). State: Uttarakhand   (ix). District: Almora   (x). Tehsil: Bhikia Sain   (xi). Pin: 263658   (xii). Landmark: Peyjal Nigam Office   (xiii). Email Address: eecd.bksain@gmail.com   (xiv). Landline Telephone No.: 5966-242056   (xv). Fax No.: NIL   (xvi). Mobile No.: 9997972448   (i). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: No Data
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Almora0.7940
Total0.7940
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Almora0.7940
Total0.7940
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Bhonkhal,Machoor, Tyoulin0.7940
Total 0.794 0
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Pipeline0.7937640
Total 0.793764 0
C. Maps of forest land proposed to be diverted
Division 1. : Almora
  (i). Area of forest land proposed to be diverted(in ha.) : 0.794   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.794    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land: No Data   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: No   (a). Reason for not providing such map: No other alignment is technically feasible
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 3   (iii). Temporary Employment(Number of person-days): 1908
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted: No Data
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
Additional information Details
Documents
S.No Documents
Remarks
1DFO 10 year
2Bar Chart
3Benifided villagers
4CCF wildlife
5Certficate of DM
6No work started
7Chayati poorak plantation
8Historical building
9Certificate of Lease period
10Certificate of user agency
11coloured google map chaytipoorak
12Contaning justification
13Cost of forest land by DM
14demarcation of piller
15Details of Trees
16digital map
17Disposal of Musk
18Estimate of 100 Trees
19Felling of less Trees
20financial detail
21Geologyst report
22google map
23joint inspection
24Land shedule by DM and DFO
25LPG
26MOU
27National park
28NBWL
29NOC of panchyats
30Non violance
31NPV by user agency
32NPV
33short note
34Task force
35topo Sheet
36V K ravi