FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/TRANS/154613/2022
(ii). Name of Project for which Forest Land is required :
Dedicated 33 KV Transmission Line to Rail Vikas Nigam Limited from Gular Sub Station to Tunnel T2 in Shivpuri Tehri Garhwal District of Uttrakhand
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
The proposed 33 KV transmission line is required exclusively for operation of trains on 126 Km long new BG Rail Between Rishikesh - Karnaprayag (RVNL Project) in the state of Uttarakhand
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Transmission Line
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
250
(viii). Area of forest land proposed for diversion(in ha.):
1.68
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
EE EDD TEHRI UPCL
(ii). Address1 :
EE,EDD-TEHRI,UPCL BADRINATH SANSKRIT MAHAVIDHYALYA ,BAURARI, TEHRI GARHWAL
(iii). Address2 :
NIL
(iv). State :
Uttarakhand
(v). District :
Tehri Garhwal
(vi). Pin :
249001
(vii). Landmark :
BADRINATH SANSKRIT MAHAVIDHYALYA ,BAURARI,
(viii). Email address :
eddteh@yahoo.com
(ix). Landline Telephone No. :
1376-233117
(x). Fax No. :
1376-233117
(xi). Mobile No. :
9412078666
(xii). Website (if any) :
www.upcl.org
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Arjun
(ii). Middle Name:
Pratap
(iii). Last Name:
Singh
(iv). Gender:
Male
(v). Designation:
EXECUTIVE ENGINEER
(vi). Address 1:
EE,EDD-TEHRI,UPCL BADRINATH SANSKRIT MAHAVIDHYALYA ,BAURARI, TEHRI GARHWAL
(vii). Address 2:
NIL
(viii). State:
Uttarakhand
(ix). District:
Tehri Garhwal
(x). Tehsil:
NIL
(xi). Pin:
249001
(xii). Landmark:
BADRINATH SANSKRIT MAHAVIDHYALYA ,BAURARI,
(xiii). Email Address:
eddteh@yahoo.com
(xiv). Landline Telephone No.:
1376-233117
(xv). Fax No.:
01376233117
(xvi). Mobile No.:
9412078666
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
1
Inprinciple
FP/UK/VELEC/13267/2015
128/X-4-16/2(06)/2016
0.6
0.6
31 Mar 2016
2
Inprinciple
FP/UK/TRANS/12514/2015
460/X-4-15/1(259)/2015
0.4
0.4
27 Jul 2015
3
Inprinciple
FP/UK/Others/10660/2015
08B/UCP/09/83/2016/FC/2181
0.12
0.12
30 Mar 2017
Total
1.12
1.12
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Narendranagar,Munikireti
1.68
0
Total
1.68
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Tehri Garhwal
1.68
0
Total
1.68
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Gular
0.636
0
2
Timli
0.2528
0
3
Bavani Shivpuri
0.7912
0
Total
1.68
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Area falling Under Transmission Line
1.67
0
2
Area Involved in Pole Foundation
0.01
0
Total
1.68
0
C.
Maps of forest land proposed to be diverted
Division 1. : Narendranagar,Munikireti
(i). Area of forest land proposed to be diverted(in ha.) :
1.68
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
1.68
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
450
(iii). Temporary Employment(Number of person-days):
16352000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
No
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii) . Reason for not providing Non-Forest Land:
For laying of transmission lines
Additional information Details
Documents
S.No
Documents
Remarks
1
Prativedan (Request Letter)
2
Power of Attorney of Applicant
3
Signed Toposheet of Proposed Land Diversion
4
Signed Digital/ Georeferenced Map of Proposed Land Diversion
5
Justification for Locating in Forest Land
6
Examination of Three Alternative Route
7
Reason to abondon other alternatives
8
Min Land Demand Certificate
9
Land Schedule
10
Length and Width of Proposed Diversion Land
11
Bar Chart
12
Certificate for work not yet started
13
Valuation of affected Trees
14
Details of Tree Actually to be cut
15
Certificate if tree are not affected
16
Certificate for min trees to be cut
17
Certificate of Wildlife Boundary Distance
18
Madvar incase of Hydropower
19
Layout Plan incase of Building or Hydropower
20
Geological Report
21
Affidavit to follow Geological Instructions by User Agency
22
Affidavit by UA to follow Task Force
23
Affidavit by UA to follow Standard Conditions defined by Forest Department
24
Certificate of Religious or Monuments Certificate
25
Undertaking by UA not to harm wildlife annimals or plants
26
Undertaking by UA to provide kerosin or rasoi gas to labourers
27
List of Benefited Villages from the Pariyojna
28
Proforma of Lease Agreement
29
Cost Assessment for 10 Yrs
30
Certificate for CA Land
31
Signed Copy of Topomap of CA Land
32
Signed Copy of Google or Geo-referenced Map of CA Land
33
Certificate for Assessment of Bauni Jati Ke Vruksh
34
Muck Dumping Plan
35
FRA 2006
36
Certificate for requirement of Revenue Land
37
Agreement Between UA and Landowners
38
NPV calculation of Proposed Diversion Land
39
Undertaking to provide increased NPV
40
Cost Calculation for Installation of Boundary Pillars
41
Lease Renewal - Not Applicable
42
Non-Voilation of FCA 1980
43
catchment Area Treatment Form
44
Requirement of EC
45
Kalajit Lease Renewal
46
Distance Certificate for Wildlife Boundary
47
Part I
48
Part II
49
Part III
50
Part IV
51
Part V
52
NOC From Chief Wildlife Conservator
53
Initial Joint Inspection Report
54
Details of Affected Trees
55
Forwarding Letter Dec 30, 2022
56
Complete FRA Dec 30, 2022
57
SDM Level FRA Dec 30, 2022
58
VLC FRA Dec 30, 2022
59
Government Order for Exemption from VLC FRA Dec 30, 2022
60
IRO MOEF&CC Dehradun approved TL with 2m and 3m width corridor Dec 30, 2022
61
Financial Approval for the Project Dec 30, 2022
62
Forwarding Letter (Part-1) 18.06.23
63
Forwarding Letter (Part-2) 18.06.23
64
Financial Approval of Project 18.06.23
65
Revised SDML FRA With Dated Marked 18.06.23
66
Copy of VLC FRA 18.06.23
67
Example of keeping width 2m from old approved forest proposal 18.06.23
68
Revised CA Digital Map 18.06.23
69
Revised CA Topo Map 18.06.23
70
Revised CA Scheme 18.06.23
71
Revised CA Suitability Certificate 18.06.23
72
Forwarding Letter (Response to IRO Queries)_July 2024
73
Justification for consideration of 2m width for transmission line
74
List of Lopping and Chopping of Trees
75
Copy of Revised CA Land Proformas
76
Copy of Administrative and Financial Approval
Print