FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/ROAD/9401/2015
(ii). Name of Project for which Forest Land is required :
Construction of thala bhayari bhitakote motor road.
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
For the Construction of road named Thala Bheyari Bhitakote sanction by Govt. order no 1542/III(2)/09-22(Mu. Ma. Gho.)/09 dated 31-03-2010 of Amount Rs. 525.00 Lac. By the const. of the road village Reewali Walli/Palli, Gaythya etc. are benefited.
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
525
(viii). Area of forest land proposed for diversion(in ha.):
3.325
(ix). Non-forest land required for this project(in ha.):
9.225
(x). Total period for which the forest land is proposed to be diverted(in years):
300
A-2.
Details of User Agency
(i). Name :
EXECUTIVE ENGINEER
(ii). Address1 :
Provincial Division P.W.D., Ranikhet
(iii). Address2 :
Mall Raod Ranikhet
(iv). State :
Uttarakhand
(v). District :
Almora
(vi). Pin :
263645
(vii). Landmark :
NIL
(viii). Email address :
eepdrani@yahoo.com
(ix). Landline Telephone No. :
5966-220679
(x). Fax No. :
NIL
(xi). Mobile No. :
7500540231
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Lalit
(ii). Middle Name:
Kumar
(iii). Last Name:
Goel
(iv). Gender:
Male
(v). Designation:
Executive Engineer
(vi). Address 1:
Provincial Division PWD, Ranikhet
(vii). Address 2:
Mall Road Ranikhet
(viii). State:
Uttarakhand
(ix). District:
Almora
(x). Tehsil:
NIL
(xi). Pin:
263645
(xii). Landmark:
Ranikhet
(xiii). Email Address:
eepdrani@yahoo.com
(xiv). Landline Telephone No.:
5966-220679
(xv). Fax No.:
05966220679
(xvi). Mobile No.:
9412919971
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
1
Approved
FP/UK/ROAD/19725/2016
8B/UCP/06/173/2016/FC/1953
2.16
2.16
29 Dec 2016
21 Feb 2018
Total
2.16
2.16
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Almora
3.325
9.225
Total
3.325
9.225
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Almora
3.325
9.225
Total
3.325
9.225
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Riwali walli
0.525
1.44
2
Riwali palli
0
0.9
3
Mayal bahkali
0.4725
0.3375
4
Gathiya
0.3325
0.495
5
Jogiya malla
0
0.225
6
garhkot talla
0.1925
5.0625
7
garhkot malla
0.595
0.5625
8
Ghuruadhunga
0.4375
0.202
9
Bhitakote
0.77
0
Total
3.325
9.2245
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Road 1.00 to 15.00 Km
3.325
8.847
2
Muck Disposal Yard
0
0.377
Total
3.325
9.224
C.
Maps of forest land proposed to be diverted
Division 1. : Almora
(i). Area of forest land proposed to be diverted(in ha.) :
3.325
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
3.325
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
220
(iii). Temporary Employment(Number of person-days):
460
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
One
District 1. : Almora
(a). Village:
Okhaliya
(b). Area(in ha.):
6.66
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
1, 2, 3, 4, 5, 6, 7
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No
Documents
Remarks
1
A Short Narrative and Importance of the Project
2
Administrative and Financial Sanction
3
Preliminary Joint Inspection Report
4
Comperative chart showing statement of both alignment or alternate site
5
Certificate from the DM that no alternative suitable non-forest land
6
Land schedule
7
Category wise land length
8
Bar Chart With Index
9
Compensatory afforestation scheme in Civil and Soyam land (10years)
10
Certificate Regarding suitability of indentified hand for CA
11
Undertaking by the user agency to bear the cost of CA
12
Road Side/Gap Filling Plantation Estimate
13
Undertaking by the User Agency to bear the cost of Road Side/Gap Filling Plantation
14
Details of the trees with their scientific name in RF, Civil Soyam, Van panchayat, Private Notified land
15
Felling of Oak trees (If involves, inspection report of the concerning CF has to be provided)
16
Certificate of felling minimum trees during the project work.
17
Muck disposal scheme
18
Whather project area is a part of National Park or sanctuary and airal distance of the project from National Park or sanctuary signed by DFO
19
No voilation has taken place, FC Act. 1980 reg.
20
NOC from local Gram Sabhas
21
Certificate work has not been started reg.
22
Geologist Report
23
Task Force Report
24
Certificate by user agency for complying the condition imposed in Manak Shartain
25
Certificate by user agency for complying the condition imposed in geologist report/Task forcex
26
historical/monumental or relegeous place will be effected certificate reg.
27
Undertaking regarding no animal will be effected adversely by the project
28
Undertading to provide alternative fuel wood, kerosene or LPG to labours
29
Benefited villagers/families/population certificate
30
NPV calculation certificate as per S. court
31
Undertaking of payment of NPV S. court increases the rates of NPV
32
Undertaking of user agency to bear the cost for dimarcation work
33
Check list/Fact Sheet
34
Hard copy recive
35
Hard copy recive CF
36
Form Part-I
37
Objection removal letter no. 2576/36c dated 26-10-16 in ref of your letter no. memo/12-1(2) dated 11-08-16
38
CA Schems
39
Objection removed by letter no 02/camp/36c/rkt dated 02-11-16
40
Objection removal letter no. 2724/36c dated 18-11-2016 in ref of your letter no. memo/12-1(2) dated 16-11-2016
41
Objection removed by letter no. 622/36c dated 30-03-2017 in ref of letter no. memo/12-1(2) dated 21-02-2017
42
Letter regarding hard copy
43
objection removed by letter no 1400/36c dated 19-06-2018 in ref of Dfo letter no. memo/12-1(2) dated 07-06-18
44
Objection removed by letter no. 1753/36C dated 21-07-2018
45
Objection removed by letter no 1862/36c dated 30-07-2018 in ref of DFO Almora dated 23-06-2018
46
Objection removed by letter no 1862/36c dated 30-07-2018 in ref of DFO Almora dated 23-06-2018
47
Objection removed by letter no 1862/36c dated 30-07-2018 in ref of DFO Almora dated 23-06-2018
48
Objection removed by letter no 1862/36c dated 30-07-2018 in ref of DFO Almora dated 23-06-2018
49
Objection removed by letter no 1862/36c dated 30-07-2018 in ref of DFO Almora dated 23-06-2018
50
Objection removed by letter no 1862/36c dated 30-07-2018 in ref of DFO Almora dated 23-06-2018
51
Objection removed by letter no 1862/36c dated 30-07-2018 in ref of DFO Almora dated 23-06-2018
52
Objection removed by letter no 1862/36c dated 30-07-2018 in ref of DFO Almora dated 23-06-2018
53
Objection removed by letter no. 1862/36c dated 30-07-2018 in ref of DFO almora letter no Nil dated 23-06-2018
54
Objection removed by letter no 51/36c dated 03-01-2019
55
Objection Removed by letter no 360/36c dated 02-02-2019
56
Wrong Letter Uploaded
57
Objection removed by letter no 1546/36c dated 07-06-2019
58
Objection Removal letter no 1214/36c dated 22-08-2020 (24-08-2020)
59
Objection Removed by letter no 1934/36c dated 16-09-2021
60
correction made as per instruction given
61
correction made as per instruction given
62
Objection removed by letter no 1104/36c dated 18-03-2023
63
Receiving copy of letter which show that Hard copy rec at your office on 21-03-23
64
Receiving copy of letter which show that Hard copy rec at your office on 21-03-23
65
Objection removed by letter no 1354/36c dated 11-04-2023
66
Letter written for Joint Inspection
67
Objection remove as per instruction
68
IT Cell Dehradun Approved For Air Distance Certificate
69
3 point objection remove latter no.1101/36 c dtd 31/05/2024