FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/ROAD/42851/2019
(ii). Name of Project for which Forest Land is required :
Construction of double lane Motor Road and foot path from Doidwala Dudhli Main road to Chandmari Mishrawal Lachhiwala bridge in district Dehradun consituency Doiwala under Hon'ble CM Ghoshna No. 105/2
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Provision of New road construction for local villagers of Chandmari, Missarwala and Lachhiwala. There is no existing road for communication, So provision of new motor road is proposed and same has been sanctioned by the UK Govt
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
13.8
(viii). Area of forest land proposed for diversion(in ha.):
3.6
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
PUBLIC WORK DEPARTMENT
(ii). Address1 :
Temporary Division, PWD, Rishikesh
(iii). Address2 :
NIL
(iv). State :
Uttarakhand
(v). District :
Dehradun
(vi). Pin :
249201
(vii). Landmark :
Near Railway Station
(viii). Email address :
eetdrksh@rediffmail.com
(ix). Landline Telephone No. :
135-2430660
(x). Fax No. :
135-135
(xi). Mobile No. :
9412053901
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Dinesh
(ii). Middle Name:
NIL
(iii). Last Name:
Sindhwal
(iv). Gender:
Male
(v). Designation:
Assistante Engineer
(vi). Address 1:
Temporary Division, PWD, Rishikesh
(vii). Address 2:
NIL
(viii). State:
Uttarakhand
(ix). District:
Dehradun
(x). Tehsil:
Rishikesh
(xi). Pin:
249201
(xii). Landmark:
Near Railway Station
(xiii). Email Address:
eetdrksh@rediffmail.com
(xiv). Landline Telephone No.:
135-2430660
(xv). Fax No.:
01352430660
(xvi). Mobile No.:
8126906336
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Dehradun
3.6
0
Total
3.6
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Dehradun
3.6
0
Total
3.6
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Doiwala Nagar Palika
3.6
0
Total
3.6
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
road
3.6
0
Total
3.6
0
C.
Maps of forest land proposed to be diverted
Division 1. : Dehradun
(i). Area of forest land proposed to be diverted(in ha.) :
3.6
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
3.6
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
already existing road
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
600
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
Yes
(a). Whether Project or a part thereof is located within a Protected Area ? :
No
(ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project :
Application yet to be submitted
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
Yes
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
One
District 1. : Dehradun
(a). Village:
ghissarpadhi
(b). Area(in ha.):
7.2
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
228
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No
Documents
Remarks
1
Part 1
2
Govt orders
3
Joint inspection report
4
land schedule
5
Project L and B
6
Bar_Chart
7
not yet work start
8
Geological_report
9
NOC of villagers
10
Geological_certificate
11
Task_force_certificate
12
Manak
13
Wild_Life_Certificate
14
Labour_Certificate
15
Villagers_List
16
NPV_List
17
Cerificate of start point and end point of road
18
Fact_sheet
19
Cover_page
20
Act 1980 cert
21
Geo Refrence CA Map
22
CA toposheet Map
23
giologist permission
24
Arial Distance Certificate
25
Work Start Cert.pdf
26
NPV Amount
27
muck dumping cert
28
Ownership Proof Cert
29
wild life clearess cert
30
ownarship proof cert
31
IRC SP Cert
32
wild life century certificate
33
justification and IRCSP cer
34
comments of cwlw
35
SDM Doiwala revenue and forest joint report
36
letter
Print