FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/ROAD/39084/2019
(ii). Name of Project for which Forest Land is required :
Construction of Triyuginarayan to Toshi moter road
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
At present, the remotest village Toshi (Total population 145) of district Rudraprayag is devoid of moter road. Villagers have to walk 4.00 km to Triyuginarayan for basic facilities such as Education, Hospitals, etc.The proposed moter road (6.00 km) will pave the way towards Schools, hospitals etc.
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
148.8
(viii). Area of forest land proposed for diversion(in ha.):
4.5
(ix). Non-forest land required for this project(in ha.):
0.243
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
EECDPWDUKM
(ii). Address1 :
EXECUTIVE ENGINEER, CONST. DIVISION, PWD UKHIMATH, RUDRAPRAYAG
(iii). Address2 :
NIL
(iv). State :
Uttarakhand
(v). District :
Rudraprayag
(vi). Pin :
246469
(vii). Landmark :
NEAR ONKARESHWAR TEMPLE
(viii). Email address :
ukhimathpwd@yahoo.in
(ix). Landline Telephone No. :
1364-284239
(x). Fax No. :
1364-284239
(xi). Mobile No. :
9675898652
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Andeep
(ii). Middle Name:
NIL
(iii). Last Name:
Rana
(iv). Gender:
Male
(v). Designation:
Assistant Engineer
(vi). Address 1:
Construction Division, PWD, Ukhimath (Rudraprayag) - 246469
(vii). Address 2:
NIL
(viii). State:
Uttarakhand
(ix). District:
Rudraprayag
(x). Tehsil:
NIL
(xi). Pin:
246469
(xii). Landmark:
Near Onkareshwar Temple
(xiii). Email Address:
ukhimathpwd@yahoo.in
(xiv). Landline Telephone No.:
1364-284239
(xv). Fax No.:
01364284239
(xvi). Mobile No.:
7055570245
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Kedarnath Wild Life Division,Gopeshwar
4.5
0.243
Total
4.5
0.243
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Rudraprayag
4.5
0.243
Total
4.5
0.243
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Toshi
4.5
0.243
Total
4.5
0.243
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Road Construction
4.011
0.243
2
Muck Disposal 1
0.04
0
3
Muck Disposal 2
0.04
0
4
Muck Disposal 3
0.041
0
5
Muck Disposal 4
0.04
0
6
Muck Disposal 5
0.04
0
7
Muck Disposal 6
0.04
0
8
Muck Disposal 7
0.04
0
9
Muck Disposal 8
0.07
0
10
Muck Disposal 9
0.075
0
11
Muck Disposal 10
0.063
0
Total
4.5
0.243
C.
Maps of forest land proposed to be diverted
Division 1. : Kedarnath Wild Life Division,Gopeshwar
(i). Area of forest land proposed to be diverted(in ha.) :
4.5
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
4.5
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
18003
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
Yes
(a). Whether Project or a part thereof is located within a Protected Area ? :
No
(ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project :
Approval obtained
(a). MoEF File No :
6-4/2018WL
(b). Copy of approval of Standing of the NBWL:
(c). Date of Approval :
07 Feb 2018
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
One
District 1. : Rudraprayag
(a). Village:
nyalsu Rampur
(b). Area(in ha.):
9
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
822,823
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No
Documents
Remarks
1
Authority Letter
2
Benefited Villages,Families Certificate
3
Certificate by user agency for complying the condition imposed in geologist report
4
Certificate by user agency for complying the condition imposed in Standard Condition
5
Certificate from the DM that no alternative suitable non-forest land is available for the project in
6
Certificate of felling minimum trees during the project work
7
Certificate work has not be started
8
Comparative Chart showing statement of both alignment
9
Copy of Mou agreement executed between the Present owner and the User Agency
10
Copy of survey of India Toposheet indicate the boundary of forest land
11
Cost of forest land
12
Demarcation of land to be diverted
13
Details of tree with Their Scientific Name
14
FRA 2006
15
Geo referenced map of forest land proposed to be diverted
16
Geologist report
17
joint inspection report
18
Justification of Project
19
Land schedule
20
Muck disposal plan
21
No Historical monuments will be effected certificate
22
No voilation has taken place, FC act 1980
23
NOC from local gram sabha
24
NPV calculation certificate as per Hon'ble Supreem court MoEF orders by DFO
25
Task Force report
26
Undertading to provide alternative fuelwood, kerosene or LPG to labours involved in project
27
Undertaking by the User Agency to bear the cost of Road side gap filling plantation
28
Undertaking of payment of NPV, if Hon'ble Supreem Court increses the rates of NPV (by user agency)
29
Undertakoing regarding no animal will be effected adversely by the project
30
copy of approval of Standing Committee of the NBWL
31
Category Wise Landd area in Ha
32
objections remove letter
33
objections remove letter
34
objections remove letter 10-07-2019
35
SIR Report
36
Part I,II,III
37
objections remove letter 28Nov2019
38
Certificate of Aerial distance of the project area
39
Colored copy of the google map showing the land identified for CA
40
Compensatory afforestation scheme in Civil and Soyam land 10 years
41
copy of non encumberence certificate for the forest land
42
copy of ownership proof
43
Administrative and Financial sanction
44
If project Area is within 10 km radius of NP or SancturyNOC of CCF
45
Mitigation Plan
46
Survey of India Toposheet in 1 50 000 scale indicating location of the land identified for creation of Compensatory Afforestation
47
Check list Fact Sheet
48
Complete File
49
Objections remove letter 02-09-2020
50
Certificate by CF Part III
51
CF side inspection report
52
CF side inspection report, Certificate by CF Part III & Felling of Oak tree
53
Felling of Oak tree
54