FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/ROAD/22249/2016
(ii). Name of Project for which Forest Land is required :
Jaal bend to Chilond Motor Road
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Chilond is a last village (population 311) in Kalimath Valley of District Rudraprayag (Uttarakhand) which is Still not connected to Road. Villagers travel by foot, a Steep Slope of 2Km to reach the Road and further travel 25 Km by road to nearest Hospital and Market. This Road will provide connectiv
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
33.6
(viii). Area of forest land proposed for diversion(in ha.):
1.61
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
EECDPWDUKM
(ii). Address1 :
EXECUTIVE ENGINEER, CONST. DIVISION, PWD UKHIMATH, RUDRAPRAYAG
(iii). Address2 :
NIL
(iv). State :
Uttarakhand
(v). District :
Rudraprayag
(vi). Pin :
246469
(vii). Landmark :
NEAR ONKARESHWAR TEMPLE
(viii). Email address :
ukhimathpwd@yahoo.in
(ix). Landline Telephone No. :
1364-284239
(x). Fax No. :
1364-284239
(xi). Mobile No. :
9675898652
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Andeep
(ii). Middle Name:
NIL
(iii). Last Name:
Rana
(iv). Gender:
Male
(v). Designation:
Assistant Engineer
(vi). Address 1:
Construction Division, PWD, Ukhimath (Rudraprayag) - 246469
(vii). Address 2:
NIL
(viii). State:
Uttarakhand
(ix). District:
Rudraprayag
(x). Tehsil:
NIL
(xi). Pin:
246469
(xii). Landmark:
Near Onkareshwar Temple
(xiii). Email Address:
ukhimathpwd@yahoo.in
(xiv). Landline Telephone No.:
1364-284239
(xv). Fax No.:
01364284239
(xvi). Mobile No.:
7055570245
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Rudraprayag
0.4
0
2.
Kedarnath Wild Life Division,Gopeshwar
1.21
0
Total
1.61
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Rudraprayag
1.61
0
Total
1.61
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Chilond
1.61
0
Total
1.61
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Road Construction
1.3748
0
2
Bridge Construction
0.0252
0
3
Muck 1
0.05
0
4
Muck 2
0.05
0
5
Muck 3
0.04
0
6
Muck 4
0.07
0
Total
1.61
0
C.
Maps of forest land proposed to be diverted
Division 1. : Rudraprayag
(i). Area of forest land proposed to be diverted(in ha.) :
0.4
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.4
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Kedarnath Wild Life Division,Gopeshwar
(i). Area of forest land proposed to be diverted(in ha.) :
1.21
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
1.21
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
11200
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
Yes
(a). Whether Project or a part thereof is located within a Protected Area ? :
Yes
(b). Status of approval of the Supreme Court :
Approval under cons
(ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project :
Approval obtained
(a). MoEF File No :
6-79/2015WL (35th Meeting)
(b). Copy of approval of Standing of the NBWL:
(c). Date of Approval :
24 Aug 2015
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
One
District 1. : Rudraprayag
(a). Village:
Jaaltalla
(b). Area(in ha.):
3.22
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
1044
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No
Documents
Remarks
1
Importance of Project
2
NOC from local gram sabha
3
Ownership proof
4
Task Force report
5
Administrative and Financial sanction.pdf
6
Authority Letter.pdf
7
Bar chart with index.pdf
8
Benefited Villages,Families Certificate.pdf
9
Category Wise Landd area in Ha.pdf
10
Certificate by user agency for complying the condition imposed in geologist report.pdf
11
Certificate by user agency for complying the condition imposed in Standard Condition.pdf
12
Certificate from the DM that no alternative suitable non-forest land is available for the project in.pdf
13
Certificate of felling minimum trees during the project work
14
Certificate regarding suitability of indentified land for Comensatory Afforestation by DFO.pdf
15
Certificate work has not be started.pdf
16
Check list Fact Sheet.pdf
17
Comparative Chart showing statement of both alignment.pdf
18
Compensatory afforestation scheme in Civil and Soyam land (10 years).pdf
19
Copy of survey of India Toposheet indicate the boundary of forest land.pdf
20
Cost of forest land.pdf
21
Demarcation of land to be diverted.pdf
22
Details of tree with Their Scientific Name.pdf
23
Felling of Oak treea.pdf
24
FRA 2006.pdf
25
Geo referenced map of forest land proposed to be diverted.pdf
26
Geologist report.pdf
27
If project Area is within 10 km radius of NP or SancturyNOC of CCF.pdf
28
joint inspection report.pdf
29
Land schedule.pdf
30
Muck Disposal.pdf
31
National Wild Life Board Sanction.pdf
32
No Historical monuments will be effected certificate.pdf
33
No voilation has taken place, FC act 1980.pdf
34
NPV calculation certificate as per Hon'ble Supreem court MoEF orders by DFO.pdf
35
Undertading to provide alternative fuelwood, kerosene or LPG to labours involved in project..pdf
36
Undertaking by the User Agency to bear the cost of Road side gap filling plantation.pdf
37
Undertaking of payment of NPV, if Hon'ble Supreem Court increses the rates of NPV (by user agency).pdf
38
Undertakoing regarding no animal will be effected adversely by the project..pdf
39
Whather project area is a part of National Park or sanctuary and airal distance of the project from National Park or sanctuary signed by DFO.pdf
40
Colored copy of the Geo referenced showing the land identified for CA
41
Survey of India Toposheet in 1 50 000 scale indicating location of the land identified for creation of Compensatory Afforestation
42
Copy of Mou agreement executed between the Present owner and the User Agency
43
Full File
44
objections remove letter
45
objections remove letter 16-03-2018
46
upload the resolved letter of objection received by Nodal office
47
objections remove letter 25-07-2018
48
objections remove letter, Dated 11-Sep-18
49
objections remove letter, Dated 08-Oct-2018