FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/ROAD/20119/2016
(ii). Name of Project for which Forest Land is required :
Const of Pastorawar motor road from Km 10 of S.D.D.S.M motor road
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
A new road of 9.00 km long is sanction vide Uttarakhand Govt order no 4089/III(2)/15-23(Pra.Aa.)/2013 dated 16-05-2015. The cost of the project for stage-I work is Rs 52.65 Lac. As per approved alignment of the road the actual length of this road is 7.85 Km. This road will provide road connectivity
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Road
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
52.65
(viii). Area of forest land proposed for diversion(in ha.):
2.205
(ix). Non-forest land required for this project(in ha.):
4.9296
(x). Total period for which the forest land is proposed to be diverted(in years):
200
A-2.
Details of User Agency
(i). Name :
EXECUTIVE ENGINEER
(ii). Address1 :
Provincial Division P.W.D., Ranikhet
(iii). Address2 :
Mall Raod Ranikhet
(iv). State :
Uttarakhand
(v). District :
Almora
(vi). Pin :
263645
(vii). Landmark :
NIL
(viii). Email address :
eepdrani@yahoo.com
(ix). Landline Telephone No. :
5966-220679
(x). Fax No. :
NIL
(xi). Mobile No. :
7500540231
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Lalit
(ii). Middle Name:
Kumar
(iii). Last Name:
Goel
(iv). Gender:
Male
(v). Designation:
Executive Engineer
(vi). Address 1:
Provincial Division PWD, Ranikhet
(vii). Address 2:
Mall Road Ranikhet
(viii). State:
Uttarakhand
(ix). District:
Almora
(x). Tehsil:
NIL
(xi). Pin:
263645
(xii). Landmark:
Ranikhet
(xiii). Email Address:
eepdrani@yahoo.com
(xiv). Landline Telephone No.:
5966-220679
(xv). Fax No.:
05966220679
(xvi). Mobile No.:
9412919971
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
1
Approved
FP/UK/ROAD/19725/2016
8B/UCP/06/173/2016/FC/1953
2.16
2.16
29 Dec 2016
21 Feb 2018
Total
2.16
2.16
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Almora
2.205
4.9296
Total
2.205
4.9296
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Almora
2.205
4.9296
Total
2.205
4.9296
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Pastorapar
1.0575
0.8186
2
Saitana
0.6525
0.2475
3
Pastorawaar
0.495
1.305
4
Raili Byali
0
2.5584
Total
2.205
4.9295
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
For Road work Km 1 to 7.85
2.205
4.86
2
For Muck Dumping Yard 1 to 3
0
0.0695
Total
2.205
4.9295
C.
Maps of forest land proposed to be diverted
Division 1. : Almora
(i). Area of forest land proposed to be diverted(in ha.) :
2.205
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
2.205
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
3
(iii). Temporary Employment(Number of person-days):
4300
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
One
District 1. : Almora
(a). Village:
Asgoli
(b). Area(in ha.):
4.41
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
1257, 1333, 400, 450 and 450M
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No
Documents
Remarks
1
A short narrative and importance of the project.
2
Administrative and financial approval
3
Preliminary joint inspection report
4
Comparative chart
5
Certificate from the DM that no alternative suitable non-forest land is available for the project.
6
Land Schedule
7
Category wise road length, width and area in Hac.
8
Bar chart with index
9
Compensatory afforestation scheme.
10
Certificate regarding suitability of identified land for CA
11
Undertaking by the user agency to bear the cost of compensatory afforestation.
12
Road side / gap filling plantation estimate.
13
Undertaking by the user agency to bear the cost of road side/ gap plantation
14
Details of trees with their scientific names
15
Certificate regarding felling of oak trees.
16
Certificate regarding felling minimum trees during the project.
17
Muck disposal scheme in prescribed formate
18
Weather project area is a part of National park or sanctuary and arial distance of the project from National park or sanctuary park.
19
No violation has taken place F.C. Act 1980.
20
NOC from local Gram sabhas.
21
Certificate regarding work has not been started.
22
Geologist Report
23
Task force report
24
Manak shartain
25
Certificate by the user agency for complying the condition imposed in Manak shartain
26
Certificate by the user agency for complying the condition imposed in geologist report/ Task force recommendation in hill area.
27
No historical/ monumental or religious place will be effected certificate.
28
Undertaking regarding no animal will be effected adversely by the project.
29
Undertaking to provide alternative fuelwood, kerosene or LPG to labours involved in project
30
Benefited villages/ families
31
NPV calculation certificate
32
Undertaking of payment of NPV if Hon'ble supreme court increase the rates of NPV
33
Cost of forest Land
34
Undertaking by the user agency to bear the cost of demarcation work
35
Check list/ Fact sheet/ Main attachments/ Additional attachments.
36
Part-I
37
Part-II to V
38
Reply on objection raised by DFO letter No Memo/12-1(2) dt 06-08-16, vide this office letter No 2324/36C dated 15-09-2016
39
Reply on objection raised by DFO letter No Memo/12-1(2) dt 04-11-16, vide this office letter No 2629/36C dated 05-11-2016
40
Reply on objection raised by DFO letter No Memo/12-1(2) dt 05-12-16, vide this office letter No 2962/36C dated 21-12-2016
41
Reply on same objection raised by nodal office vide DFO letter No Memo/ 12-1(2) dated 24-01-2017
42
reply on objection raised by DFO letter No Memo/ 12-1(2) dated 21-02-2017 vide this office letter No 360/36C dated 25-02-2017
43
Point wise reply on objection raised vide DFO office letter No Memo/12-1(2) dated 24-04-2017 by this office letter No 1006/36C dated 18-05-2017