FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/UK/ROAD/10965/2015   (ii). Name of Project for which Forest Land is required : New Construction Of Thela Tharti Chirbitiya Motor Road   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Length of the proposed alignment is 6.75 km which is technically and geologically fit .the proposed alignment contains 5 HP bends and effects the minimum reserve forest area and minimum oak trees .presently the distance between THATHI TO CHIRBATIA is approximately 30kms and after the construction of   (iv). State : Uttarakhand   (v). Category of the Proposal : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 380   (viii). Area of forest land proposed for diversion(in ha.): 4.357   (ix). Non-forest land required for this project(in ha.): 0.472   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : PUBLIC WORKS DEPARTMENT GHANSALI   (ii). Address1 : OFFICE OF EXECUTIVE ENGINEER TEMP. DIV. PWD GHANSALI UTTRAKHAND   (iii). Address2 : NIL   (iv). State : Uttarakhand   (v). District : Tehri Garhwal   (vi). Pin : 249155   (vii). Landmark : NIL   (viii). Email address : eepwdghansali@rediffmail.com   (ix). Landline Telephone No. : 1379-258327   (x). Fax No. : 1379-1379   (xi). Mobile No. : 7533944842   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: BIRENDRA   (ii). Middle Name: SINGH   (iii). Last Name: BASERA   (iv). Gender: Male   (v). Designation: ASST.ENGINEER   (vi). Address 1: C/O EXECUTIVE ENGINEER TEMP. DIV PWD GHANSALI, TEHRI GARHWAL, UTTARAKHAND   (vii). Address 2: NIL   (viii). State: Uttarakhand   (ix). District: Tehri Garhwal   (x). Tehsil: NIL   (xi). Pin: 249155   (xii). Landmark: NIL   (xiii). Email Address: eepwdghansali@rediffmail.com   (xiv). Landline Telephone No.: 1379-258327   (xv). Fax No.: 01379258327   (xvi). Mobile No.: 9012475006   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1Under Processing at State GovernmentFP/UK/ROAD/47739/20201.0850
Total 1.085 0
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Tehri,New Tehri4.3570.472
Total4.3570.472
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Tehri Garhwal4.3570.472
Total4.3570.472
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Tharti4.3570.472
Total 4.357 0.472
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1tharti 6b,7a4.3570.472
Total 4.357 0.472
C. Maps of forest land proposed to be diverted
Division 1. : Tehri,New Tehri
  (i). Area of forest land proposed to be diverted(in ha.) : 4.357   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.4.357    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 2   (iii). Temporary Employment(Number of person-days): 250
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Yes   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii). No. of districts involved for raising Compensatory Afforestation: 1   (iv). No. of patches: Five
District 1. : Tehri Garhwal
  (a). Village: tharti   (b). Area(in ha.): 8.715   (c). Copy of KML file of the patch:     View File   (d). Khasra details: 1812,1820,1906,1932,1531,1771,1801,1810,1643,1896,1893,1898,2261,1894,2272,2315   (e). Present owner: Others   (f). Copy of ownership proof:   (g). Copy of Mou/agreement executed between the Present owner and the User Agency:   (h). Copy of non encumberence certificate for the forest land:
  (v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:   (vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No Documents
Remarks
1A short narrative and importance of the project
2Administrative and Financial sanction
3Preliminary Joint Inspection report (by user agency, Forestdepartment, revenue department
4Comparative chart showing statement of both alignment and alternate site explored for the proposed project and reason for their rejection duly countersigned by DfO
5Certificate from the DM that no alternative suitable non-forest land is available for project in question and the demand of the forest land for the project is barest minimum
6Land schedule (for RF signed by DFO and civil soyam, Van panchayat and privet nap land, Notified forest land
7Category wise (RF,civil soyam,Van panchayat and privet nap land, Notified forest land etc.) land length, width and area in Ha
8Bar chart
9Compensatory afforestation scheme in Civil and Soyam land (10 years) by DFO
10Certificate regarding suitability of identified land for Compensatory Afforestation by DFO
11Undertaking by the user agency to bear the cost of compensatory afforestation duly counter signed by the DFO
12Road side/gap filling plantation estimate
13Details of the tree with their scientific name in RF.Civil Soyam ,Van panchayat ,Privet Land should be mentioned (with valuation of the trees to be filled)(0-10 dia trees will be mentioned as saplings).(pdf file)
14Felling of Oak Trees (if involves, inspection report of the concerning CF has to be provided
15If felling of tree is not involved, certificate by DFO in this regard
16Certificate of felling minimum trees during the project work
17Muck disposal scheme
18WatherProject area Is not Part Of National Park Or Sanctuary And Arial Distance Of The Project From National Park Or Sanctuary Singed By DFO
19In The Project Area Is Within 10 K.M Radios Of N/P Or Centuary Comments/No Objection Certificate Of CCE Wild Life Has To Be Provided
20In The Project Falling Within The National Park Or Centaury ,Needs Recommendation Of State Wild Life Board Of wild Life(NBWL) And Permission Of Hon Ble Supreme Court
21No Violation Has Taken Place,FC Act 1980 Reg
22Noc From Local Gram Sabha’s
23Component Wise Details Of Construction Work
24Certificate Work Has Not Been Started Reg.(
25Geologist report
26Task Force Certificate
27Certificate By user Agency For Complying The Condition Imposed In Standard Condition
28Certificate By User Agency For Complying The Condition Imposed In Geologist Report/Task Force Recommendation In Hill Areas(Excluding Drinking Water)
29No Historical / Monumental Or Religious Place Will Be Effected Certificate
30Under The Provide Alternative Fuel wood, Kerosene Or LPg To Labors Involved In Project
31Benefited Village/Families/Population
32NPV Calculation Certificate As Per Hon’bleSupreme Court/MOEF Orders By DFO
33Undertaking Of Payment Of NPV If Hon’ble Supreme Court Increase The Rates Of NPV
34Cost Of Forest Land And Lease Rent Certificate By DM
35Certificate Br Lease Period By user A Agency
36Demarcation Of Land To Be Diverted,Undertaking Of User Agency To Bear The Cost Of Demarcation Work
37Fact Sheet
38justification for the inquiry made by nodal officer.
39Query have removed as per direction received.
40Query have removed as per direction received
41Quarry have removed as per direction received.
42The correction have been made as per the instruction received
43Geo reference map of Road & CA
44Rechecking letter
45The correction have been made as per the instruction received
46Reply of EDS
47REply of EDS 30/05/2018