FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/Others/43838/2020
(ii). Name of Project for which Forest Land is required :
Mussoorie Sewerage Scheme(Camel back Zone STP)
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Construction of Sewage treatment plant on forest land due to no other proper land is available as per topographical , To maintain the proper slope and smooth flow of sewer the forest land is selected ..
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Others
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
6173
(viii). Area of forest land proposed for diversion(in ha.):
0.165
(ix). Non-forest land required for this project(in ha.):
0
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
CONSTRUCTION DIVISION UTTARAKHAND PEYJAL NIGAM MUSSOORIE
(ii). Address1 :
Kutumb vihar Sinaula Dehradun.
(iii). Address2 :
NIL
(iv). State :
Uttarakhand
(v). District :
Dehradun
(vi). Pin :
248001
(vii). Landmark :
NIL
(viii). Email address :
jalnigam.forestmussoorie@gmail.com
(ix). Landline Telephone No. :
135-2736032
(x). Fax No. :
135-
(xi). Mobile No. :
8439107648
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State PSU
A-3.
Details of Person Making Application
(i). First Name:
kamal
(ii). Middle Name:
kishore
(iii). Last Name:
Lingwal
(iv). Gender:
Male
(v). Designation:
AAE
(vi). Address 1:
Kutumb Vihar sinaula, Dehradun.
(vii). Address 2:
NIL
(viii). State:
Uttarakhand
(ix). District:
Dehradun
(x). Tehsil:
Dehradun
(xi). Pin:
248001
(xii). Landmark:
NIL
(xiii). Email Address:
jalnigam.forestmussoorie@gmail.com
(xiv). Landline Telephone No.:
135-2736032
(xv). Fax No.:
NIL
(xvi). Mobile No.:
7017383710
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Mussoorie
0.165
0
Total
0.165
0
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Dehradun
0.165
0
Total
0.165
0
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Mussoorie town
0.165
0
Total
0.165
0
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
STP
0.03
0
2
Approach road
0.135
0
Total
0.165
0
C.
Maps of forest land proposed to be diverted
Division 1. : Mussoorie
(i). Area of forest land proposed to be diverted(in ha.) :
0.165
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
One
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
0.165
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
0
(iii). Temporary Employment(Number of person-days):
25000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
Yes
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
administrative and financial approval
2
Part-1
3
Part-II
4
Part-III
5
Part-IV
6
Part-V
7
Land schedule
8
National park and wild life century
9
Bar chart
10
Plantation certificate
11
10 times of trees affected
12
NOC of angar palika parishad
13
Cencelelation of alternate alignment
14
Work not started
15
Geologist report
16
Geologist and District task force reccomandations
17
No loss of wild life
18
No alternate land availability certificate
19
No religious , ancient , historical place
20
amount will deposited double of forest land
21
Beneficial population certificate
22
Pollution control board certificate
23
Forest ;land cost certificate
24
NPV certifiocate
25
Not specific place
26
Topo sheet
27
Disposal of waste
28
Demarcation pillars
29
Lease period
30
estimated cost
31
Layout plan
32
FRA-2006 Camel Back
33
Wild life approval
34
Objection Removal
35
Justification
36
Authority letter
37
Joint Inspection Camel back zone
38
Letter
39
Layout plan
40
Financial approval Validity
41
Geo-reference map.
42
Objection removal Sheet
43
9 Tree effected
44
B-1, Details of Proposal seeking prior approval of Central Government under the Act for diversion of forest land for the project already submitted in the past.
45
Objection removal letter no 2112/FP/UK/otheres/43838/2020 dt 04.03.2022
46
Fact sheet camel back zone
47
Short Note (Prativadan)
48
Objection Removal 1.2.22
49
पर्यावरणीय स्वीकृति हेतु उत्तराखण्ड प्रदूषण नियंत्रण बोर्ड से अनापत्ति प्राप्त करने हेतु आवेदन कर लिया गया।
50
जल श्रोत प्रभावित न होने का प्रमाण पत्र
51
FRA 2006 of camel back
52
Certificate of non-availability of other alternative land
53
justification camel back zone
54
मलवा निस्तारण certificate
55
EDS