FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/IRRIG/8805/2014
(ii). Name of Project for which Forest Land is required :
Construction of Siyagad Canal
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Construction of Siyagad Canal Irrigation of Khod, Dangi, Bhunal, Baksir, Math
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Irrigation
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
415.47
(viii). Area of forest land proposed for diversion(in ha.):
0.231
(ix). Non-forest land required for this project(in ha.):
0.255
(x). Total period for which the forest land is proposed to be diverted(in years):
2
A-2.
Details of User Agency
(i). Name :
UTTARAKHAND IRRIGATION DEPARTMENT
(ii). Address1 :
Executive Engineer, Irrigation Division Belani Rudraprayag
(iii). Address2 :
NIL
(iv). State :
Uttarakhand
(v). District :
Rudraprayag
(vi). Pin :
246171
(vii). Landmark :
Rudraprayag
(viii). Email address :
exenrudraprayag@gmail.com
(ix). Landline Telephone No. :
1364-233222
(x). Fax No. :
1364-233222
(xi). Mobile No. :
9536303239
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Shailendra
(ii). Middle Name:
Kumar
(iii). Last Name:
Basliyal
(iv). Gender:
Male
(v). Designation:
executive engineer
(vi). Address 1:
Irrigation Division Belani Rudraprayag
(vii). Address 2:
Irrigation Division Belani Rudraprayag
(viii). State:
Uttarakhand
(ix). District:
Rudraprayag
(x). Tehsil:
Rudraprayag
(xi). Pin:
246171
(xii). Landmark:
Rudraprayag
(xiii). Email Address:
skbasliyal@gmail.com
(xiv). Landline Telephone No.:
1364-233222
(xv). Fax No.:
01364233222
(xvi). Mobile No.:
9411170054
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Rudraprayag
0.231
0.255
Total
0.231
0.255
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Rudraprayag
0.231
0.255
Total
0.231
0.255
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
khod,dangi,Baksir,Bhunal,Math Gaon
0.231
0.255
Total
0.231
0.255
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Canal
0.231
0.255
Total
0.231
0.255
C.
Maps of forest land proposed to be diverted
Division 1. : Rudraprayag
(i). Area of forest land proposed to be diverted(in ha.) :
0.231
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.231
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
No Data
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
No Data
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
No
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
00
(ii). Total command area of the Project(in ha.):
175
Additional information Details
Documents
S.No
Documents
Remarks
1
Site inspaction note below the rank of DCF
2
Joint Inspection Report Certificate
3
Land schedule of affected forest Land
4
National Park/Wildlife Sanctuary certificate
5
Certificate of Gram Sabha
6
Project length-width certificate
7
The project work has not started certificate
8
Geological report
9
Geological /District Task Force to comply with the recommendations certificate.
10
certificate to not damage Wildlife / vegetation
11
certificate of Absence of any alternative land and land minimum demand
12
Certificate of the Site not Religious / mythological / historical significance
13
Certificate in relation to Beneficiary villages / families /population
14
Certificates of deposit to be amount of damage plantation
15
Certificate in respect of Obtaining environmental clearance certificate
16
Certificate of the value of a reserved forest land
17
Standard Terms valid certificate
18
Estimates demarcation of RCC pillron and certificate of payble amount
19
certificate of Lease period
20
Catchment Treatment Plan for water electric project
21
Other information related to the project
22
Use of explosives certificate
23
certificate provided by Magistrate
24
Under Forest Rights Act no claims are pending in forest land
25
Form-1 Government of Office of the District Collector To whowsoever it may concern
26
Proceeding of the meeting of the district level committee constitude under shedule tribes & other traditional forest
27
Proceeding of the meeting of the district level committee constitude under shedule tribes & other traditional forest Dwellers (recognition of rights) act (FRA).2006
28
under shedule tribes & other traditional forest Dwellers act 2006
29
NOC under the Forest Rights Act, 2006 vill-Mathya Gaon Tahsil-Jakholi Rudraprayag
30
Form-23.1 Gram Panchayat- Mathya Gaon
31
NOC under the Forest Rights Act, 2006 vill-Dangi Tahsil-Jakholi Rudraprayag
32
Form-23.1 Gram Panchayat- Dangi
33
NOC under the Forest Rights Act, 2006 vill-Bhunal Gaon Tahsil-Jakholi Rudraprayag
34
Form-23.1 Gram Panchayat- Bhunal Gaon Jakholi Rudraprayag
35
NOC under the Forest Rights Act, 2006 vill-Khod Tahsil-Jakholi Rudraprayag
36
Form-23.1 Gram Panchayat- Khod Rudraprayag
37
NOC under the Forest Rights Act, 2006 vill-Basir,Tahsil-Jakholi Rudraprayag
38
Form-23.1 Gram Panchayat- Baksir Rudraprayag
39
Estimates demarcation of RCC pillron and certificate of payble amount
40
Mag Disposal
41
Compartment Area
42
Reservations Wildland Transfer Proposal
43
NOC
44
Sanction letter
45
Sanction list
Print