FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/UK/HYD/42080/2019
(ii). Name of Project for which Forest Land is required :
Tankul 12 MW Small Hydro Project
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Tankul 12 MW Small Hydro Project (run of the river) is being developed by UJVN Ltd. (A Govt. of Uttarakhand Enterprises) The proposed project is located on Simkhola Gad, a stributary of Kali River in Tehsil Dharchula, District-Pithoragarh of Uttarakhand state. Project will produce 70.72 Million Unit
(iv). State :
Uttarakhand
(v). Category of the Proposal :
Hydel
(vi). Shape of forest land proposed to be diverted :
Non Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
11842.76
(viii). Area of forest land proposed for diversion(in ha.):
9.397
(ix). Non-forest land required for this project(in ha.):
0.839
(x). Total period for which the forest land is proposed to be diverted(in years):
30
A-2.
Details of User Agency
(i). Name :
UJVN LIMITED (A GOVT. OF UTTARAKHAND ENTERPRISE)
(ii). Address1 :
Dy General Manager (E&M - SHP), UJVN Ltd, Cantt Road, Jakhani Pithoragarh.
(iii). Address2 :
NIL
(iv). State :
Uttarakhand
(v). District :
Pithoragarh
(vi). Pin :
262501
(vii). Landmark :
Pithoragarh
(viii). Email address :
ucjoshi2@gmail.com
(ix). Landline Telephone No. :
5964-228608
(x). Fax No. :
5964-228608
(xi). Mobile No. :
9456590519
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Umesh
(ii). Middle Name:
Chandra
(iii). Last Name:
Joshi
(iv). Gender:
Male
(v). Designation:
Assistant Engineer
(vi). Address 1:
Dy. General Manager (E&M- SHP) UJVN Ltd, Cantt Road, Jakhani, Pithoragarh.
(vii). Address 2:
NIL
(viii). State:
Uttarakhand
(ix). District:
Pithoragarh
(x). Tehsil:
Pithoragarh
(xi). Pin:
262501
(xii). Landmark:
Pithoragarh
(xiii). Email Address:
ucjoshi2@gmail.com
(xiv). Landline Telephone No.:
5964-228608
(xv). Fax No.:
05964228608
(xvi). Mobile No.:
9456590519
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Pithoragarh
9.397
0.839
Total
9.397
0.839
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Pithoragarh
9.397
0.839
Total
9.397
0.839
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Bung Bung
4.676
0.27
2
Tankul
4.721
0.569
Total
9.397
0.839
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Protection of head works
0.09
0
2
Intake
0.04
0
3
Intake Channel ( Feeder Channel)
0.06
0
4
Deselting Tank
1.25
0
5
Power Pipe with tunnel
2.25
0.2
6
Surge Tank
0.023
0
7
Penstoke ( single)
0.385
0
8
Penstoke ( Double)
0.28
0.02
9
Penstoke ( four)
0.6
0.275
10
Power House
0.2
0.04
11
Tail race channel
0.015
0.003
12
Switch yard
0.1
0.025
13
Muck Disposal Near weir side
0.02
0
14
Muck disposal at foreway side
0.02
0
15
Muck disposal at Power house
0.04
0
16
Quiary Site
0.2
0
17
Approach road in project site
3
0
18
Project Camp Building
0.224
0.276
19
Head works
0.6
0
Total
9.397
0.839
C.
Maps of forest land proposed to be diverted
Division 1. : Pithoragarh
(i). Area of forest land proposed to be diverted(in ha.) :
9.397
(ii). Nature of the Project:
Non Linear
(a). No. of patches :
One
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
9.397
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
20
(iii). Temporary Employment(Number of person-days):
374125
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
Five
District 1. : Pithoragarh
(a). Village:
Bung Bung
(b). Area(in ha.):
5.984
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
43, 55
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
District 2. : Pithoragarh
(a). Village:
Bung Bung
(b). Area(in ha.):
1.265
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
43, 55
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
District 3. : Pithoragarh
(a). Village:
Bung Bung
(b). Area(in ha.):
1.872
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
43, 55
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
District 4. : Pithoragarh
(a). Village:
Bung Bung
(b). Area(in ha.):
4.673
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
43, 55
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
District 5. : Pithoragarh
(a). Village:
Sirdang
(b). Area(in ha.):
5
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
4671, 6201, 6216
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
12
(ii). Total command area of the Project(in ha.):
146.75
(a). Copy of the approval of competent authority to the Catchment Area Treatment Plan (CAT Plan):
(b). Copy of the approved CAT plan:
Additional information Details
Documents
S.No
Documents
Remarks
1
Authority letter
2
justification
3
land schedule
4
NPV Certificate
5
RCC demarcation
6
Van Bhomi ka Mulya
7
No animal effected
8
work not start
9
CAT Plan MoM-29-08-2019
10
layoutplan2
11
layoutplan4
12
Part 1 to 5
13
Man_power_calculation for generation employment
14
Environmental Flow
15
76_Bord meeting
16
Revised_FRA 2006
17
Revised_muck_disposal_plan
18
Non Encumbrance
19
Estimate CA 5 Hac
20
Geologist_task force
21
complying geologist_task force
22
CA_Toposheet
23
CA_Geomap
24
Task force certi
25
Revised_length and width
26
Revised_geologist report
27
FRL_Certificate by DFO
28
TEC
29
Mou-agreement
30
CA Toposheet
31
Mou-agreement
32
Mou_agreement
33
CA Toposheet
34
78_Board_meeting
35
Arial distance map
36
arial distance certificate
37
EDS query reply letter
38
CA scheme 13.794ha
39
Guidlines_DPR_(Signed)
40
Letter to Forest dated 06-10-2020
41
khasra detail 5 ha
42
geo_map_new revised
43
Revised_CA_Estimate_of_5ha Sirdang civil
44
Toposheet map new_revised_CA
45
Tankul observation answer letter dated 31-12-20
46
RO observations dt 31-12-2020
47
48
Observation reply dated 28-04-2021
49
Revised Muck Disposal Calculation dated 28-04-2021
50
Admin Approval dated 28-04-2021
51
Lease rent order dated 28-04-2021
52
Reply to DFO dt 09-07-2021
53
Loop in Loop out diagram dt 09-07-2021
54
UERC regulation dt 09-07-2021
55
Letters UPCL dt 09-07-2021
56
Tankul Observation Answer Later Dated 12-08-2021
57
58
Letter To Quarry Answer Dated 28-10-2021
59
Letter To Administrative Approval Dated 28-10-2021
60
Letter To Muck Disposal Plan Dated 28-10-2021
61
63rd REC Meeting Observation Reply On Dated 20-01-2022
Print