FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/RJ/TRANS/43798/2020
(ii). Name of Project for which Forest Land is required :
Construction of 11 kv Transmission Line for Rural Electrification of Bera Sukh Sagar to Village Sand Mangra, Khejdi Ka Bala,Lakha ka Khet, Tehsil-Sojat,District Pali (Raj)
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
“Construction of 11 kv Transmission Line for Rural Electrification of Bera Sukh Sagar to Village Sand Mangra, Khejdi Ka Bala,Lakha ka Khet, Tehsil-Sojat,District Pali (Raj)” TOTAL ROUTE LENTH 11.174 KM
(iv). State :
Rajasthan
(v). Category of the Proposal :
Transmission Line
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
57.96
(viii). Area of forest land proposed for diversion(in ha.):
0.8491
(ix). Non-forest land required for this project(in ha.):
6.9727
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
JODHPUR VIDHYUT VITRAN NIGAM LTD
(ii). Address1 :
NEW POWER HOUSE,INDUSTRIAL AREA,JODHPUR- RAJASTHAN
(iii). Address2 :
NIL
(iv). State :
Rajasthan
(v). District :
Jodhpur
(vi). Pin :
342003
(vii). Landmark :
KANKOODEEP GARDEN
(viii). Email address :
aensojatroad1991@gmail.com
(ix). Landline Telephone No. :
291-2651200
(x). Fax No. :
291-2741870
(xi). Mobile No. :
9413359319
(xii). Website (if any) :
nil
(xiii). Legal status of User Agency :
State PSU
A-3.
Details of Person Making Application
(i). First Name:
SHIVKESH
(ii). Middle Name:
NIL
(iii). Last Name:
JAREDA
(iv). Gender:
Male
(v). Designation:
ASSISTANT ENGINEER (O&M)
(vi). Address 1:
OFFICE OF THE ASSISTANT ENGINEER (O&M),JODHPUR VIDHYUT VITRAN NIGAM LIMITED,SOJAT ROAD ,
(vii). Address 2:
NIL
(viii). State:
Rajasthan
(ix). District:
Pali
(x). Tehsil:
Sojat
(xi). Pin:
306103
(xii). Landmark:
NIL
(xiii). Email Address:
aensojatroad1991@gmail.com
(xiv). Landline Telephone No.:
2960-230399
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9413359319
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
1
Inprinciple
FP/RJ/TRANS/13198/2014
F.1(7)FOREST/2016
0.192
0.192
26 Oct 2015
2
Inprinciple
FP/RJ/TRANS/14545/2015
F.1(92)FOREST/2015
0.5613
0.5613
04 Nov 2015
3
Under Processing in NBWL
FP/RJ/719/2016
FP/RJ/719/2016
0.07
0.07
Total
0.8233
0.8233
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Rajsamand Wildlife
0.8491
6.9727
Total
0.8491
6.9727
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Pali
0.8491
6.9727
Total
0.8491
6.9727
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
LAKHAKHET
0
1.4315
2
KHODIYA
0.5131
0.2506
3
SAND MANGRA
0
3.9522
4
KHEJRI KA BALA
0.336
1.3384
Total
0.8491
6.9727
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
11 KV TRANSMISSION LINE
0.8491
6.9727
Total
0.8491
6.9727
C.
Maps of forest land proposed to be diverted
Division 1. : Rajsamand Wildlife
(i). Area of forest land proposed to be diverted(in ha.) :
0.8491
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Three
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.3374
View File
2.
0.1757
View File
3.
0.336
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
4
(iii). Temporary Employment(Number of person-days):
600
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
Yes
(a). Whether Project or a part thereof is located within a Protected Area ? :
Yes
(b). Status of approval of the Supreme Court :
Application yet to b
(ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project :
Application yet to be submitted
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
Authorized Letter for forest clearance
2
ADMINISTRATIVE SANCTION
3
JUSTIFICATION FOR LOCATING THE PROJECT
4
UNDERTAKING FOR CONSERVATION OF FLORA-FAUNA DURING CONSTRUCTION OF 11 KV TRANSMISSION LINE
5
UNDERTAKING FOR FRA CERTIFICATE
6
UNDERTAKING FOR MEDICIANAL PLANTS
7
UNDERTAKING FOR MUCK DISPOSAL
8
UNDERTAKING FOR NO CHANGES IN STATUTORY POSITION OF DIVERTED
9
UNDERTAKING FOR NO OTHER FEASIBLE ALTERNATIVE & DIVERSION OF MINIMUM FOREST LAND
10
UNDERTAKING FOR PAYMENT OF ANY OTHER COST
11
UNDERTAKING FOR TWO TIME DEGRADED FOREST LAND
12
UNDERTAKING FOR USE OF ANY MATERIAL FROM SURROUNDED FOREST LAND DURING 11 KV TRANSMISSION LINE
13
UNDERTAKING FOR USE OF FOREST LAND
14
UNDERTAKING FOR WASTE MANAGEMENT DURING
15
Employment Justification 11 KV
16
TECHNICAL SANCTION
17
GRAM PANCHYAT NOC
18
JAMABANDI COPY
19
Sarpanch Noc
20
SLD MAP
21
BAR CHART
22
CERTIFICATE FOR MINIMUM USE OF FOREST LAND
23
UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
24
UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
25
Village Wise area calculation sheet Final-05-12-2018
26
GEO-REFERENCED SURVEY OF INDIA TOPOSHEET WITH WILDLIFE SANCUTARY AND PROPOSED 11 KV TRANSMISSION LINE ROUTE ALIGNMENT SCALE 1 : 50,000
27
GEO-REFERENCED DIGITAL MAP REQUIRED FORESTLAND COORDINATE AND WILDLIFE SANCUTARY AND PROPOSED 11 KV TRANSMISSION LINE ROUTE ALIGNMENT scale 1 :4000
28
GEO -REFERENCED KHASRA MAP SUPER IMPOSED 11 KV TRANSMISSION LINE
29
EDS REPLY -13-07-2020
30
COMPARATIVE STATEMENT OF ALTERNATIVE ROUTE
31
EDS Reply-08-09-2021
32
Alternative Route Map
33
Khasra Wise Area Calculation Sheet
Print