A-1. Project Details
  (i). Proposal No. : FP/RJ/TRANS/28622/2017   (ii). Name of Project for which Forest Land is required : Babai (RRPVNL) - Bhiwani (PG) 400kV D/C Transmission Line   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The project is initiated by ministry of Power, Govt. of India under “system strengthening scheme in northern region (NRSSXXXVI) along with LILO of sikar-Neemrana 400kV D/C line at Babai (RRVPNL)”. The necessary approvals from Ministry of power have been received for the construction of the above tra   (iv). State : Rajasthan   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 11000   (viii). Area of forest land proposed for diversion(in ha.): 13.015   (ix). Non-forest land required for this project(in ha.): 243.578   (x). Total period for which the forest land is proposed to be diverted(in years): 35
A-2. Details of User Agency
  (i). Name : NRSS XXXVI TRANSMISSION LIMITED   (ii). Address1 : Shatabdi Bhawan, B 12 & 13, Sector 4, Noida   (iii). Address2 : NIL   (iv). State : Uttar Pradesh   (v). District : Gautam Buddha Nagar   (vi). Pin : 201301   (vii). Landmark : NIL   (viii). Email address : sect.nrss@gmail.com   (ix). Landline Telephone No. : -1-   (x). Fax No. : -1-   (xi). Mobile No. : 7042053497   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Private
A-3. Details of Person Making Application
  (i). First Name: Shashank Takawale   (ii). Middle Name: NIL   (iii). Last Name: NIL   (iv). Gender: NIL   (v). Designation: Head PMU   (vi). Address 1: NRSS XXXVI TRANSMISSION LIMITED, TATA Power Company Limited, Shatabdi Bhawan, B 12 & 13, Sector 4, Noida   (vii). Address 2: NIL   (viii). State: Tamil Nadu   (ix). District: Anantapur   (x). Tehsil: NIL   (xi). Pin: 201301   (xii). Landmark: NIL   (xiii). Email Address: sect.nrss@gmail.com   (xiv). Landline Telephone No.: 0-   (xv). Fax No.: NIL   (xvi). Mobile No.: 7042053497   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Jhunjhunu Territorial13.015243.578
Total13.015243.578
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.jhunjhunu13.015243.578
Total13.015243.578
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Sardarpura05.428
2Babai (CT)00.644
3Pratappura09.108
4Gadrata5.5632.349
5Pupurana7.08535.051
6Badalwas0.36716.377
7Tyonda019.285
8Dada Fatehpura08.372
9Nalpur07.912
10Gorir06.532
11Doodhwa Nangliya09.488
12Kakrai04.324
13Rawan07.82
14Ganeshpura04.048
15Balaha Khurd (147)06.072
16Balaha Kalan07.636
17Nawta05.796
18Pacheri kalan011.34
19Rasoolpur07.728
20Santor09.408
21Bamanwas06.716
22Panthorli03.036
23Ghaseda09.684
24Udamandi06.544
25Nimbas06.176
26Nanwas06.44
27kuhadwas06.9
28Jaitpur03.128
29Dalenwas010.236
Total 13.015 243.578
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Construction of Transmission Line13.0149962243.5779994
Total 13.0149962 243.5779994
C. Maps of forest land proposed to be diverted
Division 1. : Jhunjhunu Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 13.015   (ii). Nature of the Project: Linear   (b). No. of Segments : Seven
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.5.563    View File
2.0.376    View File
3.6.709    View File
4.0.12    View File
5.0.034    View File
6.0.08    View File
7.0.133    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 10   (iii). Temporary Employment(Number of person-days): 164250
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : Yes   (a). Whether Project or a part thereof is located within a Protected Area ? : Yes   (b). Status of approval of the Supreme Court : Application yet to b   (ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project : Application under process   (a). Date of submission of proposals : 16 Feb 2018   (b). Current status : NIL
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: No   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii) . Reason for not providing Non-Forest Land: For laying of transmission lines
Additional information Details
Documents
S.No Documents
Remarks
1Gazette publication by Ministry of Power, Govt. Of India
2Letter of Intent - project award
3Sec-68 approval from CEA
4Cost Benefit analysis not required as area is below 20Ha
5EDS reply
6No Other Alternate Route
7layout of line
8Environment Clearance not required
9Rehabilitation not required
10undertaking for Muck Disposal
11Employee Structure as per EDS
12Gadrata Village Map AP3 to AP4
13Reply to EDS II raised on dated 06/10/2017
14coordinates of tower located in forest and non forest area
15Reply to EDS dated 06/11/2017
16Detail note on project
17Land schedule
18Land schedule for non forest
19Minimum use of forest land
20No other alternative available
21undertaking for NPV
22undertaking for FRA
23undertaking for CA
24Gadrata village Jamabandi
25Pupurna village Jamabandi
26Badalwas village Jamabandi
27Badalwas village map
28Pupurna village map
29Bar Chart
30Reply to EDS raised by DFO dated 12-12-2017
31Compliance report dated 20/02/2018
32undertaking for installating indolite Bird flight Diverters on transmission line conductors to save birds against collision & electrocution.