FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/RJ/TRANS/149957/2021
(ii). Name of Project for which Forest Land is required :
“Construction of 400 KV D/C Quad Bikaner(PG) to Bikaner II (PS) Transmission line
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
“Construction of 400 KV D/C Quad Bikaner(PG) to Bikaner II (PS) Transmission line Length 32.547km
(iv). State :
Rajasthan
(v). Category of the Proposal :
Transmission Line
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
20000
(viii). Area of forest land proposed for diversion(in ha.):
0.8142
(ix). Non-forest land required for this project(in ha.):
148.902
(x). Total period for which the forest land is proposed to be diverted(in years):
50
A-2.
Details of User Agency
(i). Name :
POWER GRID CORPORATION OF INDIA LTD ,BIKANER
(ii). Address1 :
POWERGRID CORPORATION OF INDIA LIMITED,B-129 ,Kanta Khaturia Colony,Bikaner
(iii). Address2 :
NIL
(iv). State :
Rajasthan
(v). District :
Bikaner
(vi). Pin :
334003
(vii). Landmark :
NIL
(viii). Email address :
bchouhan@powergrid.in
(ix). Landline Telephone No. :
0-
(x). Fax No. :
0-
(xi). Mobile No. :
9501102050
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Central PSU
A-3.
Details of Person Making Application
(i). First Name:
Bhawani
(ii). Middle Name:
Shankar
(iii). Last Name:
Chouhan
(iv). Gender:
Male
(v). Designation:
Chief Manager
(vi). Address 1:
POWERGRID CORPORATION , B-129 , Kanta Khaturia Colony, Bikaner
(vii). Address 2:
NIL
(viii). State:
Rajasthan
(ix). District:
Bikaner
(x). Tehsil:
Bikaner
(xi). Pin:
334003
(xii). Landmark:
NIL
(xiii). Email Address:
bchouhan@powergrid.in
(xiv). Landline Telephone No.:
0-
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9501102050
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Bikaner Territorial
0.46
72.2062
2.
DCF STII BIKANER
0.3542
76.6958
Total
0.8142
148.902
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Bikaner
0.8142
148.902
Total
0.8142
148.902
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Dholera Jetoong
0.46
17.6502
2
Kanasar
0
18.216
3
Bharu Khiran
0
18.446
4
Bharu Pawan
0
17.894
5
Badrasar
0
18.4
6
Mehrasar
0
20.976
7
Kawani
0
16.6612
8
Jaimalsar
0.3542
20.6586
Total
0.8142
148.902
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Tower Foundation
0
3.1104
2
Stringing Area
0.3186
55.1556
3
Remaining ROW Area
0.4956
90.636
Total
0.8142
148.902
C.
Maps of forest land proposed to be diverted
Division 1. : Bikaner Territorial
(i). Area of forest land proposed to be diverted(in ha.) :
0.46
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.46
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : DCF STII BIKANER
(i). Area of forest land proposed to be diverted(in ha.) :
0.3542
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.3542
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
5
(iii). Temporary Employment(Number of person-days):
10065
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
Administrative Sanction
2
Authorization Letter
3
BAR CHART
4
Canal Notification
5
UNDERTAKING FOR IRRIGATION DEPARTMENT NOC
6
Map Showing for Geo-Referenced Survey Of India Toposheet With 400 KV D/C Quad Bikaner(PG) to Bikaner II (PS) Transmission line Route Alignment Scale 1 : 50000
7
Geo-Referenced Digital Map Total Route Alignment With 400 KV D/C Quad Bikaner(PG) to Bikaner II (PS) Transmission line Route Alignment
8
Geo-Referenced Digital Map Required Land Coordinate Segment-2
9
Alternative Route Digital Map
10
Geo-Referenced Digital Map Required Land Coordinate Segment-1 (Bikaner Territorial )
11
Geo-Referenced Digital Map Required Land Coordinate Segment-2 (IGNP ST -II BIKANER)
12
CERTIFICATE TOWARD MUCK DISPOSAL AND MANAGMENT PLAN
13
Details of Permanent Employment to be Generated
14
COMPARATIVE STATEMENT OF ALTERNATIVE ROUTE
15
JUSTIFICATION FOR LOCATING THE PROJECT IN FOREST AREA
16
UNDERTAKING FOR All TYPE FOREST LAND INCLUDED
17
Component Wise Area Calculation Sheet
18
CERTIFICATE FOR MINIMUM USE OF FOREST LAND
19
UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
20
UNDERTAKING FOR MEDICIANAL PLANTS
21
UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
22
UNDERTAKING FOR MUCK DISPOSAL
23
UNDERTAKING FOR NO CHANGES IN STATUTORY POSITION OF DIVERTED FOREST LAND
24
Segment Wise Area Calculation Sheet
25
STATEMENT SHOWING DETAILS OF FOREST AREA PROPOSED FOR DIVERSION
26
UNDERTAKING FOR PAYMENT OF ANY OTHER COST AND CONDITION
27
UNDERTAKING FOR CONSERVATION OF FLORA-FAUNA DURING CONSTRUCTION OF TRANSMISSION LINE
28
UNDERTAKING FOR TWO TIME DEGRADED FOREST LAND
29
UNDERTAKING FOR USE OF ANY MATERIAL FROM SURROUNDED FOREST LAND DURING CONSTRUCTION OF TRANSMISSION LINE
30
UNDERTAKING FOR USE OF FOREST LAND
31
UNDERTAKING OF FRA CERTIFICATE
32
UNDERTAKING FOR NO OTHER FEASIBLE ALTERNATIVE
33
Village Wise Area calculation Sheet Forest and Non-Forest Land
34
EDS Reply-28-03-2022
35
EDS Reply to DCF Bikaner-10-10-2022
36
EDS Reply to DCF STG-II Bikaner-10-10-2022
37
EDS reply to DCF Bikaner-16-01-2023
38
EDS reply to DCF IGNP-II Bikaner-16-01-2023
Print