FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/RJ/TRANS/144853/2021   (ii). Name of Project for which Forest Land is required : Construction of 765 KV D/C Sikar-II -Aligarh Transmission line, District- Sikar, Jaipur & Alwar (Rajasthan)” in Rajasthan Portion Ap-01 to Ap-180 Common Point Rajasthan State Boundary. Total Route Length 180.946 km   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of 765 KV D/C Sikar-II -Aligarh Transmission line, District- Sikar, Jaipur & Alwar (Rajasthan)” in Rajasthan Portion Ap-01 to Ap-183 Common Point Rajasthan -Haryana State Boundary. Total Route Length 180.946km   (iv). State : Rajasthan   (v). Category of the Proposal : Transmission Line   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 100600   (viii). Area of forest land proposed for diversion(in ha.): 15.8321   (ix). Non-forest land required for this project(in ha.): 1196.5061   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : SIKAR -II ALIGARH TRANSMISSION LIMITED (A 100% WHOLLY OWNED SUBSIDIARY OF POWERGRID CORPORATION OF INDIA LIMITED)   (ii). Address1 : PLOT NO-339 , SHANTI KUNJ SCHEME, ALWAR (RAJASTHAN)   (iii). Address2 : NIL   (iv). State : Rajasthan   (v). District : Alwar   (vi). Pin : 301001   (vii). Landmark : NIL   (viii). Email address : kanchan@powergrid.in   (ix). Landline Telephone No. : 0-   (x). Fax No. : 0-   (xi). Mobile No. : 9560690612   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : Central PSU
A-3. Details of Person Making Application
  (i). First Name: Kanchan   (ii). Middle Name: Kumar   (iii). Last Name: Choudhary   (iv). Gender: Male   (v). Designation: Sr General Manager   (vi). Address 1: PLOT NO 339 , SHANTI KUNJ SCHEME , ALWAR-RAJASTHAN   (vii). Address 2: NIL   (viii). State: Rajasthan   (ix). District: Alwar   (x). Tehsil: Alwar   (xi). Pin: 301001   (xii). Landmark: NIL   (xiii). Email Address: kanchan@powergrid.in   (xiv). Landline Telephone No.: 0-   (xv). Fax No.: NIL   (xvi). Mobile No.: 9560690612   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Sikar Territorial0.2278449.4293
2.Jaipur (North) Territorial11.2828228.4633
3.Alwar Territorial4.3215518.6135
Total15.83211196.5061
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Sikar0.2278449.4293
1.Jaipur11.2828228.4633
3.Alwar4.3215518.6135
Total15.83211196.5061
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Dukiya016.5356
2Ganeshpura011.725
3Majipura016.7768
4Chetandas ki Dhani014.5926
5Governdhanpura08.5827
6Vijaynagar07.6715
7Badhala ki Dhani0.227834.304
8Govindpura026.5454
9Dudwaloka bas06.1707
10Kankrawali08.2745
11Lalana012.395
12Pragnpura014.137
13Kirarodh0.221112.9109
14Raghunathpura011.859
15Bhaloji012.261
16Basai08.911
17Nangal Panditpura011.792
18Dhani Todawali06.566
19Tiryala09.7485
20Alampur09.045
21Rampur08.375
22Kanpura08.576
23Khera09.3465
24Khabriyana011.1555
25Bansur09.2795
26Chandwali011.323
27Maira Rawat08.71
28Ramnagar012.73
29Fatehpur07.37
30Bhupsera011.39
31Ladpur010.988
32Mauthuka07.2025
33Chula014.3715
34Guwara014.8271
35Bamanwas010.05
36Thakuriyawas010.653
37Talwas010.854
38Bhuriyawas07.839
39Ranot013.9963
40Tatarpura010.05
41Raipur010.586
42Pehal011.256
43Sukhmeri011.2895
44Nangal Oja09.715
45Rasgah08.2075
46Kharola011.189
47Khairthal012.596
48Saidpur011.5575
49Khirwadi012.194
50Mirka012.998
51Bassi Jsepur012.1002
52Tarwala08.7502
53Santhalka07.437
54Kankra ka Bas011.993
55Seokhera011.189
56Nagalia010.7535
57Gothara0.15418.308
58Bhagtala06.9345
59Chamrodah07.6045
60Bhicupari09.1589
61Bolni08.04
62Naugavwan09.045
63Bijalahra010.854
64Hamlaka08.978
65Maler Jatwali08.576
66Baingaheri07.504
67Hasanpur09.179
68Gujar Maler06.834
69Johara ka Bas010.05
70Bagor07.504
71Nimli4.16748.107
72Nimera012.663
73Basi ka Bas08.174
74Shivpura08.71
75Ralawta015.008
76Jairampura012.06
77Khanipura08.911
78Kalyanpura Goran013.333
79Dehrawali Dhani012.06
80Kotri018.894
81Dabawali015.745
82Gidhalya016.08
83Kalyanpura014.539
84Bamarda Joda012.328
85Dhani Khairwan08.0735
86Jharli022.445
87Kanath ki Dhani011.859
88Bhuranpura015.678
89Hardas ka Bas017.42
90Hathideh016.616
91Sanwalpura Tanwran010.921
92Jugalpura07.437
93Meena ki Dhani08.4755
94Ahiron ki Dhani08.04
95Churala011.055
96Buchara11.061719.6712
97Chotkiyo ki Dhani07.37
98Dudhawas012.529
99Torda Kalan014.9745
100Taksola012.797
101Rajora ki Dhani08.5425
102Rampura018.492
103Panditpura015.7115
104Kakrana09.514
Total 15.8321 1196.5061
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Tower Foundation0.19449.5904
2Stringing5.4768419.0088
3Remaining ROW10.1609767.9069
Total 15.8321 1196.5061
C. Maps of forest land proposed to be diverted
Division 1. : Sikar Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 0.2278   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.2278    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Alwar Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 4.3215   (ii). Nature of the Project: Linear   (b). No. of Segments : Two
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.0.1541    View File
2.4.1674    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 3. : Jaipur (North) Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 11.2828   (ii). Nature of the Project: Linear   (b). No. of Segments : Two
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.11.0617    View File
2.0.2211    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 15   (iii). Temporary Employment(Number of person-days): 420864
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: No
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Not Applicable   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: Not Applicable   (iii) . Reason for not providing Non-Forest Land: Not Applicable
Additional information Details
Documents
S.No Documents
Remarks
1Section 68 Approval
2AUTHORIZATION LETTER
3CERTIFICATE FOR MINIMUM USE OF FOREST LAND
4UNDERTAKING FOR All TYPE FOREST LAND INCLUDED
5UNDERTAKING FOR CONSERVATION OF FLORA-FAUNA DURING CONSTRUCTION OF TRANSMISSION LINE
6UNDERTAKING FOR MEDICIANAL PLANTS
7UNDERTAKING FOR MUCK DISPOSAL
8CERTIFICATE TOWARD MUCK DISPOSAL
9UNDERTAKING FOR NO CHANGE S IN STATUTORY POSITION OF DIVERTED FOREST LAND
10UNDERTAKING FOR PAYMENT OF ANY OTHER COST AND CONDITION
11UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
12UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
13UNDERTAKING FOR TWO TIME DEGRADED FOREST LAND
14UNDERTAKING FOR USE OF ANY MATERIAL FROM SURROUNDED FOREST LAND DURING CONSTRUCTION OF TRANSMISSION LINE
15UNDERTAKING FOR USE OF FOREST LAND
16UNDERTAKING OF FRA CERTIFICATE
17Village Wise Area calculation Sheet Forest and Non-Forest Land
18Segment Wise Area Calculation Sheet
19Component Wise Area Calculation Sheet
20Details of Permanent Employment to be Generated
21Area Calculation Sheet for Forest and Non Forest Land
22Jamabandi Buchara-Jaipur
23Jamabandi Gothra-Alwar
24Jamabandi Nimli-Alwar
25Khasra Map NH-8 -Kirarodh Segment-2
26Khasra Map Gothra Segment-3
27Khasra Map Nimli Segment-4
28Geo-Referenced DGPS Map Segment-2
29Geo-Referenced DGPS Map Segment-3
30Geo-Referenced DGPS Map Segment-4
31Geo-Referenced DGPS Map Total Route Alignment Part-2
32BAR CHART
33ALTERNATIVE SURVEY OF INDIA TOPOSHEET MAP SCALE 1 : 50000
34EDS Reply To Jaipur North Division-20-11-2021
35COMPLETE ALIGNMENT TOWER COORDINATES
36Jamabandi Village-Kirarodh-Jaipur
37JUSTIFICATION FOR LOCATING THE PROJECT IN FOREST AREA
38STATEMENT SHOWING DETAILS OF FOREST AREA PROPOSED FOR DIVERSION
39Map Showing for Geo-Referenced Survey of India Toposheet With Proposed 765 KV D/C Sikar-II -Aligarh Transmission line Route AlignmentScale 1 : 50000 (Forest Division -Alwar)
40Map Showing for Geo-Referenced Survey of India Toposheet With Proposed 765 KV D/C Sikar-II -Aligarh Transmission line Route Alignment Scale 1 : 50000 (Forest Division -Jaipur North)
41Khasra Map Village-Buchara Segment-1
42Geo-Referenced DGPS Map Segment-1
43Geo-Referenced DGPS Map Total Route Alignment Part-1
44EDS Reply To Sikar Division-20-11-2021
45Toposheet Map Total route alignment -Part-1
46EDS Reply to DCF Jaipur North-21-03-2022
47Jamabandi Kirod-khasra no 22
48Map Showing for Geo-Referenced Survey of India Toposheet With Proposed 765 KV D/C Sikar-II -Aligarh Transmission line Route Alignment Scale 1 : 50000 (Forest Division -Sikar)
49DGPS Map NH-52 (Sikar Division)
50Digital Map Final (Sikar Division)
51Undertaking and All Documents (Sikar Forest -Division)
52Khasra Map Super Imposed (Sikar Division) Scale 1 : 4000
53EDS Reply-27-12-2022
54COMPARATIVE STATEMENT OF ALTERNATIVE ROUTE
55Permission for Proposal Area Editing Application to Nodal Officer Jaipur