FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/RJ/TRANS/143945/2021
(ii). Name of Project for which Forest Land is required :
Construction of Sikar-II_Neemrana 400 KV D/C Transmission Line(Twin HTLS*)in Rajasthan
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
“Construction of Sikar-II Neemrana 400 KV D/C Transmission line(Twin HTLS*) , District-Sikar, Jhunjhunu, Jaipur & Alwar (Rajasthan)” (Total Route Length 134.810 km) in Rajasthan Portion Route Length 126.290km
(iv). State :
Rajasthan
(v). Category of the Proposal :
Transmission Line
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
13591.205
(viii). Area of forest land proposed for diversion(in ha.):
13.0134
(ix). Non-forest land required for this project(in ha.):
564.9674
(x). Total period for which the forest land is proposed to be diverted(in years):
50
A-2.
Details of User Agency
(i). Name :
SIKAR NEW TRANSMISSION LIMITED (A 100% WHOLLY OWNED SUBSIDIARY OF POWERGRID CORPORATION OF INDIA LIMITED)
(ii). Address1 :
Sikar 400/220KV Sub Station , Village-Bhadadhar, Post-Khuri Badi,13th Mile Stone Sikar-Bikaner Highway, (Rajasthan)
(iii). Address2 :
NIL
(iv). State :
Rajasthan
(v). District :
Sikar
(vi). Pin :
332315
(vii). Landmark :
NIL
(viii). Email address :
ppchaurasia@powergrid.in
(ix). Landline Telephone No. :
0-
(x). Fax No. :
0-
(xi). Mobile No. :
6378774484
(xii). Website (if any) :
NIL
(xiii). Legal status of User Agency :
Central PSU
A-3.
Details of Person Making Application
(i). First Name:
PRANVEER
(ii). Middle Name:
PRATAP
(iii). Last Name:
CHAURASIA
(iv). Gender:
Male
(v). Designation:
ChiefManager
(vi). Address 1:
Sikar 400/220 KV Sub Station ,Village-Bhadadhar, Post - Khuri Badi , 13 th Mile Stone Sikar-Bikaner NH, Rajasthan
(vii). Address 2:
NIL
(viii). State:
Rajasthan
(ix). District:
Sikar
(x). Tehsil:
Sikar
(xi). Pin:
332315
(xii). Landmark:
NIL
(xiii). Email Address:
ppchaurasia@powergrid.in
(xiv). Landline Telephone No.:
0-
(xv). Fax No.:
NIL
(xvi). Mobile No.:
6378774484
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Sikar Territorial
7.5486
380.627
2.
Jhunjhunu Territorial
0
14.3796
3.
Jaipur (North) Territorial
0
25.0608
4.
Alwar Territorial
5.4648
144.9
Total
13.0134
564.9674
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Sikar
7.5486
380.627
1.
jhunjhunu
0
14.3796
3.
Jaipur
0
25.0608
4.
Alwar
5.4648
144.9
Total
13.0134
564.9674
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Akhepura
0
13.0502
2
Palsana
0
13.616
3
Govindpura
0
14.306
4
Sajanpura
0
6.854
5
Hamirpura
0
9.2
6
Khatundra
0
9.936
7
Garhrwalo Ki Dhani
0
10.4052
8
Soladipura
0
10.6076
9
Padampura
0
10.971
10
Bhojpura
0
11.8726
11
Dulapura
0
10.258
12
Math
0
9.844
13
Basri
0
10.994
14
Pratapura
0
13.0134
15
Nimki
0
12.328
16
Charan ka Bas
0
13.1974
17
Choukri
0
9.476
18
Hanuman Nagar
0
11.04
19
Challa
0
7.475
20
Bhopalpura
0
5.3636
21
Sirohi
0
7.82
22
Ranasar
0
8.303
23
Nayabas
0
7.452
24
Neem Ka Thana
0
9.108
25
Gorawas
0
9.062
26
Kalu Ki Dhani
0
7.13
27
Bageshwar
0
7.82
28
Barala
0
7.038
29
Khadag Bijpur
4.8622
6.21
30
Nathuwala
2.6864
7.0288
31
Dokan
0
8.556
32
Dhandela
0
6.44
33
Patan
0
7.9212
34
Rajpura
0
7.268
35
Mohanpura
0
8.234
36
Balupura
0
6.21
37
Jhamas
0
12.236
38
Rampura
0
9.867
39
Dalpatpura
0
7.682
40
Dilpura
0
7.981
41
Sirsa ki Dhani
0
7.452
42
Pachalngi
0
7.5256
43
Jharaya
0
6.854
44
Banar
0
9.6048
45
Chola ki Dhani
0
5.06
46
Deota
0
5.658
47
Chhadra
0
4.738
48
Nalota
0
4.048
49
Dhindhor
0
8.602
50
Gadoj
0
5.865
51
Gunti
0.15
5.106
52
Simla
0
7.452
53
Gokulpur
0
5.566
54
Jagwas
0
5.451
55
Bahror
0
7.36
56
Kalyanpura
0
7.337
57
Nangla Rudh
0
3.68
58
Devnagar
0
8.832
59
Bardod
1.8078
6.8126
60
Batkhani
0
6.624
61
Bhungra Thetar
1.012
5.543
62
Kolila Joga
0
5.98
63
Manjrakath
1.035
10.511
64
Sanauli
1.4122
9.982
65
Isrisinghpura
0
6.5044
66
Fauladpur
0
11.776
67
Shanjapur
0.0478
11.868
Total
13.0134
564.9674
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Tower Foundation
0.2268
11.6964
2
Stringing Area
4.8654
209.3778
3
Remaining ROW Area
7.9212
343.8932
Total
13.0134
564.9674
C.
Maps of forest land proposed to be diverted
Division 1. : Alwar Territorial
(i). Area of forest land proposed to be diverted(in ha.) :
5.4648
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Four
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
0.15
View File
2.
1.8078
View File
3.
3.4592
View File
4.
0.0478
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Sikar Territorial
(i). Area of forest land proposed to be diverted(in ha.) :
7.5486
(ii). Nature of the Project:
Linear
(b). No. of Segments :
Three
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
2.323
View File
2.
4.2412
View File
3.
0.9844
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
6
(iii). Temporary Employment(Number of person-days):
58636
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
Yes
(a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
ADMINISTRATIVE SANCTION
2
Authorization
3
LoI Rajasthan Part C
4
PROJECT REPORT
5
EDS REPLY-08-07-2021
6
Approval Section 68 _Raj C
7
BAR CHART
8
CERTIFICATE FOR MINIMUM USE OF FOREST LAND
9
CERTIFICATE TOWARD MUCK DISPOSAL AND MANAGMENT PLAN
10
Details of Permanent Employment to be Generated
11
ENVIRONMENTAL CLEARANCE CERTIFICATE
12
JUSTIFICATION FOR LOCATING THE PROJECT IN FOREST AREA
13
Segment Wise Area Calculation Sheet
14
UNDERTAKING FOR All TYPE FOREST LAND INCLUDED
15
UNDERTAKING FOR CONSERVATION OF FLORA-FAUNA DURING CONSTRUCTION OF TRANSMISSION LINE
16
UNDERTAKING FOR MEDICIANAL PLANTS
17
UNDERTAKING FOR MUCK DISPOSAL
18
UNDERTAKING FOR NO CHANGE S IN STATUTORY POSITION OF DIVERTED FOREST LAND
19
UNDERTAKING FOR PAYMENT OF ANY OTHER COST AND CONDITION
20
UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION
21
UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA
22
UNDERTAKING FOR TWO TIME DEGRADED FOREST LAND
23
UNDERTAKING FOR USE OF ANY MATERIAL FROM SURROUNDED FOREST LAND DURING CONSTRUCTION OF TRANSMISSION LINE
24
UNDERTAKING FOR USE OF FOREST LAND
25
UNDERTAKING OF FRA CERTIFICATE
26
Village Wise Area calculation Sheet Forest and Non-Forest Land
27
Map Showing For Geo-Referenced Survey of India Toposheet With Proposed Construction of Sikar-Neemrana 400 KV D/C Transmission line Full Toposheet No-45m/6, 45m/10 , 45m/13 , 45m/14 , 54 A/1 (Forest Division -Sikar) Scale 1 : 50000
28
Geo-Referenced Revenue Khasra Map Village -Khadag Bijpur and Nathuwala Division -Sikar Scale 1 : 4000
29
STATEMENT SHOWING DETAILS OF FOREST AREA PROPOSED FOR DIVERSION (Division-Sikar)
30
STATEMENT SHOWING DETAILS OF NON FOREST AREA INVOLVED IN THE PROPOSAL
31
Jamabandi (Sikar Forest - Division)
32
Map Showing For Geo-Referenced Survey of India Toposheet With Proposed Construction of Sikar-Neemrana 400 KV D/C Transmission line Full Toposheet No- 54 A/1 ,54 A/5, 54D/8 ( Forest Division -Alwar) Scale 1 : 50000
33
Geo-Referenced DGPS Map Showing for Required Land Coordinate with Proposed Construction of Sikar-Neemrana 400 KV D/C Transmission line (Alwar -Forest Division)
34
STATEMENT SHOWING DETAILS OF FOREST AREA PROPOSED FOR DIVERSION (Forest Division-Alwar)
35
Jamabandi (Alwer Division)
36
Geo-Referenced KHASRA MAP Segment 4 to 7 (Alwar Forest Division) Scale 1 :4000
37
COMPARATIVE STATEMENT OF ALTERNATIVE ROUTE
38
Geo-Referenced Google Map (Sikar -Forest Division)
39
Geo-Referenced DGPS Map Showing for Required Land Coordinate with Proposed Construction of Sikar-Neemrana 400 KV D/C Transmission line (Sikar -Forest Division)
40
Geo-Referenced Digital Map Total Route with Proposed Construction of Sikar-Neemrana 400 KV D/C Transmission line
41
Geo-Referenced Alternative Digital Map
42
Alternative Toposheet map
43
EDS Reply Powergrid to Jaipur Forest Division-4-01-2022
44
EDS Reply Power grid to Jaipur Forest Division-4-01-2022
45
EDS Reply Power grid to Sikar Forest Division-4-01-2022
46
EDS reply-19-01-2022 Forest dcf letter 12-01-2022 Regarding
Print