FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/RJ/ROAD/29812/2017   (ii). Name of Project for which Forest Land is required : Laxmipura-Dora-Dabi-Ranaji Ka Guda NH-12   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Project, NH 12-Laxmipura-Dora-Dabi-Ranaji ka Gudha Road starts from T-Junction with NH-12 (Kota-Bundi Section) at Moheepura & terminates at 3-legged junction near Ranaji ka Gudha. The project road overlaps with NH-76 for 3.7 km and diverges to left from Dabi town. The Project Road as described   (iv). State : Rajasthan   (v). Category of the Proposal : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 10325   (viii). Area of forest land proposed for diversion(in ha.): 32.3264   (ix). Non-forest land required for this project(in ha.): 46.6192   (x). Total period for which the forest land is proposed to be diverted(in years): 100
A-2. Details of User Agency
  (i). Name : ADD. CHIEF ENGINEER PPP PWD   (ii). Address1 : Additional Chief Engineer PPP PWD,Rajasthan,Jaipur-302006   (iii). Address2 : NIL   (iv). State : Rajasthan   (v). District : Jaipur   (vi). Pin : 302006   (vii). Landmark : Opposite Jaipur Club,Jaipur-Rajasthan   (viii). Email address : pdkotappppwd@gmail.com   (ix). Landline Telephone No. : 141-5110547   (x). Fax No. : 141-5110547   (xi). Mobile No. : 9414338655   (xii). Website (if any) : www.pwd.rajasthan.gov.in   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Naurat   (ii). Middle Name: Mal   (iii). Last Name: Agarwal   (iv). Gender: Male   (v). Designation: Project Director   (vi). Address 1: Public Works Department (PPP-1 Division) Ajmer (Raj.)   (vii). Address 2: NIL   (viii). State: Rajasthan   (ix). District: Ajmer   (x). Tehsil: Ajmer   (xi). Pin: 305007   (xii). Landmark: Office of the Project Director   (xiii). Email Address: pdkotappppwd@gmail.com   (xiv). Landline Telephone No.: 141-5110547   (xv). Fax No.: 01415110547   (xvi). Mobile No.: 9413369360   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Bundi Territorial32.326446.6192
Total32.326446.6192
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Bundi32.326446.6192
Total32.326446.6192
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1Bharta Bavdi1.91233.1794
2Laxmipura1.15656.5475
3Maradi Talab2.81375.2506
4Dora10.70913.7545
5Kachaliya3.96053.5535
6Kanwarpura7.09593.744
7Dabi1.5523.7192
8Chhant ka Khera1.97443.4205
9Lambakoh1.15213.45
Total 32.3264 46.6192
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Development of Road32.326446.6192
Total 32.3264 46.6192
C. Maps of forest land proposed to be diverted
Division 1. : Bundi Territorial
  (i). Area of forest land proposed to be diverted(in ha.) : 32.3264   (ii). Nature of the Project: Linear   (b). No. of Segments : Six
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.3.0688    View File
2.19.4592    View File
3.5.12    View File
4.1.552    View File
5.1.9744    View File
6.1.152    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: No   (a). Reason for not providing such map: Road is already exist.
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 0   (iii). Temporary Employment(Number of person-days): 850
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : Yes   (a). Whether Project or a part thereof is located within a Protected Area ? : Yes   (b). Status of approval of the Supreme Court : Application yet to b   (ii). Status of approval of the Standing Committee of National Board for the Wildlife(NBWL) to the Project : Application under process   (a). Date of submission of proposals : 22 Nov 2022   (b). Current status : NIL
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Yes   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii). No. of districts involved for raising Compensatory Afforestation: 1   (iv). No. of patches: Two
District 1. : Bundi
  (a). Village: Bhartabawri Forest Block   (b). Area(in ha.): 60   (c). Copy of KML file of the patch:     View File   (d). Khasra details: Degraded Forest Land   (e). Present owner: Others   (f). Copy of ownership proof:   (g). Copy of Mou/agreement executed between the Present owner and the User Agency:   (h). Copy of non encumberence certificate for the forest land:
District 2. : Bundi
  (a). Village: Chanda Ka Talab   (b). Area(in ha.): 32.3264   (c). Copy of KML file of the patch:     View File   (d). Khasra details: 355/241,357/243   (e). Present owner: Others   (f). Copy of ownership proof:   (g). Copy of Mou/agreement executed between the Present owner and the User Agency:   (h). Copy of non encumberence certificate for the forest land:
  (v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:   (vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No Documents
Remarks
1Administrative and Financial Sanction.
2Project Report.
3Typical Cross Section.
4EDS reply Lettter 14_02_2020.
5EDS Reply Letter dated 06_07_2020.
6CERTIFICATE FOR MINIMUM USE OF FOREST LAND.
7UNDERTAKING FOR CA Land NFL.
8UNDERTAKING FOR CONSERVATION OF FLORA FAUNA DURING.
9UNDERTAKING FOR FRA CERTIFICATE.
10UNDERTAKING FOR NO CHANGES IN STATUTORY POSITION OF DIVERTED FOREST LAND.
11UNDERTAKING FOR NO OTHER FEASIBLE ALTERNATIVE MINIMUM FOREST LAND.
12UNDERTAKING FOR PAYMENT OF ANY OTHER COST and CONDITION.
13UNDERTAKING FOR PAYMENT OF COST OF COMPENSATORY AFFORESTATION.
14UNDERTAKING FOR PAYMENT OF NET PRESENT VALUE OF FOREST AREA.
15Undertaking for Use of Any Material From Forest Land During CONSTRUCTION OF ROAD.
16UNDERTAKING FOR USE OF FOREST LAND.
17Undertaking for Waste Management.
18Khasra Map and Jamabandi.
19Bar Chart status.
20EDS Reply Letter DFO Bundi dated 16_12_2020.
21UNDERTAKING BY USER AGENCY TO RAISE STRIP PLANTATION.
22EDS Reply Letter dated 30_09_2021.
23Reply Letter of 30.08.2022 EDS
24Reply letter of 30.12.2022 EDS.
25Reply of 16.01.2023
26Village Wise Area Calculation Sheet.
27Digital Maps.
28Segment Wise Area Calculation Sheet.
29Toposheet Map.
30Reply of EDS raised on dated 29.03.2023.
31Wildlife NoC Undertaking.
32Reply of 19.04.2023 EDS.
33Cost Benefit Analysis Report.
34Reply of 24.05.2023 EDS.
35Proposed CA land Map NFL
36CA Land Allotment Documents NFL
37New CA Land has been identified and Land Allotment / Set Apart Letter has been issued by District Collector Bundi. Accordingly CA Land Maps as well as KML file of the proposed Land has been Prepared and uploaded in the Part Ist .
38Reply of EDS raised on dated 31.05.2024.
39Reply of EDS raised on dated 10.07.2024
40EDS Reply Letter dated 18_09_2024 with Annexure
4180th NBWL MoM.