FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/OR/Others/149695/2021
(ii). Name of Project for which Forest Land is required :
NALCO Conveyor Cooridor System
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Conveyor project is for evacuation of Bauxite Ore from Pottangi Bauxite Mines to the existing Plant of Alumina Refinery, of NALCO Ltd at a distance of 18.5 KM.
(iv). State :
Orissa
(v). Category of the Proposal :
Others
(vi). Shape of forest land proposed to be diverted :
Linear
(vii). Estimated cost of the Project(Rupees in lacs) :
7320000
(viii). Area of forest land proposed for diversion(in ha.):
41.297
(ix). Non-forest land required for this project(in ha.):
89.565
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
NALCO
(ii). Address1 :
NALCO Bhawan, P-1, Nayapalli
(iii). Address2 :
P.O.-RRL, Bhubaneswar
(iv). State :
Orissa
(v). District :
Anugul
(vi). Pin :
751013
(vii). Landmark :
NIL
(viii). Email address :
gm_uecb@nalcoindia.co.in
(ix). Landline Telephone No. :
6764-220323
(x). Fax No. :
6764-220824
(xi). Mobile No. :
9437072198
(xii). Website (if any) :
www.nalcoindia.com
(xiii). Legal status of User Agency :
Central PSU
A-3.
Details of Person Making Application
(i). First Name:
Kalikinkar
(ii). Middle Name:
NIL
(iii). Last Name:
Panda
(iv). Gender:
Male
(v). Designation:
Executive Director (P&T)
(vi). Address 1:
NALCO Bhawan, P-1, Nayapalli
(vii). Address 2:
P.O.-RRL, Bhubaneswar
(viii). State:
Orissa
(ix). District:
Khordha
(x). Tehsil:
Khordha
(xi). Pin:
751013
(xii). Landmark:
NIL
(xiii). Email Address:
gm_uecb@nalcoindia.co.in
(xiv). Landline Telephone No.:
674-2300633
(xv). Fax No.:
NIL
(xvi). Mobile No.:
9437071929
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Koraput
41.297
89.565
Total
41.297
89.565
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Koraput
41.297
89.565
Total
41.297
89.565
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Marichamala
0
20.662
2
Sindhipar
0
5.739
3
Aligan
0.751
24.866
4
Charanguli
0.117
2.203
5
Jamukota
0
4.021
6
Mania
0
9.554
7
Marla
0
6.131
8
Sorisapadar
0
7.627
9
Bhitarkota
0.457
3.481
10
Jungle Block
29.037
0
11
Jungle Block (pottangi Range)
10.935
0
12
Damanjodi
0
5.281
Total
41.297
89.565
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
proposed Conveyor Corrodor System
41.297
89.565
Total
41.297
89.565
C.
Maps of forest land proposed to be diverted
Division 1. : Koraput
(i). Area of forest land proposed to be diverted(in ha.) :
41.297
(ii). Nature of the Project:
Linear
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
41.297
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
Yes
(a). Copy of map indicating location of alternative examined:
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
10
(iii). Temporary Employment(Number of person-days):
30
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
Yes
(a). Copy of Cost-Benefit analysis:
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
No
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
No
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Not Applicable
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
Not Applicable
(iii) . Reason for not providing Non-Forest Land:
Not Applicable
Additional information Details
Documents
S.No
Documents
Remarks
1
Land scheduled as on 25.10.1980.
2
Minimum use of forest
3
Undertaking for CA Levies
4
Road Land scheduled as on 25.10.1980.
5
Undertaking for NPV
6
Short narrativce of the Project.
7
Allotment letter of IDCO
8
Undertaking for Environmental Clearance.
9
EDS has been complied.
10
CA Dgps Map
11
DGPS Map Platee-1
12
DGPS Map Plate-2
13
DGPS Map Plate-3
14
DGPS Map Plate-4
15
DGPS Map Plate-5
16
DGPS Map Plate-6
17
EDS has been complied vide this office Letter dated 21.08.2023.