FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/OR/IRRIG/148107/2021   (ii). Name of Project for which Forest Land is required : Budhabalanga Barrage Project Canal System   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Budhabalanga Barrage Project envisages construction of a Barrage at village Kamata in Kuliana Block of Mayurbhanj District across the River Budhabalanga consists of Right Main Canal of 48.360 km with sub canal of 69.063 km. The catchment area of the proposed project at site is 1008 Sq K.M. The proje   (iv). State : Orissa   (v). Category of the Proposal : Irrigation   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 2423700   (viii). Area of forest land proposed for diversion(in ha.): 39.401   (ix). Non-forest land required for this project(in ha.): 291.413   (x). Total period for which the forest land is proposed to be diverted(in years): 99
A-2. Details of User Agency
  (i). Name : SE, MAYURBHANJ INVESTIGATION DIVISION   (ii). Address1 : O/o Superintendent Engineer, Mayurbhanj Investigation Division, Udala, Mayurbhanj   (iii). Address2 : NIL   (iv). State : Orissa   (v). District : Mayurbhanj   (vi). Pin : 757041   (vii). Landmark : Infront of Mendakhai School   (viii). Email address : eemidudala20@gmail.com   (ix). Landline Telephone No. : 6795-232236   (x). Fax No. : 6795-   (xi). Mobile No. : 9437729307   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Bajinath   (ii). Middle Name: NIL   (iii). Last Name: Hembram   (iv). Gender: Male   (v). Designation: Executive Engineer   (vi). Address 1: O/o Superintendent Engineer, Mayurbhanj Investigation Division, Udala, Mayurbhanj   (vii). Address 2: NIL   (viii). State: Orissa   (ix). District: Mayurbhanj   (x). Tehsil: Udala   (xi). Pin: 757041   (xii). Landmark: Infront of Mendakhai School   (xiii). Email Address: eemidudala20@gmail.com   (xiv). Landline Telephone No.: 6795-232236   (xv). Fax No.: NIL   (xvi). Mobile No.: 9437729307   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
NIL
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Baripada39.401291.413
Total39.401291.413
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Mayurbhanj39.401291.413
Total39.401291.413
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1ANANDABRUNDABANPUR02.355
2ARAPATA0.013.876
3ASTAJHARAN0.3293.038
4ASTIABERA00.323
5BADASAHI08.978
6BADASORISABHILA02.371
7BALABHADRAPUR00.587
8BALIJODA00.867
9BARAGADI00.779
10BARAKERAKA0.4773.176
11BARAPARA01.221
12BARUDIHI01.638
13BATHUDIBANDHA03.089
14BELAM00.882
15BELAPAL00.278
16BIRESWARAPUR02.504
17CHAKAMADHAPUR01.013
18CHAULIASHULA00.066
19CHHELIA04.8
20CHOPARAPUR02.45
21DANTUNI05.46
22DHABALANGA02.881
23DHANAPOTA04.861
24DHANASAHI00.393
25DHOBADHOBANI01.168
26DUMURIA00.968
27FATAKUSUMA01.571
28GODIDIHASAMILKAMALASHULA0.5311.033
29GOVINDAPUR0.0031.566
30GURIALBANDHA0.1519.037
31HARIPUR1.0111.309
32HINJALGARIA0.6043.864
33ITAMUNDIA0.1680.927
34JADIPAL03.41
35JAMUNA08.546
36JATIADIHA02.891
37KADUALABANDHA03.021
38KAINSALI03.027
39KANDALIAPAL01.004
40KANDALIASULA2.2051.035
41KANJIKULA00.145
42KHANUA2.35318.066
43KHUNTAPAL04.753
44KOCHILAPADA04.833
45KOLIDIHA07.571
46KOTHAPAL01.552
47NARANKHUNTA02.044
48NARANPUR0.0868.671
49NAYABRAJANANDAPUR02.352
50NILAKANTHAPUR00.106
51PANDUAPIDHA01.148
52PRATAPPUR02.875
53PUNDAL03.274
54SAHARASUNI00.147
55SANAKERAKA00.453
56SANANUAGAON01.35
57SANASORISABHILA0.0174.34
58SINGITIA0.1393.089
59TALANDA0.0015.056
60TUNGASULA0.0449.464
61UNCHABALI00.095
62UTHANINUAGAON07.36
63DANTAMUSAL2.8212.509
64KAMARPAL4.5492.813
65KATHAPAL2.7410.503
66PATIHINJA1.0421.984
67SARAPANKHA04.725
68AKARSILA4.4010.687
69AMBASIKADA05.292
70BAJRATUNDI02.509
71BALIMUNADALI00.24
72BAUNSABHILA0.01112.511
73BHALUKI01.207
74BISHNUPAL0.2190.395
75CHAHATIABASANGABANI01.855
76CHANABARIA1.7760.18
77DANGARASAHI04.421
78GARUPAL0.291.064
79GUNDIHUDI01.798
80HARISHCHANDRAPUR00.096
81HATIMARA00.529
82JAMSULA1.1930.072
83JANUDIHI01.055
84JAYABHILA0.0184.677
85JHILIRIBANI1.2030.09
86KARANJIA01.2
87KHANDIA0.5225.13
88KUNDALABANI08.652
89MAHULAKARAKACHIA03.627
90MATIALI0.1713.929
91PAIKABASA0.0552.781
92PHULAJHAASAMILPHATUDIHI0.62.682
93RANGAMATIA04.978
94SANAKOCHIAMARA0.0613.481
95SATAPOUTIA01.311
96TOLAKAPOKHARI01.423
97DUKURA RF9.60
Total 39.401 291.413
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1Main Canal34.831160.148
2Sub Canal4.57131.265
Total 39.401 291.413
C. Maps of forest land proposed to be diverted
Division 1. : Baripada
  (i). Area of forest land proposed to be diverted(in ha.) : 39.401   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.39.401    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 25   (iii). Temporary Employment(Number of person-days): 30000
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : No
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Yes   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii). No. of districts involved for raising Compensatory Afforestation: 1   (iv). No. of patches: One
District 1. : Mayurbhanj
  (a). Village: Jhatisiring   (b). Area(in ha.): 40   (c). Copy of KML file of the patch:     View File   (d). Khasra details: Parbat-II   (e). Present owner: Others   (f). Copy of ownership proof:   (g). Copy of Mou/agreement executed between the Present owner and the User Agency:   (h). Copy of non encumberence certificate for the forest land:
  (v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:   (vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
M. Hydel/Irrigation/Multipurpose Project
  (i). Installed power generation capacity of the Project(in MW): 0   (ii). Total command area of the Project(in ha.): 8523   (a). Copy of the approval of competent authority to the Catchment Area Treatment Plan (CAT Plan):   (b). Copy of the approved CAT plan:
Additional information Details
Documents
S.No Documents
Remarks
1EDS has been complied vide this 07.09.2022.