FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A.
General Details
A-1.
Project Details
(i). Proposal No. :
FP/OR/IRRIG/12731/2015
(ii). Name of Project for which Forest Land is required :
Sono Barrage Project
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Sono Irrigation project is Barrage project on river Sono (Sunei) a tributary to Bhudahbalang River in Budhabalang-Jambhira basin. The barrage will be constructed at Jaida Village of GB Nagar block of Mayrubhanj District. The project will irrigate a CCA of 9900ha
(iv). State :
Orissa
(v). Category of the Proposal :
Irrigation
(vi). Shape of forest land proposed to be diverted :
Hybrid
(vii). Estimated cost of the Project(Rupees in lacs) :
21600
(viii). Area of forest land proposed for diversion(in ha.):
14.928
(ix). Non-forest land required for this project(in ha.):
491.85
(x). Total period for which the forest land is proposed to be diverted(in years):
99
A-2.
Details of User Agency
(i). Name :
MAYURBHANJ INVESTIGATION DIVISION DEPARTMENT OF WATER RESOURCES ODISHA
(ii). Address1 :
Mayurbhanj Investigation Division, Udala
(iii). Address2 :
NIL
(iv). State :
Orissa
(v). District :
Mayurbhanj
(vi). Pin :
757041
(vii). Landmark :
Infront of Mendhakhai School
(viii). Email address :
fdpsono@gmail.com
(ix). Landline Telephone No. :
6795-232236
(x). Fax No. :
6795-232236
(xi). Mobile No. :
9437636015
(xii). Website (if any) :
www.dowrorissa.gov.in
(xiii). Legal status of User Agency :
State Government
A-3.
Details of Person Making Application
(i). First Name:
Somanath
(ii). Middle Name:
NIL
(iii). Last Name:
Sahoo
(iv). Gender:
Male
(v). Designation:
Executive Engineer
(vi). Address 1:
Mayurbhanj Investigation Division, Udala
(vii). Address 2:
NIL
(viii). State:
Orissa
(ix). District:
Mayurbhanj
(x). Tehsil:
Udala
(xi). Pin:
757041
(xii). Landmark:
Infront of Mendhakhai School
(xiii). Email Address:
fdpsono@gmail.com
(xiv). Landline Telephone No.:
6795-232236
(xv). Fax No.:
6795232236
(xvi). Mobile No.:
9437636015
(xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B.
Details of land required for the Project
B-1.
Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
List of proposal submitted in Past
S.no
Proposal Status.
Proposal No.
Moef File No.
Area Proposed for Diversion(Ha.)
Area Diverted(Ha.)
Date of In-Principle Approval
Date of Final Approval
NIL
B-2.
Details of forest land proposed to be diverted
B-2.1
Details of Divisions involved
Details of Divisions involved
S.no
Division Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Baripada
12.274
391.252
2.
Balasore Wildlife
2.654
100.598
Total
14.928
491.85
B-2.2
Details of Districts involved
District wise breakup
S.no
District Name
Forest Land(ha.)
Non-Forest Land(ha.)
1.
Mayurbhanj
12.274
391.252
1.
Baleshwar
2.654
100.598
Total
14.928
491.85
B-2.3
Village wise breakup
Villages wise breakup
S.no
Village
Forest Land(ha.)
Non-Forest Land(ha.)
1
Adapal
0.433
30.696
2
Badasingaria
0.255
6.386
3
Jualia
0.045
14.448
4
Naharpada
0
20.477
5
Hatisahi
2.396
59.166
6
Belapal
0.753
58.219
7
Brundagadi
0
2.764
8
Nijikainsari
0.174
26.366
9
Jaida
0
8.632
10
Bharadadihi
0
0.315
11
Marsigan
0
3.626
12
Kalimeghi
0
2.987
13
Keshpur
0
5.483
14
Astia
0
1.756
15
Sartakipur
0.016
2.165
16
Kaliapada
0.008
2.476
17
Joypur
0
6.941
18
Dambarudiha
0
0.834
19
Brahmansahi
0
0.768
20
Sirathali
0
2.501
21
Puruna Baripada
0.004
8.094
22
Gadadhara Kumaripu Sasan
0.024
3.601
23
Chilima
0
3.222
24
Kudilo Kuamara
0
5.135
25
Upar Kadada
0
5.192
26
Parichipur
0
1.914
27
Khipada
0
2.242
28
Ambasul
0
2.869
29
Palasa
0
0.805
30
Tikayatpur
0
0.267
31
Samaraypur
0
1.149
32
Arapata
0.202
13.323
33
Daundia
0
4.221
34
Dolisul
0
1.752
35
Chainpur
0
1.169
36
Bhuinchada
0.065
3.319
37
Dahadapaikali
0
0.983
38
Rautrapur
0.008
1.25
39
Jambani
0
0.575
40
Jambeswarpur
0.158
1.611
41
Kudia
0.028
1.752
42
Chandakundia
0.142
1.384
43
Dasipur
0
1.105
44
Udaypur
0.486
6.693
45
Barakoli
0
0.522
46
Dekhand
0
3.836
47
Bhadrasia
0.016
3.828
48
Isupur
0
1.084
49
Gududa
0
6.042
50
Barabanka
0.045
0.793
51
Mayurgaon
0.372
4.46
52
Khadikapada
0
2.849
53
Mankadakenda
0.008
1.003
54
Chaturigariamala
0
3.751
55
Gohiradiha
0
3.537
56
Pashuda
0
3.266
57
Patua
0
2.586
58
Sikidia
0
1.311
59
Kusumia Patapur
0.065
7.661
60
Brahmapur
0
4.5
61
Patisari
0
4.938
62
Tentuligaon
0.138
6.605
63
Yamunadeipur
0.012
1.417
64
Kanhupur
0.737
4.626
65
Ratanpur
0.097
5.698
66
Arjunabaria
1.214
2.736
67
Chinguamangalpur
0
3.771
68
Beguniabani
0
3.213
69
Bhimda
0
4.832
70
kashibani
0
5.475
71
Adidiha
0
4.2
72
Radhakishorepur
0.409
6.879
73
Pundal
0.146
10.607
74
Purukhi
0.045
5.852
75
junoda
0
1.971
76
Surajpur
0
2.772
77
Kantabania
0
0.696
78
Maninathapur
0.069
1.246
79
Kualhati
0.134
2.659
80
Santahati
0
1.826
81
Tentrada
0.316
3.832
82
Dhadamandaripur
0
2.165
83
Junoda-2
0.057
1.728
84
Mundigaon Diachhak
0
0.421
85
Mahada
0.097
4.933
86
Silasuan
0.061
2.845
87
Balipal
0
0.789
88
Parhata
0
1.234
89
Chhachna
0
1.582
90
Mundigon
0
1.032
91
Deghi
0.024
1.38
92
Kashimpur
0
4.5
93
Barhampur-2
0
1.728
94
Kanhupur Reserve Forest
5.669
0
Total
14.928
491.85
B-2.4
Component wise breakup
Component wise breakup
S.no
Component
Forest Land(ha.)
Non-Forest Land(ha.)
1
Canal
10.872
268.78
2
Pondage
4.056
223.07
Total
14.928
491.85
C.
Maps of forest land proposed to be diverted
Division 1. : Balasore Wildlife
(i). Area of forest land proposed to be diverted(in ha.) :
2.654
(ii). Nature of the Project:
Hybrid
(a). No. of patches :
One
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
0
View File
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
2.654
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
Division 2. : Baripada
(i). Area of forest land proposed to be diverted(in ha.) :
12.274
(ii). Nature of the Project:
Hybrid
(a). No. of patches :
One
Patch wise details
Patch No.
Area of Patch(in ha.)
Kml File of Patches
To view KML file on google the same may be downloaded and then open if in google earth install in your computer.
1.
4.056
View File
(b). No. of Segments :
One
Segment wise details
Segments
Segment Area(in ha.)
Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.
8.218
View File
(iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:
(iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D.
Justification for locating the Project in forest land and details of alternatives examined:
(i). Copy of note containing justification for locating the Project in forest land:
(ii). Whether a copy of map indicating location of alternative examine is required to be provided:
No
(a). Reason for not providing such map:
Site Specific Project
E.
Employment likely to be generated
(i). Whether the Project is likely to generate employment ?:
Yes
(ii). Permanent/Regular Employment(Number of persons):
30
(iii). Temporary Employment(Number of person-days):
300000
F.
Displacement of People due to the Project, if any
(i). Whether Project involves displacement?:
No
G.
Details of Cost-Benefit analysis for the Project
(i). Whether the Project requires Cost-Benefit analysis?:
No
H.
Status of Environmental Clearance
(i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? :
Yes
(a). Status of the Environmental Clearance to the Project:
EC obtained
(b). Environmental Clearance File No.:
SEIAA/85 dated 14.02.2011
(c). Copy of Environmental Clearance to the Project:
(d). Date of grant of Environmental Clearance to the Project:
NIL
I.
Status of Wildelife Clearance
(i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? :
No
J.
Applicability of special provisions governing Scheduled Areas
(i).Whether the Project or a part thereof is located in a Scheduled Area? :
Yes
K.
Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
(i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? :
No
L.
Details of land identified for Compensatory Afforestation
(i). Whether non-forest or Revenue forest land is required to be provided by User Agency?:
Yes
(ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?:
No
(iii). No. of districts involved for raising Compensatory Afforestation:
1
(iv). No. of patches:
Two
District 1. : Mayurbhanj
(a). Village:
Daundia
(b). Area(in ha.):
6.07
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
38
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
District 2. : Mayurbhanj
(a). Village:
Gohira
(b). Area(in ha.):
8.9
(c). Copy of KML file of the patch:
View File
(d). Khasra details:
357,401,539
(e). Present owner:
Others
(f). Copy of ownership proof:
(g). Copy of Mou/agreement executed between the Present owner and the User Agency:
(h). Copy of non encumberence certificate for the forest land:
(v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:
(vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
M.
Hydel/Irrigation/Multipurpose Project
(i). Installed power generation capacity of the Project(in MW):
0
(ii). Total command area of the Project(in ha.):
9900
(a). Copy of the approval of competent authority to the Catchment Area Treatment Plan (CAT Plan):
(b). Copy of the approved CAT plan:
Additional information Details
Documents
S.No
Documents
Remarks
1
Clarification regarding mismatch area of KML file and Applied area
2
Clarification regarding submission of FRA certificate
3
Clarification regarding the Patch area equal to 0.00 ha in Balasore WL division
Print